Professional Documents
Culture Documents
BQ Owner Spec 3 160 Interior Finishing Add Work (Workshop) - Submit
BQ Owner Spec 3 160 Interior Finishing Add Work (Workshop) - Submit
D04 WORKSHOP
Floring work -
Wall work -
D04 Ceiling work -
Door & Windows work -
Painting work -
Canopy -
Miscellaneous work -
Floring work -
Wall work -
Ceiling work -
D05
Door & Windows work -
Painting work -
Canopy -
Toilet Cubical -
Miscellaneous work -
Client : TOKYU-WIKA JOINT OPERATION Bidding Date 24 June 2016 Prepared by Devi Yandri Date 24 June 2016
Project : JAKARTA MASS RAPID TRANSIT PROJECT (SP 2)
Additional Cost for different Quantity 21,402 m2 4,100,000,000 2.53% 191,574 Rp/sqm
Client : TOKYU-WIKA JOINT OPERATION Bidding Date 24 June 2016 Prepared by Devi Yandri Date 24 June 2016
Project : JAKARTA MASS RAPID TRANSIT PROJECT
Client : TOKYU-WIKA JOINT OPERATION Bidding Date 24 June 2016 Prepared by Devi Yandri Date 24 June 2016
Project : JAKARTA MASS RAPID TRANSIT PROJECT
Client : TOKYU-WIKA JOINT OPERATION Bidding Date 24 June 2016 Prepared by Devi Yandri Date 24 June 2016
Project : JAKARTA MASS RAPID TRANSIT PROJECT
Client : TOKYU-WIKA JOINT OPERATION Bidding Date 24 June 2016 Prepared by Devi Yandri Date 24 June 2016
Project : JAKARTA MASS RAPID TRANSIT PROJECT
No3b.3 b . Complete all plants, and buildings of depot including structural frames, foundations, exterior and interior finishes.
Note :
1 Subcontractor should be re-check the work items and its quantity
2 The Work items and its quantity only for guidance (indicative).
3 Subcontractor can revise it accordance to the tender reference drawings.
JAKARTA MASS RAPID TRANSIT PROJECT
WIKA-TOKYU JOINT OPERATION
STRUCTURE & ARCHITECTURAL WORKS FOR SUBCONTRACT PACKAGE 2 (SP 2)
SUMMARY
BLDG
Milestone No CODE DESCRIPTIONS AMOUNT (IDR) Remarks
No3b.3 b . Complete all plants, and buildings of depot including structural frames, foundations, exterior and interior finishes.
Note :
1 Subcontractor should be re-check the work items and its quantity
2 The Work items and its quantity only for guidance (indicative).
3 Subcontractor can revise it accordance to the tender reference drawings.
JAKARTA MASS RAPID TRANSIT PROJECT
WIKA-TOKYU JOINT OPERATION
STRUCTURE & ARCHITECTURAL WORKS
BILL OF QUANTITY
PACKAGE 2
Milestone
DESCRIPTIONS Qty Unit UNIT PRICE TOTAL
No.
PRELIMINARIES
1 The Contract Documents Note
The cost of making and printing copies of the Contract Documents 5 ( five ) complete
with drawings and other expenses in connection with such stamp duty etc .
2 Insurance of the Works (CAR) and Public Liability Insurance Note Exclude
3 Site Management and Establishment Costs Note
Allow for all on and off site management and establishment cost. The Subcontractor must
provide the costs incurred to conduct technical personnel and project manager in the field
who are competent , proficient, master the job and experienced that will manage the
execution of the work and take care of all matters related to its responsibilities for this
contract including all costs administration required during project implementation .
Allow for all equipment, plant, tools, materials, labour, etc. necessary for the proper
execution and protection of the Works. The Subcontractor at its own expense should
provide all the means of implementation, materials, workers , including transport to and
from the field, in and around work and other equipment needed in the implementation of
good work for temporary work , the preparatory work and the main work ( between
another is the barricade , while the lightning rod , hoist material , cargo , scaffolding lifts ,
concrete mixers , concrete pumps , generators, compressors , alarms work and others ) .
The Subcontractor shall submit in good time or provide for approval samples of
workmanship and prototypes of pavings, wall and ceiling finishes, fair faced concrete,
painting, etc., and other work where requested by the Contractor's Representative before
proceeding with the work
Should any material or article be rejected it shall be removed from the site at the
Subcontractor's expense
PACKAGE 2
Milestone
DESCRIPTIONS Qty Unit UNIT PRICE TOTAL
No.
Allow for safeguarding the Works, materials and plant against damage or theft including
providing all necessary lighting, watchmen, barriers and all safe-guards for the prevention
of site accidents and theft, and the protection of the public. Provide accommodation and
other facilities for any watchmen/security guards so required
The Subcontractor shall be solely responsible for the safety from damage or theft of all
his own materials, plant, tools and equipment .
14 Maintenance and Protection of exiting roads, footpaths, fences, etc. Note
Maintain all existing roads, footpaths, fences etc., and reinstate any damage caused by
any reason whatsoever, during the progress of the works.
15 Protection of Private and Public Services Note
Protect, uphold, upkeep and maintain all pipes, ducts, storm water drains, sewers,
electrical and telephone cables and the like during the currency of the Contract. Special
precautions shall be taken to prevent undermining of foundations to service lines, and the
Subcontractor is to make good any damage due to any cause within his control at his
own costs and expenses and pay all costs and charges in connection therewith
16 Signboard Note
The Contractor has erected temporary fencing and gates to fence off the Site from the
public. The Subcontractor shall review and adapt as necessary for his own purposes, pay
all maintenance costs and remove on completion of the Subcontract Works
The Subcontractor shall allow for providing all additional fencing and hoardings within the
site boundary as are required for the performance of Subcontract Works during the
course of the Subcontract Works
18 Progress Photographs Note
Provide for coloured photographs to show the work in progress. Digital photographs shall
be taken at monthly intervals throughout the whole of the construction period and these
will show the overall progress of the Works plus close-ups of construction works of
particular interest. An electronic copy of each photograph shall be supplied to the
Contractor's Representative. Each photograph shall be numbered, dated and annotated
to show the general details of and the positions from which they were taken
PACKAGE 2
Milestone
DESCRIPTIONS Qty Unit UNIT PRICE TOTAL
No.
The Subcontractor must carry out repairs during the maintenance period for the work that
is still lacking or defects or imperfections resulting from the use of the substance or
quality of the work that do not qualify are recorded upon delivery of the first known work
and consequently in the maintenance period. The Subcontractor shall guarantee the
Work for at least a two year period (“Defects Notification Period”) from the time of the
issuance of the Taking Over Certificate for the Works issued by the Contractor.
Provide all necessary shoring, propping, strutting, etc., whether for the support of new
work under construction or of existing buildings and existing slopes. All shoring,
propping, strutting, etc. required by the Contractor's Representative shall not be
interpreted as in any way reducing the Subcontractor's responsibility. the Contractor's
Representative may subsequently provide drawings detailing his requirements and the
Subcontractor shall construct the shoring, propping, strutting, etc. in accordance with
such drawings at no extra cost. The use of timber shoring, propping or strutting will not
be allowed unless by prior approval of the Contractor's Representative
The Subcontractor shall provide full and adequate protection for all finished surfaces and
for all materials subject to injury or staining including the work of Specialist Contractors of
the Contractor and shall be responsible for making good all damage done to such
finished surfaces and materials until the Works are handed over complete
PACKAGE 2
Milestone
DESCRIPTIONS Qty Unit UNIT PRICE TOTAL
No.
All materials shall be stored on site and in the building in a neat and orderly manner. All
rubbish, disused shoring, crates, surplus materials, etc. are to be removed from the site
or surrounding areas as soon as is possible and at least once daily during the course of
the contract so as to maintain unhindered access to and easy inspection of all work. The
Subcontractor shall provide and maintain for as long as required for the Works a
temporary external rubbish chute which shall be constructed and located to the approval
of the Contractor's Representative
34 Cleaning up Note
The Subcontractor shall on completion of the works leave all roofs throughout watertight
and clean, ease doors and windows, oil ironmongery, handover keys, cut out cracks in
plastering and make good clean all wall linings and floors, clean all glass inside and out,
touch up all painted and polished work and leave the whole of the premises and
surrounding ground clean and in good order to the satisfaction of the Contractor's
Representative
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings" and
1 Note
"subcontract documents"
The words "as described" where used in this Bill mean as described in the documents
2 Note
mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be paid as
3 Note
set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
4 Contractor shall comply with the Project Manager's instructions regarding the timing Note
and departure the site of plant and equipment and materials required for the works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such discrepancy
or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the side
8 Note
of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built into
9
the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings etc., in
the structural works, brickwork and blockwork he will be required to cut them at his
10 Note
own expense. No cutting however be carried out without the specific approval of the
Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items being
11 incorrectly positioned in the Works the Contractor shall carry out at his own expense all Note
necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves, anchors,
14 brakets, and the like sundry items supplied by the Other Contractors into concrete, Note
reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft in
17 Note
accordance with the requirements of the Direct Contractors for Lifts
3b.3.(2).2 Earth Work
3b.3.(2).2.1 Site Clearance etc.
