You are on page 1of 13

Sustainability in Public Works Conference

24 – 26 August 2016

Guidelines for Building Energy Efficiency Retrofitting

Morshed Alam 1, Patrick X.W. Zou1, Jay Sanjayan1, Rodney Stewart2, Oz Sahin2,
Edoardo Bertone2, John Wilson1
1
Department of Civil and Construction Engineering and Centre for Sustainable Infrastructure,
Swinburne University of Technology, VIC, Australia
2
Griffith School of Engineering, Griffith University, QLD, Australia

Corresponding Author: Morshed Alam Email: mmalam@swin.edu.au

Abstract
Retrofitting existing buildings for energy efficiency has been identified as an effective measure to
reduce global energy consumptions and greenhouse gas emissions. Many governments and
organisations have put significant effort towards energy efficiency improvement in existing buildings. In
this research, a comprehensive review of the barriers to retrofitting, retrofitting guidelines and research
progress to date has been carried out. The barriers to the uptak e of energy retrofitting were
categoris ed as Regulatory barrier, Economic barrier, Knowledge barrier or Social barrier. The review
of existing guidelines showed that at least one important step in the building retrofitting process is
missing, which is risk assessment and management. It was found that although existing research has
shown the importance of conducting a risk assessment in the building retrofitting process, none of the
currently available retrofitting guidelines of different countries includes risk assessment. Inaccurate
predictions are becoming more problematic for the industry as new financing schemes such as
Environmental Upgrade A greements (EUAs) and E nergy Perf ormance Contracting (EPCs), relying on
predicted savings are introduced locally, nationally and internationally. Risk assessment is important
to ensure that the predicted energy saving is achieved once the building is retrofitted and in use. In
addition, it was also found that some guidelines have no directions for post occupancy evaluation of
installed retrofit measures. Based on the review, the essential steps of a building retrofit guideline are
proposed, outlined and discussed in this paper.

