Grid Volume ft3

1 2 3 4

a (625.00) 625.00 6,250.00 39,375.00


b (5,625.00) (6,875.00) (2,500.00) 7,500.00
c (5,000.00) (7,500.00) (3,125.00) 4,375.00
d (2,500.00) (7,500.00) (6,875.00) 625.00

58,750.00 Cut
(48,125.00) Fill
10,625.00 Nett

On Site = RM10.00 RM10.00


(cut - fill) = (58,750-(-48,125.00))
ft3 ft3

On Site = RM 1,068,750.00

Off Site = RM10.00 RM10.00


(cut - fill) = (58,750-48,125.00)
ft3 ft3

Off Site = RM 106,250.00

Total Cost = On Site + Offsite


Total Cost = RM 1,175,000.00