Allow for clearing the site including breaking out existing foundations, disused sewers,
a 1 Item Include
manholes, filling in all voids with hard materials and removing all debris from site.
Allow for removing existing drain pipes, electricity cables, gas and water pipes
b 1 Item Include
encountered during excavation works.
Excavation commencing from existing level including dispose excavated soil off-site
3b.3.(2).2.2
work
a Excavate for pile cap and ground beam 260 m3 126,500 32,890,000
TOTAL Earth Work - TO FORM OF MILESTONE : 32,890,000
Supply assemble, set and install steel doors and frames finish duco, install complete
including ironmongery and all fixing accessories, all the exposed frame to primed with
3b.3.(2).3.2.4.1
approved primer, grouting the frames in water proofing cement mortar, protecting
frames and cleaning on completion, all as described;
Supply assemble, set and install glass window, 8mm thick clear glass with aluminum
3b.3.(2).3.2.4.3 extruded frame in powder coating finish, installed complete with ironmongeries, gasket,
seal, fitting and all necessary fixing accessories; al as described:
TOTAL MISCELLANEOUS WORK for Exterior Finishing Work - TO FORM OF MILESTONE : 82,827,000
Toilet Cubicle, 2100mm high, timber cubicle partition, devided into partition and door,
3b.3.(2).3.2.6.3 install complete including pedestal, ironmongery, door stopper with hook and all
necessary fixing accessories as the manufacturer's instructions
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings"
1 Note
and "subcontract documents"
The words "as described" where used in this Bill mean as described in the documents
2 Note
mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be paid
3 Note
as set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
4 Contractor shall comply with the Project Manager's instructions regarding the timing Note
and departure the site of plant and equipment and materials required for the works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such discrepancy
or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the side
8 Note
of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built into
9
the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings etc., in
the structural works, brickwork and blockwork he will be required to cut them at his
10 Note
own expense. No cutting however be carried out without the specific approval of the
Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items being
11 incorrectly positioned in the Works the Contractor shall carry out at his own expense Note
all necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves, anchors,
14 brakets, and the like sundry items supplied by the Other Contractors into concrete, Note
reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft in
17 Note
accordance with the requirements of the Direct Contractors for Lifts
3b.3.(3).2 Earth Work
3b.3.(3).2.1 Site Clearance etc.
Allow for clearing the site including breaking out existing foundations, disused sewers,
a 1 Item Include
manholes, filling in all voids with hard materials and removing all debris from site.
Allow for removing existing drain pipes, electricity cables, gas and water pipes
b 1 Item Include
encountered during excavation works.
Excavation commencing from existing level including dispose excavated soil off-site
3b.3.(3).2.2
work
a Excavate for pile cap and ground beam 333 m3 126,500 42,124,500
TOTAL Earth Work - TO FORM OF MILESTONE : 42,124,500
3b.3.(3).3.1.5 Stair
3b.3.(3).3.1.5.1 Vibrated Reinforced concrete fc' 24 N/mm2
a Stair 16 m3 1,264,100 20,225,600
3b.3.(3).3.1.5.2 Bar reinforcement; deformed high tensile steel BJTD 40
a Ditto; in stair 2,260 kg 10,600 23,956,000
3b.3.(3).3.1.5.3 Fair face finish formwork
a Stair 98 m2 217,000 21,266,000
TOTAL Stair - TO FORM OF MILESTONE : 65,447,600
3b.3.(3).3.2 ARCHITECTURAL WORK
3b.3.(3).3.2.1 FLOORING WORK
3b.3.(3).3.2.1.1 Exterior Finishing Work
Supply and install homogenous/ceramic tile, laid on screed bedded and jointed in
3b.3.(3).3.2.1.1.1 instant cement ex. Mortar Utama or equal, pointed in coloured grouting ex. AM or
equal as described to:
a F1A, HT 600x600mm Unpolished 60 m2 485,500 29,130,000
3b.3.(3).3.2.1.1.2 Sundries
a F11, Asphalt waterproof 531 m2 259,200 137,635,200
TOTAL Flooring- Extterior Work - TO FORM OF MILESTONE : 166,765,200
3b.3.(3).3.2.1.2 Interior Finishing Work
Waterproofing coating system as specified, applied strictly in accordance with the
3b.3.(3).3.2.1.2.1
manufacturer's instruction, all as described to:
Supply and install homogenous/ceramic tile, laid on screed bedded and jointed in
3b.3.(3).3.2.1.2.2 instant cement ex. Mortar Utama or equal, pointed in coloured grouting ex. AM or
equal as described to:
a F1, HT 600x600mm Polished 51 m2 485,500 24,760,500
b F2, HT 400x400mm 281 m2 375,700 105,571,700
c F3, CT 200x200mm 76 m2 258,600 19,653,600
Floor Hardener Non-metalic 3 kg/m2 complete including cement mortar screeding and
3b.3.(3).3.2.1.2.3
50mm thick topping concrete all as described to:
a F8 42 m2 32,900 1,381,800
3b.3.(3).3.2.1.2.4 Sundries
a F11, Asphalt waterproof 76 m2 98,700 7,501,200
b F12, Lightweigt concrete with trench 11 m2 171,100 1,882,100
c F13, Carpet tile 354 m2 592,100 209,603,400
TOTAL Flooring- Interior Work - TO FORM OF MILESTONE : 370,354,300
3b.3.(3).3.2.2 WALLING WORK
3b.3.(3).3.2.2.1 Exterior Finishing Work
Block wall in dry mix mortar system, complete with reinforcement, lintels, stiffeners,
3b.3.(3).3.2.2.1.1
anchorage, latching and accessories as described
a 200mm thick 832 m2 372,400 309,836,800
3b.3.(3).3.2.2.1.2 Plaster trowelled smooth in dry mix mortar system as described
a General 832 m2 63,200 52,582,400
Supply and install homogenous/ceramic tile, laid on screed bedded and jointed in
3b.3.(3).3.2.2.1.3 instant cement ex. Mortar Utama or equal, pointed in coloured grouting ex. AM or
equal as described to:
a External wall tile 160 m2 277,000 44,320,000
TOTAL Walling - Exterior Work - TO FORM OF MILESTONE : 406,739,200
3b.3.(3).3.2.2.2 Interior Finishing Work
Block wall in dry mix mortar system, complete with reinforcement, lintels, stiffeners,
3b.3.(3).3.2.2.2.1
anchorage, latching and accessories as described
a 200mm thick 1,176 m2 372,400 437,942,400
b 100mm thick - m2 186,200 -
c Gypsum board 12mm thick 379 m2 263,200 99,752,800
3b.3.(3).3.2.2.2.2 Plaster trowelled smooth in dry mix mortar system as described
a General 2,440 m2 63,200 154,208,000
Supply and install homogenous/ceramic tile, laid on screed bedded and jointed in
3b.3.(3).3.3.3 instant cement ex. Mortar Utama or equal, pointed in coloured grouting ex. AM or
equal as described to:
Note: 3.2 m height from floor level
a W4, CT 200x200mm 295 m2 277,000 81,715,000
TOTAL Walling - Interior Work - TO FORM OF MILESTONE : 773,618,200
3b.3.(3).3.2.3 CEILING WORK \
Supply and install suspended ceiling framing with metal furring and C channel fixed to
concrete soffit consist with 5 mm diameter galvanized steel including wall trim, fixed
3b.3.(3).3.2.3.1
with scrimped and flush joint, including forming holes and additional framing for ME
fitting, all as described;
a Gypsum board 12mm thick 698 m2 263,200 183,713,600