1. Introduction
emphasis on retrofits of government and other
Energy and water scarcity, as well as public buildings by issuing “Notification on
environmental pollution, have become key Further Implementation of Energy-efficiency
challenges for sustainable development of the Retrofits in Public Buildings” [4]. It requires a
2
whole world. The building sector accounts for 10% reduction of energy consumption per m
40% of the global energy consumptions and for public buildings and 15% reduction for large
2
contribut es up to 30% of global greenhouse public buildings with over 20, 000 m of floor
gas emissions [1]. Therefore, it becomes area by the end of 2015. In 2010, the UK
obvious that energy efficiency of buildings is a government made a significant commitment to
key component of reducing global energy use upgrade the energy efficiency of 7.0 million
and climate harmful emissions. Currently the British homes by 2020 aiming at reducing
majority of the existing building stocks were carbon emissions by 29% [5]. The International
built before the introduction of sustainability Energy Agency (IEA) has launched a set of
benchmarks and are energy inefficient. To Annex projects to promote energy efficiency of
achieve an energy use reduction in the building existing buildings, such as: Annex 46 – Holistic
sector, the issue of energy inefficiency of assessment toolkit on energy efficient retrofit
existing buildings must be addressed [2]. The measures for government buildings; Annex 55
implementations of energy retrofit measures – Reliability of energy efficient building
(ERM) for increasing the energy efficiency of retrofitting; and Annex 56 – Energy &
the existing buildings have been shown to greenhouse gas optimised building renovation
have a significant effect on reducing the total [6]. These efforts provided policy guidance,
energy demand [3]. financial assistance and technical support for
During the last decade, many governments the implementation of energy efficiency
and international organisations have put measures in existing buildings.
significant effort towards energy efficiency In the USA, the Energy Policy Act of 2005,
improvement in existing buildings. In 2011, the expanded under the Energy Independence
Chinese government strengthened the and Security Act of 2007, requires that all
existing buildings must reduce energy Table 1 Barriers to uptake of building energy
consumption 30% by 2015, compared with retrofitting
2003 levels, through building upgrades and
efficient appliances. In Australia, Energy 1. Economic Barrier
Efficiency in Government Operation (EEGO)
policy was introduced in 2006 according to Lack of Building owners or consumers
which minimum performance standard for Finance do not have access to
government office buildings should be sufficient fund for retrofitting.
NABERS 4.5 star [7]. In 2008, the City of High upfront Retrofitting existing buildings
Melbourne launched a program to retrofit 1200 costs and requires high upfront costs and
CBD buildings to achieve 4.5 NABE RS star by payback the benefits accrue gradually
2020 [8]. expectations over time which sometimes
result in longer payback
While there are a number of policies with the period.
requirement of reducing emission and energy Priorities in Interested to invest the capital
consumption through building retrofitting, there investments in other higher earning
is still a lack of a comprehensive strategy investments.
outlining how it can be ac hieved. Therefore, Price signals Have a higher propensity to
the aim of this paper is to propose a
undertake energy retrofit
comprehensive guideline to guide the building
investments, if the financial
retrofitting process efficiently and cost- incentive associated with it is
effectively. In this process, potential barriers to
sufficiently large.
the upt ake of energy efficiency ret rofitting have
Split- Not interested to retrofit when
been identified. It is then followed by the
incentives the person who would pay the
evaluation of existing building ret rofitting
cost of retrofitting would not
guidelines from different countries to
receive the full benefit of them
understand their strengths and limitations.
Minimize Cutting the funds for energy
Then, research progress in the area of building
cost efficiency generally comes first
retrofitting has been explored to see what a
if cost minimization is required.
building retrofitting guideline should entail from
Uncertainties The difference between actual
research pers pectives. Finally, based on the
understanding of potential barriers, existing over and predicted energy savings
financial gain from retrofit influence cost
guidelines, and research progress a new
savings and hence payback
retrofitting guideline have been proposed.
period.
Lack of Incremental savings from
2. Barriers to implementing attention and retrofitting are quite small
building retrofitting materiality compared to the benefits from
other investments and hence
Retrofitting existing buildings for energy less attention is given.
efficiency is a big challenge becaus e it involves 2. Regulatory Barrier
substantial funding and decision-making from a Fragmented In most cases, none of the
wide range of stakeholders such as landlords, market involved professionals (during
tenants, property managers, developers and design, construction and
local council. Potential barriers against uptake operation stage) are expert in
of energy efficient retrofitting may arise from building energy efficiency, but
any stakeholder or group of stakeholders. the responsibility for achieving
Therefore it is essential to understand the it is diffused among them
potential factors that may prohibit the uptake of which present a coordination
energy efficient measures in buildings. This challenge.
knowledge is also important to design and Institutional There is a bias among
implement policies that will effectively promote institutional investors more
energy efficiency investments. From the familiar and comfortable with
existing literatures [9-11], four main categories supply- side investments and
of barriers to retrofitting existing buildings have large-scale financing, rather
been identified which are presented in Table 1. than generally smaller (and
“more risky”) projects on the
demand side.
Structural A verage age of the building
stock is increasing because of energy efficiency investment would not
a low demolition rate. Because efficiency yield a return and see it as
of the age of buildings, the compliance and cost burden.
landlord-tenant dilemma 4. Social Barrier
makes it difficult to ameliorate Interruption The us ual operation of a
the existing building stock. to building building is interrupted when a
Multi- It can be very difficult to agree operation renovation is being
stakeholder on energy saving investments undertaken. In the case of
issues in multi-owner buildings if the deep renovation, the entire
owners have to either approve building may need to be
a decision or mak e a financial vacated which will involve
contribution. practical and financial barriers
Government If the government demonstrate associated with re-locating the
not a strong a strong commitment to occupant for the period of the
driver policies that encourage retrofit.
sustainability, as well as lead
by example, this can create a 3. Review of current guidelines
long-term positive impact on
industry.
In order to carry out the building energy
3. Knowledge Barrier
retrofitting process efficiently through
Lack of Sustainability is not usually
minimizing the effect of potential barriers, a
Information understood well by owners or
number of retrofitting guidelines have been
and consumers. In some cases, developed in many countries around the world.
awareness they are not aware of current
Brief discussions of the available ret rofitting
best practise or do not fully
guidelines have been presented below.
comprehend the effectiveness
of energy efficient 3.1 USA guideline
technologies.
Awareness While there is a general Figure 1 shows the flow chart of the ret rofitting
of savings appreciation that energy project according to advanced energy
potential saving is a “good thing”, there retrofitting guideline developed by the U.S
remains a lack of Department of Energy [12]. The guide begins
understanding of the energy, with an introduction to key concepts
cost and carbon savings from underpinning energy efficiency projects;
different measures. discussions of goal setting, project planning,
Lack of Some building owners are not and performance t racking to illustrate the
Motivation interested in improving their process for initiating energy efficiency projects.
buildings unless the equipment It also explains energy audits, financial
is about to break or there is a analysis, and financing options, to provide the
concerning high level of remaining elements needed for a strong
vacancy that is affecting his business case. This section lays the foundation
rental income. upon which energy efficiency project options
Skills & Skill shortages exist in bot h the are built in the subsequent sections. In the
knowledge contractor market responsible subsequent sections, three levels of upgrade
related to for the effective installation of approach have been pres ented: (1)
building energy saving measures, as Implementing operations and maint enance
professional well as in professional (O&M) improvements through Existing Building
s services, with few architects Commissioning (EBCx), (2) standard retrofits,
and designers familiar with and (3) deep retrofits. It was reported in this
energy efficient renovation. guide that up to 22% energy savings can be
Confusion in If t wo or more professionals achieved through by improving building
choosing the give supposedly conflicting operations and restructuring maint enance
best option advic e as to the best way to procedures, with an average simple payback
renovate, this may lead to period of 1.1 years. Standard retrofit measures
scepticism amongst the provide cost- effective and low-risk efficiency
consumer over the installation upgrade options including equipment, system,
of energy efficient measures. and assembly retrofits. Deep retrofit measures
Perception Some building owners have require a larger upfront investment and may
regarding the perception that energy
have longer payback periods than EBCx or discussion of measurement and verification
standard ret rofit measures. In this guide, the (M&V) strategies to ensure that improvements
proposed retrofit options are also customized are operating as intended and operation and
for five different climates to consider the effect maintenance (O&M) activities to maint ain and
of local climat e which has broadened its continually improve building performance
applicability. The guide concludes wit h a

