no Process / Activities Equipment Energy Application

I Main Equipment
1 Production Turbine Energi kinetik
2 Production Condenser Heat Transfer
3 Production Cooling Tower Heat Transfer
II Auxiliary
1 Production Motor Pump & Fan Proses
III Fasilitas
1 Lighting Lampu Lighting
2 Office Peralatan Elektronik Proses
3 Workshop Mechanical & Electrical Equipment Mekanik, Panas, dll…
4 Emergency Emergency Diesel Generator Proses

BREAKDOWN - AUXILIARY EQUIPMENT


No Equipment Kwh
1 Motor Cooling Tower
2 Motor PACW
3 Motor SACW
4 Fan Motor Cooling Tower
5 Motor Compressor
6 Motor Hotwell Pump
7 dll…

BREAKDOWN - OFFICE EQUIPMENT


No Equipment Kwh
1 Komputer
2 AC
3 Printer
4 Kulkas
5 Dispenser
6 dll…
Energy Input Equipment Owner Source Data Energy Aspect

Steam Ophar Flow Meter Steam Drop


Cooling Water Ophar Pressure & Temp. Meter Vacuum
Cooling Water Ophar Temp. Meter Delta Temp

Electricity Ophar Kwh Meter Efisiensi Pemakaian Sendiri

Electricity Ophar Kwh Meter Efisiensi Pemakaian Sendiri


Electricity Administrasi Kwh Meter Efisiensi Pemakaian Sendiri
Electricity Ophar Kwh Meter Efisiensi Pemakaian Sendiri
Fuel Ophar Energy Bill Fuel Consumption
Existing Control for Energy
Conservation

Not Present
Not Present
Not Present

Modifikasi System

Not Present
Not Present
Not Present