b Silicate Calcium board 6mm thick 75 m2 204,300 15,322,500
c Cement plaster to exposed concrete ceiling 148 m2 38,100 5,638,800
d Cornice - m - -
TOTAL Ceiling Work - TO FORM OF MILESTONE : 204,674,900
Supply assemble, set and install steel doors and frames finish duco, install complete
including ironmongery and all fixing accessories, all the exposed frame to primed with
3b.3.(3).3.2.4.1
approved primer, grouting the frames in water proofing cement mortar, protecting
frames and cleaning on completion, all as described;
Supply assemble, set and install glass window, 8mm thick clear glass with aluminum
3b.3.(3).3.2.4.2 extruded frame in powder coating finish, installed complete with ironmongeries,
gasket, seal, fitting and all necessary fixing accessories; al as described:
Toilet Cubicle, 2100mm high, timber cubicle partition, devided into partition and door,
3b.3.(3).3.2.6.2.3 install complete including pedestal, ironmongery, door stopper with hook and all
necessary fixing accessories as the manufacturer's instructions
Client : TOKYU-WIKA JOINT OPERATION Bidding Date 31 July 2017 Prepared by Devi Yandri Date 31 July 2017
Project : JAKARTA MASS RAPID TRANSIT PROJECT (SP 2)
Dear Sir,
Referring to your requirements, we are pleased to submit our rough cost estimation base on Technical Drawing as follow :
NOTE : This is to inform you that we reserve our right to claim TOTAL 4,357,700,402
an extention of time on this additional work. ROUNDED 4,357,700,000
Sinceraly yours
PT. TOKYU CONSTRUCTION INDONESIA
KOJI KOIKE
Project Manager
Wisma HAKA 2nd Floor Jl. KH. Wahid Hasyim No. 71 Jakarta-INDONESIA, 10350
Phone +6221 3147613 (Hunting) | Fax +6221 3147620 | E-mail: jakarta@tokyucnst-id.com
BREAK DOWN
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 -WORKSHOP BUILDING
Milestone No. DESCRIPTIONS Unit UNIT PRICE TOTAL Unit UNIT PRICE TOTAL Unit UNIT PRICE TOTAL
ARCHITECTURE WORK
3b.3.(4) - WORKSHOP
BILL OF QUANTITY NEW QUOTATION BALANCE
Milestone No. DESCRIPTIONS Unit UNIT PRICE TOTAL Unit UNIT PRICE TOTAL Unit UNIT PRICE TOTAL
3b.3.(4) - WORKSHOP
BILL OF QUANTITY NEW QUOTATION BALANCE
Milestone No. DESCRIPTIONS Unit UNIT PRICE TOTAL Unit UNIT PRICE TOTAL Unit UNIT PRICE TOTAL
Supply assemble, set and install steel doors and frames finish duco, install complete
including ironmongery and all fixing accessories, all the exposed frame to primed with
3b.3.(5).3.3.4.1
approved primer, grouting the frames in water proofing cement mortar, protecting
frames and cleaning on completion, all as described;
a SD-1, overall 750x2200 mm, non fire rated 2 No 13,813,800 27,627,600 2 No 13,813,800 27,627,600 - No 13,813,800 0
b SD-1, overall 850x2200 mm, non fire rated 1 No 13,813,800 13,813,800 - No 13,813,800 - (1) No 13,813,800 (13,813,800)
c SD-1, overall 800x2200 mm, non fire rated 9 No 13,813,800 124,324,200 21 No 13,813,800 290,089,800 12 No 13,813,800 165,765,600
d SD-3, overall 800x2200 mm, non fire rated 5 No 13,813,800 69,069,000 5 No 13,813,800 69,069,000 - No 13,813,800 0
e SD-3, overall 750x2200 mm, non fire rated 1 No 13,813,800 13,813,800 2 No 13,813,800 27,627,600 1 No 13,813,800 13,813,800
f SD-5, overall 1200x2200 mm, non fire rated 3 No 26,048,900 78,146,700 - No 26,048,900 - (3) No 26,048,900 (78,146,700)
g SD-5, overall 1200x2400 mm, non fire rated 1 No 26,048,900 26,048,900 4 No 26,048,900 104,195,600 3 No 26,048,900 78,146,700
h SD-5, overall 1300x2400 mm, non fire rated 1 No 26,048,900 26,048,900 1 No 26,048,900 26,048,900 - No 26,048,900 0
i SD-5, overall 1350x2400 mm, non fire rated 1 No 26,048,900 26,048,900 - No 26,048,900 - (1) No 26,048,900 (26,048,900)
j SD-5, overall 1500x2200 mm, non fire rated 4 No 26,048,900 104,195,600 5 No 26,048,900 130,244,500 1 No 26,048,900 26,048,900
k GL-1, overall 1500x2400 mm, non fire rated 1 No 26,048,900 26,048,900 1 No 26,048,900 26,048,900 - No 26,048,900 0
New Item SD-1, overall 650x2200 mm, non fire rated - No 13,813,800 - 1 No 13,813,800 13,813,800 1 No 13,813,800 13,813,800
New Item SD-5, overall 4200x6000 mm, non fire rated - No 82,882,800 - 1 No 82,882,800 82,882,800 1 No 82,882,800 82,882,800
New Item SSD-1, overall 3000x3000 mm, non fire rated - No 29,601,000 - 4 No 29,601,000 118,404,000 4 No 29,601,000 118,404,000
New Item SD-8, overall 1300x2200 mm, non fire rated - No 26,048,900 - 1 No 26,048,900 26,048,900 1 No 26,048,900 26,048,900
3b.3.(5).3.3.4.2 Roller Shutter Door
a : SHS, overall 4200 x 3000 mm 2 No 45,401,400 90,802,800 2 No 45,401,400 90,802,800 - No 45,401,400 0
b : SHS, overall 4200 x 6100 mm 2 No 72,352,800 144,705,600 2 No 72,352,800 144,705,600 - No 72,352,800 -
c : SHS, overall 3200 x 3000 mm 3 No 40,106,100 120,318,300 3 No 40,106,100 120,318,300 - No 40,106,100 -
d : SHS, overall 5050 x 3000 mm 1 No 57,011,600 57,011,600 1 No 57,011,600 57,011,600 - No 57,011,600 -
e : SHS, overall 5200 x 3000 mm 1 No 57,011,600 57,011,600 - No 57,011,600 - (1) No 57,011,600 (57,011,600)
Supply assemble, set and install glass window, 8mm thick clear glass with aluminum
3b.3.(5).3.3.4.3 extruded frame in powder coating finish, installed complete with ironmongeries,
gasket, seal, fitting and all necessary fixing accessories; al as described:
a : Overall 1450 mm x 1800 mm 244 No 6,867,500 1,675,670,000 - No 6,867,500 - (244) No 6,867,500 (1,675,670,000)
b : Overall 60000 mm x 1800 mm 2 No 312,586,600 625,173,200 2 No 312,586,600 625,173,200 - No 312,586,600 -
c : Overall size 1500mm x 1700mm, with louver 500mm high 7 No 8,051,500 56,360,500 - No 8,051,500 - (7) No 8,051,500 (56,360,500)
d : Overall size 3000mm x 1700mm, with louver 500mm high 3 No 16,103,000 48,309,000 - No 16,103,000 - (3) No 16,103,000 (48,309,000)
e : Overall size 4500mm x 1700mm, with louver 500mm high 1 No 24,154,500 24,154,500 - No 24,154,500 - (1) No 24,154,500 (24,154,500)
f : Overall size 6000mm x 1700mm, with louver 500mm high 1 No 32,205,900 32,205,900 - No 32,205,900 - (1) No 32,205,900 (32,205,900)
g : Overall size 7450mm x 1700mm, with louver 500mm high 2 No 39,989,000 79,978,000 - No 39,989,000 - (2) No 39,989,000 (79,978,000)
h : Overall size 9000mm x 1700mm, with louver 500mm high 27 No 48,308,900 1,304,340,300 - No 48,308,900 - (27) No 48,308,900 (1,304,340,300)
i : Overall size 12000mm x 1700mm, with louver 500mm high 1 No 64,411,800 64,411,800 - No 64,411,800 - (1) No 64,411,800 (64,411,800)
New Item : Overall size 1600mm x 2450mm, with louver 1200mm high - No 12,377,200 - 9 No 12,377,200 111,394,800 9 No 12,377,200 111,394,800
New Item : Overall size 3100mm x 2450mm, with louver 1200mm high - No 23,980,800 - 2 No 23,980,800 47,961,600 2 No 23,980,800 47,961,600
New Item : Overall size 4600mm x 2450mm, with louver 1200mm high - No 35,584,400 - 1 No 35,584,400 35,584,400 1 No 35,584,400 35,584,400
New Item : Overall size 6200mm x 2450mm, with louver 1200mm high - No 47,961,600 - 2 No 47,961,600 95,923,200 2 No 47,961,600 95,923,200
New Item : Overall size 7550mm x 2450mm, with louver 1200mm high - No 58,404,800 - 4 No 58,404,800 233,619,200 4 No 58,404,800 233,619,200
New Item : Overall size 9100mm x 2450mm, with louver 1200mm high - No 70,395,200 - 21 No 70,395,200 1,478,299,200 21 No 70,395,200 1,478,299,200