Figure 1 Project planning flow chart of the USA guideline [12]

The second step is maintenance and


3.1.1 UK guideline purchasing review step which doesn’t cost
much but can lead to significant performance
International engineering consulting firm ARUP improvements (Similar to EBCx of USA
[13] has developed a 5 step survival strategies guideline). The next step is establishing targets
for the existing building stock of UK (Figure 2) and goals which will serve as a driver in
to turn a tired asset into one that benefits users, developing a specific upgrade plan for a given
communities, the environment, business and property. The subsequent step is about the
the balance sheet. The first step towards identification of optimum upgrade initiatives.
upgrading an existing property is baseline There is no one solution or approach for any
assessment to see how the building is building upgrade; each initiative needs to be
positioned against the current code and assessed based on its merits and the building
regulatory requirements. At this step, energy in question. The key parameters that are
auditing is carried out to determine the areas of considered while selecting the optimum
largest consumption and target areas for retrofitting options are the level of
improvement. In addition, a condition audit is refurbishments, capital cost and qualitative
also carried out to determine the current benefit of the initiative to sustainability, building
condition and expected remaining economic occupants and owner. A list of 195 initiatives
life of a building’s component. This guide has has been provided to help the owner to get
presented four levels of refurbishment (as started. The final step is to implement the
opposed to three levels from USA guideline) selected retrofit options. Decisions have to be
approach where the degree of intervention taken regarding the sequence of ret rofitting
required is decided on the reports of building implementation whether the upgrades be
condition and performance. phased progressively or carried out at once.
Figure 2 UK’s Five step survival strategies for existing buildings in the UK [13]