New Item : Overall size 9100mm x 2550mm, with louver 2000mm high - No 73,268,400 - 32 No 73,268,400 2,344,588,800 32 No 73,268,400 2,344,588,800
New Item : Louver size 1000mm x 600mm high - No 1,184,100 - 2 No 1,184,100 2,368,200 2 No 1,184,100 2,368,200
New Item : Louver size 1000mm x 1000mm high - No 1,973,400 - 2 No 1,973,400 3,946,800 2 No 1,973,400 3,946,800
New Item : Louver size 1000mm x 1200mm high - No 2,368,100 - 1 No 2,368,100 2,368,100 1 No 2,368,100 2,368,100
3b.3.(4) - WORKSHOP
BILL OF QUANTITY NEW QUOTATION BALANCE
Milestone No. DESCRIPTIONS Unit UNIT PRICE TOTAL Unit UNIT PRICE TOTAL Unit UNIT PRICE TOTAL
c Maintenance Deck with Railing; 800mm 320 m 1,315,600 420,992,000 320 m 1,315,600 420,992,000 - m 1,315,600 0
d : Canopy 1200mm x 1000mm 1 No 1,894,500 1,894,500 - No 1,894,500 - (1) No 1,894,500 (1,894,500)
e : Canopy 1550mm x 1000mm 4 No 2,447,100 9,788,400 7 No 2,447,100 17,129,700 3 No 2,447,100 7,341,300
f : Canopy 1900mm x 1000mm 1 No 2,999,600 2,999,600 - No 2,999,600 - (1) No 2,999,600 (2,999,600)
g : Canopy 2000mm x 1000mm 1 No 3,157,500 3,157,500 4 No 3,157,500 12,630,000 3 No 3,157,500 9,472,500
h : Canopy 2300mm x 1000mm 1 No 3,631,100 3,631,100 - No 3,631,100 - (1) No 3,631,100 (3,631,100)
i : Canopy 3400mm x 1000mm 1 No 5,367,700 5,367,700 3 No 5,367,700 16,103,100 2 No 5,367,700 10,735,400
j : Canopy 4400mm x 1000mm 1 No 6,946,400 6,946,400 1 No 6,946,400 6,946,400 - No 6,946,400 0
k : Canopy 5250mm x 1000mm 1 No 8,288,300 8,288,300 2 No 8,288,300 16,576,600 1 No 8,288,300 8,288,300
l : Canopy 5400mm x 1000mm 1 No 8,525,100 8,525,100 1 No 8,525,100 8,525,100 - No 8,525,100 0
m : Canopy 24700mm x 1000mm 1 No 38,994,400 38,994,400 - No 38,994,400 - (1) No 38,994,400 (38,994,400)
New Item : Canopy 24700mm x 3500mm - No 136,480,400 - 1 No 136,480,400 136,480,400 1 No 136,480,400 136,480,400
FINISHING WORK
FLOOR WALL CEILING PAINTING DOOR WINDOWS WINDOWS + LOUVER
No. ROOM NAME M2 SHS SD1 SD1 SD3
Ceramic Ceramic Ceramic Silicate SHS SHS SHS SD1 SD3 SD5 SD5 SD5 SD5 SD8 SSD1 GL1 Cubicle w=60.0 w=1.6 w=3.1 w=4.6 w=6.2 w=7.55 w=9.1 w=9.1 w=1.0 w=1.0 w=1.0
Hardener Waterproof Brick Plaster Gypsum Wall Ceiling (5.05x3.0 (0.65x2.2 (0.75x2.2 (0.75x2.2
40 x 40 20 x 20 20 x 20 Calcium (4.2x3.0) (4.2x6) (3.2x3.0) (0.8x2.2) (0.8x2.2) (1.2x2.4) (1.3x2.4) (1.5x2.2) (4.2x6) (1.3x2.2) (3x3) (1.5x2.4) (0.8x2.2) h=1.8 h=2.45 h=2.45 h=2.45 h=2.45 h=2.45 h=2.45 h=2.55 h=0.6 h=1.0 h=1.2
) ) ) )
1st Floor
1 RESTING ROOM 01 50.00 50.00 127.40 312.40 50.00 312.40 50.00 1.00 2.00
2 RESTING ROOM 02 30.00 30.00 96.00 207.00 30.00 207.00 30.00 1.00 2.00
3 LOCKER ROOM (M) 31.50 31.50 78.50 207.50 31.50 207.50 31.50 1.00 1.00 1.00 1.00
4 TOILET 01 (M) 16.50 16.50 16.50 92.00 118.00 72.10 16.50 45.90 16.50 1.00 3.00
5 SHOWER ROOM (M) 24.00 24.00 24.00 98.60 278.80 107.68 24.00 171.12 24.00 2.00 10.00
6 TOILET 01 (F) 17.50 17.50 17.50 84.00 126.00 76.10 17.50 49.90 17.50 1.00 2.00
7 SHOWER ROOM 01 (F) 14.00 14.00 14.00 60.50 117.50 73.50 14.00 44.00 14.00 1.00 4.00
8 STAFF KITCHEN 10.24 10.24 57.60 76.80 10.24 76.80 10.24 1.00
9 LOCKER ROOM (F) 27.60 27.60 99.30 167.70 27.60 167.70 27.60 1.00
10 PRAY ROOM 20.00 20.00 54.00 128.00 20.00 128.00 20.00 1.00 1.00
11 CORRIDOR 1 43.47 43.47 37.25 276.95 43.47 276.95 43.47 1.00 1.00
12 AIR SOURCE ROOM 114.00 114.00 201.00 376.75 114.00 376.75 114.00 1.00 1.00 2.00
13 SUBSTATION, 258.00 258.00 427.50 1108.45 258.00 1108.45 258.00 3.00 2.00
14 BOILER ROOM 66.00 66.00 105.00 278.75 66.00 278.75 66.00 1.00 1.00 1.00
15 ELECTRIC EQUIPMENT 270.00 270.00 213.00 411.00 0.00 411.00 0.00 1.00 1.00 1.00 1.00
16 TOILET 02 (F) 20.40 20.40 20.40 118.40 142.40 80.68 20.40 61.72 20.40 1.00 3.00
17 TOILET 02 (M) 24.90 24.90 24.90 119.30 177.10 100.48 24.90 76.62 24.90 1.00 3.00
18 BATTERY CHARGING 61.20 61.20 117.00 239.40 61.20 239.40 61.20 1.00 1.00
19 VALVE SHOP 198.00 198.00 197.40 445.80 198.00 445.80 198.00 1.00 1.00 2.00
20 BEARING SHOP 125.00 125.00 212.50 473.75 125.00 473.75 125.00 2.00 1.00 1.00
21 CLIMATE CONTROL 56.00 56.00 198.00 954.00 56.00 954.00 56.00 1.00
22 STORAGE OFFICE 24.00 24.00 144.00 180.00 24.00 180.00 24.00 1.00
23 WAREHOUSE 290.00 290.00 310.50 758.75 758.75 1.00 1.00 1.00 1.00
24 ENTRANCE HALL 10.00 10.00 0.00 133.25 10.00 133.25 10.00 1.00
25 COORIDOR 02 90.00 90.00 0.00 327.00 327.00 1.00 1.00
26 INSPECTION SHOP 1312.00 1312.00 768.00 2991.40 2991.40 3.00 1.00 1.00 2.00 3.00 13.00 16.00
27 WORKSHOP 6830.50 6830.50 0.00 2949.40 2949.40 2.00 1.00 1.00 3.00 2.00 1.00 6.00 16.00 1.00
2nd Floor
28 INSPECTION ROOM 24.00 24.00 124.80 249.60 24.00 249.60 24.00 1.00 2.00 1.00
TOTAL 10,058.81 9,694.70 246.81 117.30 117.30 4,141.55 14,213.45 510.54 1,149.01 117.30 13,702.91 1,266.31 2.00 2.00 3.00 1.00 1.00 2.00 21.00 5.00 2.00 4.00 1.00 5.00 1.00 1.00 4.00 1.00 25.00 2.00 9.00 2.00 1.00 2.00 4.00 21.00 32.00 2.00 2.00 1.00
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
1 RESTING ROOM 01 Flooring: 50.00 m2
a= 5000 Cramic 400 x 400 5.00 10.00 1.00 50.00
Wall : 127.40 m2
b2 = 7400
a 5.00 6.00 1.00 30.00
10000
10000
b1 2.60 6.00 1.00 15.60
b2 7.40 7.00 1.00 51.80
b=
d=
b1 = 2600
d - - - - - exterior
Ceiling: 50.00 m2
Gypsum 5.00 10.00 1.00 50.00
Painting: 362.40 m2
Wall EP 312.40
Ceiling EP 50.00
Wall : 96.00 m2
a 5.00 6.00 1.00 30.00
b = 6000
d= 6000
Ceiling: 30.00 m2
Gypsum 5.00 6.00 1.00 30.00
Painting: 237.00 m2
Wall EP 207.00
Ceiling EP 30.00
Page : 34
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
Wall : 78.50 m2
a 9.00 6.00 1.00 54.00
b = 3500
d= 3500
b 3.50 7.00 1.00 24.50
c - - - - - exterior
d 0.00 6.00 1.00 0.00
Ceiling: 31.50 m2
Gypsum 9.00 3.50 1.00 31.50
Painting: 239.00 m2
Wall EP 207.50
Ceiling EP 31.50
Waterproofing: 16.50 m2
a= 3000 3.00 5.50 1.00 16.50
d1= 2000
Wall : 92.00 m2
a 3.00 6.00 1.00 18.00
b = 5500
d= 5500
Ceiling: 16.50 m2
Silicate Calcium 3.00 5.50 1.00 16.50
Painting: 62.40 m2
Wall EP 45.90
Ceiling EP 16.50
Page : 35
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
5 SHOWER ROOM (M) Flooring: 24.00 m2
Cramic 200 x 200 5.00 4.80 1.00 24.00
Waterproofing: 24.00 m2
a= 5000 5.00 4.80 1.00 24.00
d2= 2000
Wall : 98.60 m2
a 5.00 6.00 1.00 30.00
b = 4800
d3= 4800
b 4.80 7.00 1.00 33.60
c - - - - - Inc. (3)
d1= 1500
d1 1.50 2.00 5.00 15.00
d2 2.00 2.00 5.00 20.00
d3 - - - - - Inc. (4)
Ceiling: 24.00 m2
Silicate Calcium 5.00 4.80 1.00 24.00
Painting: 195.12 m2
Wall EP 171.12
Ceiling EP 24.00
Waterproofing: 17.50 m2
a= 5000 5.00 3.50 1.00 17.50
Wall : 84.00 m2
a 5.00 6.00 1.00 30.00
b = 3500
3500
c Inc. (4,5)
d=
- - - - -
d 3.50 6.00 1.00 21.00
d1 2.00 2.00 3.00 12.00
Ceiling: 17.50 m2
Silicate Calcium 5.00 3.50 1.00 17.50
Painting: 67.40 m2
Wall EP 49.90
Ceiling EP 17.50
Page : 36
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
7 SHOWER ROOM 01 (F) Flooring: 14.00 m2
Cramic 200 x 200 4.00 3.50 1.00 14.00
Waterproofing: 14.00 m2
a= 4000 4.00 3.50 1.00 14.00
Wall : 60.50 m2
a 4.00 6.00 1.00 24.00
b = 3500
3500
b 3.50 7.00 1.00 24.50
d1= 2000
c Inc. (5)
d=
- - - - -
d - - - - - Inc. (6)
d1 2.00 2.00 3.00 12.00
Ceiling: 14.00 m2
Silicate Calcium 4.00 3.50 1.00 14.00
Painting: 58.00 m2
Wall EP 44.00
Ceiling EP 14.00
Wall : 57.60 m2
a 3.20 6.00 1.00 19.20
b = 3200
d= 3200
Ceiling: 10.24 m2
Gypsum 3.20 3.20 1.00 10.24
Painting: 87.04 m2
Wall EP 76.80
Ceiling EP 10.24
Page : 37
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
9 LOCKER ROOM (F) Flooring: 27.60 m2
a= 8900 Cramic 400 x 400 8.90 1.50 1.00 13.35
5.70 2.50 1.00 14.25
d2= 1500
Wall : 99.30 m2
a 8.90 7.00 1.00 62.30
b = 4000
2500
c1 - - - - - Inc. (6,7)
c2 - - - - - Inc. (8)
d1 Inc. (8)
d1=
- - - - -
d2 1.50 6.00 1.00 9.00
c1= 5700 c2= 3200
Plaster: 167.70 m2
a 8.90 7.00 1.00 62.30
b 4.00 7.00 1.00 28.00
c1 5.70 6.00 1.00 34.20
c2 3.20 6.00 1.00 19.20
d1 2.50 6.00 1.00 15.00
d2 1.50 6.00 1.00 9.00
Ceiling: 27.60 m2
Gypsum 8.90 1.50 1.00 13.35
5.70 2.50 1.00 14.25
Painting: 195.30 m2
Wall EP 167.70
Ceiling EP 27.60
Wall : 54.00 m2
a - - - - - Inc. (2)
b = 4000
d= 4000
Ceiling: 20.00 m2
Gypsum 5.00 4.00 1.00 20.00
Painting: 148.00 m2
Wall EP 128.00
Ceiling EP 20.00
Page : 38
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
11 CORRIDOR 1 Flooring: 43.47 m2
a1= 2150 a2= 2450 Cramic 400 x 400 2.15 12.30 1.00 26.45
4.60 3.70 1.00 17.02
12300
Wall : 37.25 m2
b = 16000
a1
d2=
2.15 7.00 1.00 15.05
a2 - - - - - Inc. (10)
d1= 3700
b - - - - - Inc. (4,6,8)
c - - - - - exterior
d1 3.70 6.00 1.00 22.20
c= 4600 d2 - - - - - Inc. (1,2,10)
Plaster: 276.95 m2
a1 2.15 7.00 1.00 15.05
a2 2.45 6.00 1.00 14.70
b 16.00 6.00 1.00 96.00
c 4.60 12.00 1.00 55.20
d1 3.70 6.00 1.00 22.20
d2 12.30 6.00 1.00 73.80
Ceiling: 43.47 m2
Gypsum 2.15 12.30 1.00 26.45
4.60 3.70 1.00 17.02
Painting: 320.42 m2
Wall EP 276.95
Ceiling EP 43.47
Wall : 201.00 m2
a 12.00 6.00 1.00 72.00
b = 9500
d= 9500
b - - - - - exterior
c 12.00 6.00 1.00 72.00
d 9.50 6.00 1.00 57.00
Ceiling: 114.00 m2
Gypsum 12.00 9.50 1.00 114.00
Painting: 490.75 m2
Wall EP 376.75
Ceiling EP 114.00
Page : 39
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
13 SUBSTATION, Flooring: 258.00 m2
TRANSFORMER ROOM a= 12000 Floor Hardener 12.00 21.50 1.00 258.00
12000
18900
Wall : 427.50 m2
b = 21500
d1=
d3=
12.00 7.00 1.00 84.00
b - - - - - exterior
d2= 2600
c1 6.00 6.00 3.00 108.00
c2 2.60 6.00 1.00 15.60
c1= 6000 c2= 2600 c3 - - - - - Inc. (12)
c3= 12000 d1 12.00 6.00 1.00 72.00
d2 2.60 6.00 1.00 15.60
d3 18.90 7.00 1.00 132.30
Plaster: 1108.45 m2
a 12.00 7.00 1.00 84.00
b 21.50 18.50 1.00 397.75
c1 6.00 6.00 6.00 216.00
c2 2.60 6.00 2.00 31.20
c3 12.00 6.00 1.00 72.00
d1 12.00 6.00 2.00 144.00
d2 2.60 6.00 2.00 31.20
d3 18.90 7.00 1.00 132.30
Ceiling: 258.00 m2
Gypsum 12.00 21.50 1.00 258.00
0.00 2.60 1.00 0.00
Painting: 1366.45 m2
Wall EP 1108.45
Ceiling EP 258.00
Wall : 105.00 m2
a - - - - - Inc. (12)
b = 5500
d= 5500
b - - - - - exterior
c 12.00 6.00 1.00 72.00
d 5.50 6.00 1.00 33.00
Ceiling: 66.00 m2
Gypsum 12.00 5.50 1.00 66.00
Painting: 344.75 m2
Wall EP 278.75
Ceiling EP 66.00
Page : 40
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
15 ELECTRIC EQUIPMENT Flooring: 270.00 m2
SHOP a= 18000 Floor Hardener 18.00 15.00 1.00 270.00
Wall : 213.00 m2
d= 15000
b= 15000
Ceiling: 0.00 m2
Gypsum 0.00 15.00 1.00 0.00
Painting: 411.00 m2
Wall EP 411.00
Ceiling EP 0.00
Waterproofing: 20.40 m2
a= 6800 6.80 3.00 1.00 20.40
Wall : 118.40 m2
a 6.80 7.00 1.00 47.60
b = 3000
d= 3000
b - - - - - Inc. (17)
c 6.80 6.00 1.00 40.80
c1 2.00 6.00 2.00 24.00
d 3.00 2.00 1.00 6.00
c1= 2000
c= 6800 Plaster: 142.40 m2
a 6.80 7.00 1.00 47.60
b 3.00 0.00 1.00 0.00
c 6.80 6.00 1.00 40.80
c1 2.00 6.00 4.00 48.00
d 3.00 2.00 1.00 6.00
Ceiling: 20.40 m2
Silicate Calcium 6.80 3.00 1.00 20.40
Painting: 82.12 m2
Wall EP 61.72
Ceiling EP 20.40
Page : 41
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
17 TOILET 02 (M) Flooring: 24.90 m2
Cramic 200 x 200 1.50 3.00 1.00 4.50
a= 6800 6.80 3.00 1.00 20.40
d2= 3000
1.50 3.00 1.00 4.50
6.80 3.00 1.00 20.40
b = 6000
Wall : 119.30 m2
d1= 3000
a1 1.50 7.00 1.00 10.50
a2 - - - - - Inc. (16)
b 6.00 7.00 1.00 42.00
c1= 2000 c 6.80 6.00 1.00 40.80
c= 6800 c1 2.00 2.00 2.00 8.00
d1 3.00 6.00 1.00 18.00
d2 - - - - - Inc. (16)
Plaster: 177.10 m2
a1 1.50 7.00 1.00 10.50
a2 5.30 6.00 1.00 31.80
b 6.00 7.00 1.00 42.00
c 6.80 6.00 1.00 40.80
c1 2.00 2.00 4.00 16.00
d1 3.00 6.00 1.00 18.00
d2 3.00 6.00 1.00 18.00
Ceiling: 24.90 m2
Silicate Calcium 1.50 3.00 1.00 4.50
6.80 3.00 1.00 20.40
Painting: 101.52 m2
Wall EP 76.62
Ceiling EP 24.90
Wall : 117.00 m2
a - - - - - Inc. (17)
b = 9000
d= 9000
Ceiling: 61.20 m2
Gypsum 6.80 9.00 1.00 61.20
Painting: 300.60 m2
Wall EP 239.40
Ceiling EP 61.20
Page : 42
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
19 VALVE SHOP Flooring: 198.00 m2
a= 13200 Floor Hardener 13.20 15.00 1.00 198.00
Wall : 197.40 m2
a 13.20 7.00 1.00 92.40
b = 15000
d= 15000
b - - - - - Inc. (16,17,18)
c - - - - - exterior
d 15.00 7.00 1.00 105.00
Ceiling: 198.00 m2
Gypsum 13.20 15.00 1.00 198.00
Painting: 643.80 m2
Wall EP 445.80
Ceiling EP 198.00
Wall : 212.50 m2
a 10.00 9.00 1.00 90.00
b = 12500
d= 12500
Ceiling: 125.00 m2
Gypsum 10.00 12.50 1.00 125.00
Painting: 598.75 m2
Wall EP 473.75
Ceiling EP 125.00
Page : 43
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
21 CLIMATE CONTROL Flooring: 56.00 m2
STORAGE a= 14000 Floor Hardener 14.00 4.00 1.00 56.00
Wall : 198.00 m2
a 14.00 9.00 1.00 126.00
b = 4000
4000
b 4.00 9.00 1.00 36.00
c1 4.00 9.00 1.00 36.00
d=
c2 - - - - - Inc. (20)
d - - - - - exterior
Ceiling: 56.00 m2
Gypsum 14.00 4.00 1.00 56.00
Painting: 1010.00 m2
Wall EP 954.00
Ceiling 56.00
Wall : 144.00 m2
a 6.00 9.00 1.00 54.00
b = 4000
4000
d - - - - - Inc. (21)
Plaster: 180.00 m2
c= 6000 a 6.00 9.00 1.00 54.00
b 4.00 9.00 1.00 36.00
c 6.00 9.00 1.00 54.00
d 4.00 9.00 1.00 36.00
Ceiling: 24.00 m2
Gypsum 6.00 4.00 1.00 24.00
Painting: 204.00 m2
Wall EP 180.00
Ceiling 24.00
Wall : 310.50 m2
a 20.00 9.00 1.00 180.00
b = 14500
14500
b
14.50 9.00 1.00 130.50
c - - - - - Inc. (21,22)
d=
d - - - - - exterior
Plaster: 758.75 m2
c= 20000 a 20.00 9.00 1.00 180.00
b 14.50 9.00 1.00 130.50
c 20.00 9.00 1.00 180.00
d 14.50 18.50 1.00 268.25
Painting: 758.75 m2
Wall EP 758.75
Page : 44
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
24 ENTRANCE HALL Flooring: 10.00 m2
a= 2500 Cramic 400 x 400 2.50 4.00 1.00 10.00
Wall : 0.00 m2
a - - - - - Inc. (10)
b = 4000
d= 4000
b - - - - - Inc. (11)
c - - - - - exterior
d - - - - - exterior
Ceiling: 10.00 m2
Gypsum 2.50 4.00 1.00 10.00
Painting: 143.25 m2
Wall EP 133.25
Ceiling EP 10.00
Wall : 0.00 m2
a - - - - -
b = 15000
d= 15000
b - - - - - Inc. (15)
c - - - - - Inc. (17,18)
d - - - - - exterior
Painting: 327.00 m2
Wall EP 327.00
Wall : 768.00 m2
b = 8200
d= 8200
a - - - - - exterior
b - - - - - exterior
c1 10.00 4.80 1.00 48.00
c1= 10000 c2= 150000 c2 150.00 4.80 1.00 720.00
d - - - - - exterior
Plaster: 2991.40 m2
a 160.00 12.00 1.00 1920.00
b 8.20 18.50 1.00 151.70
c1 10.00 4.80 1.00 48.00
c2 150.00 4.80 1.00 720.00
d 8.20 18.50 1.00 151.70
Painting: 2991.40 m2
Wall EP 2991.40
Page : 45
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
27 WORKSHOP a= 140000 Flooring: 6830.50 m2
a1= 10000 a2= 120000 Floor Hardener 140.00 18.50 1.00 2590.00
44.00 21.80 1.00 959.20
b 1= 18500
18500
88.00 15.00 1.00 1320.00
7400
10.00 12.50 1.00 125.00
b2= 21800
d4=
c1= 12000
b3 = 15000
Plaster: 2949.40 m2
a1 10.00 4.80 1.00 48.00
a2 120.00 4.80 1.00 576.00