that in the latter one decisions regarding the


3.1.2 Singapore guidelines level of refurbishment required is taken in step
one whereas in the former one the decision is
In Singapore, a six step process has been made at step 4. In the Singapore guideline, the
developed by Building and Construction lists of suggested initiatives have been
Authority of Singapore [14] in conjunction with updated for Singapore perspective.
ARUP which has been presented in Figure 3.
The difference between this Singapore
guideline and the A RUP guideline for the UK is

Figure 3 Singapore’s six-step building retrofitting process [14]

sources. The next stage is the “undertake


3.1.3 Australian’s guidelines retrofit works” where retrofit action plan is
implemented. At this stage, one has to
The Australian guideline, developed by ARUP communicate with t enants (if applicable), apply
and property council of A ustralia [ 15], is mostly for planning/building approval if necessary,
similar to that of Singapore except that step 3 organize builder t o carry out the work etc. In
in the Singapore guideline is now step 2 in the annual update stage, the progress of
Australian guideline and step 2 in Singapore retrofit implement ation is monitored and
guideline is step 3 in Australian guideline. The compared with the retrofit action plan to see
City of Melbourne council also developed a whet her t he project is on the right track. Once
building retrofit map under their 1200 Buildings the retrofitting is completed, commissioning of
program which is shown in Figure 3. The the ret rofitted building is undertaken to achieve
baseline assessment step determines how the best result in the complete work stage. The
much energy and water the building consumes building tenants/managers and cont ractors are
undertaking an energy/ water benchmarking trained to ensure optimum ongoing operational
tools NABERS and Green Star. The retrofit efficiency. Finally, the building is re-assessed
action plan stage explores different retrofit one year after the completion of final works to
strategies, selects optimum strategies through quantify the extent of savings.
necessary analysis and determines funding
Sustainability in Public Works Conference
24 – 26 August 2016

Figure 4 City of Melbourne’s 1200 building retrofitting process [15]

3.1.4 Indian guidelines practices and operating methods. From the


benchmarking analysis, if there is a need to
There are six main steps in this roadmap for improve the energy levels is detected, a detail
energy efficiency ret rofits which are presented energy simulation is carried out to determine
in Figure 5 [16] . The internal assessment is a the energy savings from different retrofit
preliminary energy us e analysis which includes technologies. This step is then followed by
1) det ermining the building total built-up area, 2) cost-benefit analysis to choose the best retrofit
Collecting utility bills to calculate total energy option as per the user requirement and
used. 3) Calculation of energy performance budgetary constraints. Two types of financing
index (EPI) which is the ratio of total annual model: Self-financing and Partnering with
energy used to the tot al built-up area energy services company (ES CO) have been
(kWh/sq.m./year) and 4) Comparison of the discussed for funding the building retrofit
calculated EPI having similar characteristics activities.
with climatic zones. The second step is to carry
out detailed energy survey with the help of In the project implementation step, a retrofit
energy auditing team t o identify potential areas implementation plan is developed including
of improvement. Next is the technical analysis appropriate timelines of retrofit process,
step which studies the data from the energy commitment, and finance mechanism so that
survey, including energy consumption and the implementation is seamless. The final step
peak demand analysis. Based on the analysis, Operation and maintenance is there to ensure
an action plan is formulated to improve the recurring energy savings from the ret rofitted
building performance. The action plan includes building.
a review of mechanical and electrical systems
design, installed condition, maint enance

Figure 5 Building retrofitting roadmap India [16]