b1 18.50 1.00 0.00
b2 21.80 7.00 1.00 152.60
b3 15.00 7.00 1.00 105.00
c1 12.00 7.00 1.00 84.00
c2 44.00 7.00 1.00 308.00
c3 10.00 9.00 1.00 90.00
c4 5.00 7.00 1.00 35.00
c5 11.00 7.00 1.00 77.00
c6 88.00 12.00 1.00 1056.00
d1 18.50 9.00 1.00 166.50
d2 16.00 7.00 1.00 112.00
d3 12.50 7.00 1.00 87.50
d4 7.40 7.00 1.00 51.80
Painting: 2949.40 m2
Wall EP 2949.40
Page : 46
FINISHING WORK
OWNER : TWJO
PROJECT : MRT CP 101-SP 02
BUILDING AREA : D04 - WORKSHOP BUILDING
No. ROOM DESCRIPTION FINISHING LENGTH WIDTH HEIGHT NOS VOLUME TOTAL VOLUME UNIT REMARKS
28 INSPECTION ROOM Flooring: 24.00 m2
2nd a= 12000 Cramic 400 x 400 12.00 2.00 1.00 24.00
Wall : 124.80 m2
a 12.00 4.00 1.00 48.00
b = 2000
d= 2000
b 2.00 4.00 1.00 8.00
b1 1.20 4.00 1.00 4.80
b1 = 1200
Plaster: 249.60 m2
a 12.00 4.00 2.00 96.00
b 2.00 4.00 2.00 16.00
b1 1.20 4.00 2.00 9.60
c 12.00 4.00 2.00 96.00
c1 2.00 4.00 2.00 16.00
d 2.00 4.00 2.00 16.00
Ceiling: 24.00 m2
Gypsum 12.00 2.00 1.00 24.00
Painting: 273.60 m2
Wall EP 249.60
Ceiling EP 24.00
Page : 47
QUOTATION
OWNER : TOKYU - WIKA JOINT OPERATION
PROJECT : FINISHING WORK FOR D04-D05 BUILDING
LOCATION : LEBAK BULUS - JAKARTA
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings"
1 Note
and "subcontract documents"
The words "as described" where used in this Bill mean as described in the
2 Note
documents mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be paid
3 Note
as set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
4 Contractor shall comply with the Project Manager's instructions regarding the timing Note
and departure the site of plant and equipment and materials required for the works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such
discrepancy or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the
8 Note
side of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built
9 Note
into the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings etc.,
in the structural works, brickwork and blockwork he will be required to cut them at
10 Note
his own expense. No cutting however be carried out without the specific approval of
the Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items
11 being incorrectly positioned in the Works the Contractor shall carry out at his own Note
expense all necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves, anchors,
14 brakets, and the like sundry items supplied by the Other Contractors into concrete, Note
reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft in
17 Note
accordance with the requirements of the Direct Contractors for Lifts
Supply and install structural steel frame works, fixed to the existing concrete
and/or to steel coulmn and beams; including all labour, materials and plant in
3b.3.(5).3.2.7
fabricating, assembling and erecting with welded and bolted shop and site
connections, complete including zinc cromate priming, as described to:-
200mm thick block wall in dry mix mortar system, complete with reinforcement,
3b.3.(5).3.3.2.1
lintels, stiffeners, anchorage, latching and accessories as described
100mm thick block wall in dry mix mortar system, complete with reinforcement,
3b.3.(5).3.3.2.2
lintels, stiffeners, anchorage, latching and accessories as described
a General - m2 186,200 -
3b.3.(5).3.3.2.3 Plaster trowelled smooth in dry mix mortar system as described
a General 7,085 m2 63,200 447,772,000
Powder coated glavanized steel roof cladding, install complete including steel angle
3b.3.(5).3.3.2.4
frames and all necessary fixing accessories as described to:-
a General 3,616 m2 559,200 2,022,067,200
3b.3.(5).2.2.5 Prepare and apply resin emulsion paint finish, all as described to:
a General 7,634 m2 63,200 482,468,800
Supply and install homogenous/ceramic tile, laid on screed bedded and jointed in
3b.3.(5).3.3.2.6 instant cement ex. Mortar Utama or equal, pointed in coloured grouting ex. AM or
equal as described to:
a W4, CT 200x200mm 302 m2 485,500 146,621,000
3b.3.(5).3.3.3 CEILING WORK
Supply and install suspended ceiling framing with metal furring and C channel fixed
to concrete soffit consist with 5 mm diameter galvanized steel including wall trim,
3b.3.(5).3.3.3.1
fixed with scrimped and flush joint, including forming holes and additional framing
for ME fitting, all as described;
a Gypsum board 12mm thick 332 m2 263,200 87,382,400
b Silicate Calcium board 6mm thick 150 m2 204,300 30,645,000
3b.3.(5).3.3.3.2 Prepare and apply syntetic resin emulsion paint finish, all as described to:
a Gypsum and Silicate Calcium ceiling 482 m2 63,200 30,462,400
3b.3.(5).3.3.4 DOORS AND WINDOWS
Supply assemble, set and install steel rolling door in paint finish, complete including
3b.3.(5).3.3.4.1 rooling mechine and rolling box, fitting and all necessary fixing accessories; all as
described:
a SHS-01, overall 5200x6000 mm 6 No 81,521,200 489,127,200
Supply assemble, set and install steel doors and frames finish duco, install
complete including ironmongery and all fixing accessories, all the exposed frame to
3b.3.(5).3.3.4.2
primed with approved primer, grouting the frames in water proofing cement mortar,
protecting frames and cleaning on completion, all as described;
Toilet Cubicle, 2100mm high, timber cubicle partition, devided into partition and
3b.3.(5).3.3.5.2.1 door, install complete including pedestal, ironmongery, door stopper with hook and
all necessary fixing accessories as the manufacturer's instructions
Qty Unit UNIT PRICE TOTAL Qty Unit UNIT PRICE TOTAL
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
Note Note
- m3 126,500 - - m3 126,500 -
ORM OF MILESTONE : - ORM OF MILESTONE : -
Qty Unit UNIT PRICE TOTAL Qty Unit UNIT PRICE TOTAL
- m2 33,300 - - m2 33,300 -
Qty Unit UNIT PRICE TOTAL Qty Unit UNIT PRICE TOTAL
- m2 186,200 - - m2 186,200 -
Qty Unit UNIT PRICE TOTAL Qty Unit UNIT PRICE TOTAL
Qty Unit UNIT PRICE TOTAL Qty Unit UNIT PRICE TOTAL
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings"
1 Note
and "subcontract documents"
The words "as described" where used in this Bill mean as described in the
2 Note
documents mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be
3 Note
paid as set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
Contractor shall comply with the Project Manager's instructions regarding the
4 Note
timing and departure the site of plant and equipment and materials required for the
works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such
discrepancy or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the
8 Note
side of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built
9 Note
into the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings
etc., in the structural works, brickwork and blockwork he will be required to cut
10 Note
them at his own expense. No cutting however be carried out without the specific
approval of the Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items
11 being incorrectly positioned in the Works the Contractor shall carry out at his own Note
expense all necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves, anchors,
14 brakets, and the like sundry items supplied by the Other Contractors into concrete, Note
reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft
17 Note
in accordance with the requirements of the Direct Contractors for Lifts
Supply and install structural steel frame works, fixed to the existing concrete
and/or to steel coulmn and beams; including all labour, materials and plant in
3b.3.(07).1.7
fabricating, assembling and erecting with welded and bolted shop and site
connections, complete including zinc cromate priming, as described to:-
100mm thick block wall in dry mix mortar system, complete with reinforcement,
3b.3.(07).2.2.1
lintels, stiffeners, anchorage, latching and accessories as described
Supply assemble, set and install steel doors and frames finish duco, install
complete including ironmongery and all fixing accessories, all the exposed frame to
3b.3.(07).2.3.1
primed with approved primer, grouting the frames in water proofing cement mortar,
protecting frames and cleaning on completion, all as described;
Supply and install roof steel works, fixed to the existing concrete and/or to steel
coulmn and beams; including all labour, materials and plant in fabricating,
3b.3.(07).2.5.1
assembling and erecting with welded and bolted shop and site connections,
complete including zinc cromate priming, as described to:-
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings"
1 Note
and "subcontract documents"
The words "as described" where used in this Bill mean as described in the
2 Note
documents mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be paid
3 Note
as set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
4 Contractor shall comply with the Project Manager's instructions regarding the timing Note
and departure the site of plant and equipment and materials required for the works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such
discrepancy or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the
8 Note
side of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built
9 Note
into the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings etc.,
in the structural works, brickwork and blockwork he will be required to cut them at
10 Note
his own expense. No cutting however be carried out without the specific approval of
the Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items
11 being incorrectly positioned in the Works the Contractor shall carry out at his own Note
expense all necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves, anchors,
14 brakets, and the like sundry items supplied by the Other Contractors into concrete, Note
reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft in
17 Note
accordance with the requirements of the Direct Contractors for Lifts
Supply and install structural steel frame works, fixed to the existing concrete
and/or to steel coulmn and beams; including all labour, materials and plant in
3b.3.(10).1.8
fabricating, assembling and erecting with welded and bolted shop and site
connections, complete including zinc cromate priming, as described to:-
100mm thick block wall in dry mix mortar system, complete with reinforcement,
3b.3.(10).2.2.1
lintels, stiffeners, anchorage, latching and accessories as described
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings"
1 Note
and "subcontract documents"
The words "as described" where used in this Bill mean as described in the
2 Note
documents mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be paid
3 Note
as set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
4 Contractor shall comply with the Project Manager's instructions regarding the timing Note
and departure the site of plant and equipment and materials required for the works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such
discrepancy or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the
8 Note
side of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built
9 Note
into the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings etc.,
in the structural works, brickwork and blockwork he will be required to cut them at
10 Note
his own expense. No cutting however be carried out without the specific approval of
the Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items
11 being incorrectly positioned in the Works the Contractor shall carry out at his own Note
expense all necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves, anchors,
14 brakets, and the like sundry items supplied by the Other Contractors into concrete, Note
reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft in
17 Note
accordance with the requirements of the Direct Contractors for Lifts
Supply and install structural steel frame works, fixed to the existing concrete
and/or to steel coulmn and beams; including all labour, materials and plant in
3b.3.(11).1.8
fabricating, assembling and erecting with welded and bolted shop and site
connections, complete including zinc cromate priming, as described to:-
100mm thick block wall in dry mix mortar system, complete with reinforcement,
3b.3.(11).2.2.1
lintels, stiffeners, anchorage, latching and accessories as described
Supply assemble, set and install steel doors and frames finish duco, install complete
including ironmongery and all fixing accessories, all the exposed frame to primed
3b.3.(11).2.3.2
with approved primer, grouting the frames in water proofing cement mortar,
protecting frames and cleaning on completion, all as described;
a D-16, overall size 1400mm x 2200mm x 55mm thick, non firerated 2 No 26,048,900 52,097,800
Supply assemble, set and install glass window, 8mm thick clear glass with
aluminum extruded frame in powder coating finish, installed complete with
3b.3.(11).2.3.3
ironmongeries, gasket, seal, fitting and all necessary fixing accessories; al as
described:
a W-34, overall size 15000mm x 1000mm 2 No 43,414,800 86,829,600
TOTAL : 905,154,010
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings"
1 Note
and "subcontract documents"
The words "as described" where used in this Bill mean as described in the
2 Note
documents mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be paid
3 Note
as set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
4 Contractor shall comply with the Project Manager's instructions regarding the timing Note
and departure the site of plant and equipment and materials required for the works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such
discrepancy or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the
8 Note
side of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built
9 Note
into the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings etc.,
in the structural works, brickwork and blockwork he will be required to cut them at
10 Note
his own expense. No cutting however be carried out without the specific approval of
the Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items
11 being incorrectly positioned in the Works the Contractor shall carry out at his own Note
expense all necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves, anchors,
14 brakets, and the like sundry items supplied by the Other Contractors into concrete, Note
reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft in
17 Note
accordance with the requirements of the Direct Contractors for Lifts