Sustainability in Public Works Conference
24 – 26 August 2016

4. Review of relevant research of uncertainty was reported for physical and


user behaviour parameters variation,
A number of studies have been undertaken by respectively, in the same study. Variation in
previous res earchers to investigate the HVAC operation was found to result in -15.3%
effectiveness different retrofit measures in to 70.3% variation in annual energy
improving the energy performance of existing consumption for a medium sized office building
buildings and develop a guideline for the [23]. Daly et al. [24] reported more than 50%
retrofitting process. Griego et al [17] indicated variation in the predicted energy consumptions
that over 49% annual energy savings can be for all studied locations in Australia, due to the
achieved cost-effectively for bot h retrofit and inconsistencies in the assumptions of ‘hard-to-
new construction commercial office buildings measure’ building and occupant behaviour
by reducing office equipment loads and more input parameter values. These types of
efficient lighting technology and controls. A inaccurat e predictions are becoming more
reduction in primary energy consumption by 40% problematic for the industry as new financing
was achieved in the case study of Aste and schemes such as Environmental Upgrade
Pero [18] through improving building envelope Agreements (EUAs) and Energy Performance
only, without intervention on HVAC plant, lights Cont racting (EPCs), relying on predicted
or other technical systems. Fiaschi et al [19] savings are introduced locally, nationally and
showed that installation of PV modules internationally.
guarantees annual savings of 4.5% and 5%
with respect to the annual cost of electricity. Risk analysis/assessment/evaluation is,
Upgrade of wall insulation lead to energy therefore, essential to transform risk in practice
savings of approximately 40–50%, which to simulations and provide decision makers
agrees with the average values available in the with a sufficient level of confidence to select
literature for similar buildings. Virote and and determine the best retrofit solutions. A
Neves-Silva [20] reported that human typical risk analysis method consists of
behaviour plays a very important role in the sensitivity analysis, probability analysis of the
overall building energy consumption. Careless input parameters, Monte Carlo simulation and
behaviour can add one-third to a building’s risk assessment steps [25]. Sensitivity analysis
designed energy performance, while is required to identify the most uncertain and
conservation behaviour can save a third. influential parameters in t he risk analysis. The
Saelens et al (2011), showed that encouraging next step is the quantification of uncertainties
people to actively switch off the lights reduces using probabilistic approach. Aft er assigning a
lighting and cooling energy demand. probability distribution to selected input
parameters, values from within their probability
A building ret rofit is subject to many challenges distribution are picked randomly and one
such as uncertainty in savings estimation, simulation is undertaken. Simulations are
energy use measurements, weather forecast, repeated with new randomly selected values
the changes of energy consumption patterns, each time. Values are picked from distributions
system performance degradations, etc. of each parameter by possibility, which
Uncertainty paramet ers can be divided into generates thousands of combinations. This is
three categories: physical (uncertainties in known as Monte Carlo approach. Those
physical properties, such as conductivity, combinations are treat ed as possible cases
thickness of mat erials etc.), design (design that might occur in practice. In the risk
variations that occur during the planning assessment steps, the res ults from Monte
process) and scenario uncertainty (changes in Carlo simulation are used to generate a
parameters during the operating stage such as, probability distribution curve of energy
occupancy pattern, behaviour, weather) [21]. performance. The distribution curve, for both
Taking scenario uncertainties int o account is energy performance and utility cost, presents
very important when considering design the possibility of different scenarios in reality,
robustness and future adaptability of the thus can be used for assessing risks involved
building. in energy savings and payback period
predictions.
In a recent case study by Silva and Ghisi [22],
up to 19. 5% and 36.5% of uncert ainty was In order to select the optimum retrofit
reported in the prediction of heating energy strategies for maximum energy and cost
consumption for physical and user behaviour savings a number of retrofit analysis toolkits
parameters, respectively. In the case of cooling have been developed by previous researchers.
energy consumption, up to 43.5% and 38.0% The CBES (Commercial Building Energy Saver)
retrofit analysis toolkit of Hong et al [26] evaluation. A description of decision making
calculates the energy use of a building, model based on multi-criteria evaluation
identifies and evaluates retrofit measures in methodology can be found in Shao et al [28].
terms of energy savings, energy cost savings Almeida et al [29] showed that a decision
and payback period. CBES includes 100 making model based on life cycle cost benefit
configurable energy conservation measures analysis considering both technical and
(ECMs) that encompass IA Q, technical economic uncertainties parameters provide
performance and cost data, for assessing 7 more realistic economic evaluation and reveal
different prot otype buildings in 16 climate the investment risk. Hopfe et al. [30] proposed
zones in California, USA. The tool developed a methodology using Fuzzy-AHP (Analytical
by Hillebrand [27] evaluates ret rofitting hierarchy process). The conventional AHP
combinations according to energy, ecology, protocol that handles only deterministic
and economic criteria. The results show that a information was enhanced to include
generally preferred retrofit option cannot uncertainties. Their proposed method
always be identified. Each evaluation criterion presented a viable means of collaboratively
may deliver different retrofit orders, which ranking complex design options based on the
points out the necessity of a multi-criteria multi-criteria analysis.