Supply and install structural steel frame works, fixed to the existing concrete
and/or to steel coulmn and beams; including all labour, materials and plant in
3b.3.(15).1.10
fabricating, assembling and erecting with welded and bolted shop and site
connections, complete including zinc cromate priming, as described to:-
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings"
1 Note
and "subcontract documents"
The words "as described" where used in this Bill mean as described in the
2 Note
documents mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be paid
3 Note
as set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
4 Contractor shall comply with the Project Manager's instructions regarding the timing Note
and departure the site of plant and equipment and materials required for the works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such
discrepancy or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the
8 Note
side of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built
9 Note
into the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings etc.,
in the structural works, brickwork and blockwork he will be required to cut them at
10 Note
his own expense. No cutting however be carried out without the specific approval of
the Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items
11 being incorrectly positioned in the Works the Contractor shall carry out at his own Note
expense all necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves, anchors,
14 brakets, and the like sundry items supplied by the Other Contractors into concrete, Note
reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft in
17 Note
accordance with the requirements of the Direct Contractors for Lifts
Supply and install structural steel frame works, fixed to the existing concrete
and/or to steel coulmn and beams; including all labour, materials and plant in
3b.3.(16).1.3
fabricating, assembling and erecting with welded and bolted shop and site
connections, complete including zinc cromate priming, as described to:-
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings"
1 Note
and "subcontract documents"
The words "as described" where used in this Bill mean as described in the
2 Note
documents mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be paid
3 Note
as set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
4 Contractor shall comply with the Project Manager's instructions regarding the timing Note
and departure the site of plant and equipment and materials required for the works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such
discrepancy or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the
8 Note
side of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built
9 Note
into the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings etc.,
in the structural works, brickwork and blockwork he will be required to cut them at his
10 Note
own expense. No cutting however be carried out without the specific approval of the
Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items
11 being incorrectly positioned in the Works the Contractor shall carry out at his own Note
expense all necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves, anchors,
14 brakets, and the like sundry items supplied by the Other Contractors into concrete, Note
reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft in
17 Note
accordance with the requirements of the Direct Contractors for Lifts
Supply and install structural steel frame works, fixed to the existing concrete
and/or to steel coulmn and beams; including all labour, materials and plant in
3b.3.(17).1.8
fabricating, assembling and erecting with welded and bolted shop and site
connections, complete including zinc cromate priming, as described to:-
100mm thick block wall in dry mix mortar system, complete with reinforcement,
3b.3.(17).2.2.1
lintels, stiffeners, anchorage, latching and accessories as described
PRELIMINARIES
General Notes :
This Bill is to be read in conjunction with accompanying "Specification", "Drawings"
1 Note
and "subcontract documents"
The words "as described" where used in this Bill mean as described in the
2 Note
documents mentioned above
Notwithstanding anything elsewhere to the contrary the excavation work will be
3 Note
paid as set out in the Milestone Payment Schedule
Access to and egress from the site shall be determined by the Employer and the
Contractor shall comply with the Project Manager's instructions regarding the
4 Note
timing and departure the site of plant and equipment and materials required for the
works
The Contractor shall check the accuracy of the levels shown on the Site plans and
notify the Project manager of any discrepancy. No claim for additional work will be
5 Note
admitted due to any such additional work will be admitted due to any such
discrepancy or inaccuracy if the Contractor fails to notify the Project manager
The Contractor shall submit with his tender full details of his proposed method of
6 carrying out the excavations and his proposed method of keeping the site free from Note
water during the excavation works
The Contractor shall allow in this tender for all cost in liasing and working with the
7 Note
Contractor for the Bore Pile Works
The Contractor shall be responsible for maintaining the safety and stability of the
8 Note
side of the excavations at all the times during the execution of the works
The Contractor shall be responsible for ensuring that the setting out of items built
9 Note
into the Works is correct
In the event of the Contractor failing to form chases, recesses, holes, openings
etc., in the structural works, brickwork and blockwork he will be required to cut
10 Note
them at his own expense. No cutting however be carried out without the specific
approval of the Project Manager
In the event of pipes, pipe sleeves, anchors, brackets and the like sundry items
11 being incorrectly positioned in the Works the Contractor shall carry out at his own Note
expense all necessary work to correct the error to the Project Manager's approval
The Contractor shall allow for forming all chases, recesses, holes and penetrations
13 Note
through concretework and brickwork for the works of the Other Contractors
The Contractor shall allow for building or casting in all pipes, pipe sleeves,
14 anchors, brakets, and the like sundry items supplied by the Other Contractors into Note
concrete, reinforced concrete and masonry
The Contractor shall allow for supply and install sparing pipe, conduit pipe for
15 plumbing, fire fighting or other MEP works into concrete, reinforced concrete and Note
masonry
The Contractor shall allow for grouting all MEP coring to the concrete, reinforced
16 Note
concrete.
The Contarctor shall allow for supplying and installing hooks above each lifh shaft
17 Note
in accordance with the requirements of the Direct Contractors for Lifts
Supply and install structural steel frame works, fixed to the existing concrete
and/or to steel coulmn and beams; including all labour, materials and plant in
3b.3.(18).1.8
fabricating, assembling and erecting with welded and bolted shop and site
connections, complete including zinc cromate priming, as described to:-