Figure 6 A systematic approach for sustainable building retrofits. (Ma et al 2012 [2])
From the review of existing research Ma et al occupancy survey is also recommended by Ma
[2] developed a systematic approach to et al (2012) t o understand whether the building
identifying, determining and implementing the occupants and building owners are satisfied
best retrofit measures for existing buildings as with the overall retrofit result.
shown in Figure 6. The retrofitting starts with
establishing goals, building audit and energy 5. Discussions
performance monitoring of an existing building.
Latter, audit data is used to develop a base- In this paper, a comprehensive analysis of
case simulation model. If audit data is positive building ret rofitting guidelines of different
for retrofitting, the base case simulation model countries as well as research to date on
is used to quantify the energy benefits of building retrofitting strategy have been carried
different retrofit measures. After that, out. Table 2 shows the comparison of different
appropriate economic analysis tools and risk building energy retrofitting guidelines
assessment methods are used to quantify the discussed in previous sections. The table
performance of a range retrofit options. The points out that the “Advanced Energy retrofit
next step is the selection of optimum retrofit guide” from U.S. department of energy covers
option based using appropriate decision all steps of the required guideline components
support tools as discussed above. The except risk analysis. The guidelines for UK,
selected ret rofit measures are then Singapore, and Australia are developed based
implemented on-site. Test and commissioning on the same source of “existing building
(T&C) is employed to tune the retrofit survival strategies” from ARUP. Similar to the
measures to ensure the building and its one of the USA, these guidelines does not
services systems operat e in an optimal manner. provide any direction for considering risks
The final phase is measurement and involved in retrofitting projects. In addition,
verification of energy savings. A post

Table 2 Comparison building retrofit guidelines of different countries and proposed strategy
Guideline components USA UK Singapore Australia Australia India Research
(by (by ARUP) (by ARUP) (City of (Ma et al
ARUP) Melbourne 2012)
1200
Buildings
retrofitting
Program)
Baseline assessment √ √ √ √ √ √ √
Energy Audit √ √ √ √ √ √ √
Project planning
• Establish targets √ √ √ √ √ √ √
• Analyse potential
barriers and
challenges
Exploration of retrofit √ √ √ √ √ √2 √2
measures
• Level 1 √ √ √ √ √
• Level 2 √ √ √ √ √
• Level 3 etc. √ √ √ √ √
Making business case
of retrofit
• Cost-benefit
analysis using √ √ √ √ √ √
simple payback
period
• Life Cycle Analysis

Risk analysis √
Investment risk
Performance risk
Selection of optimum √1 √1 √1 √1 √1 √
retrofit measures
Financing √ √
Implementation √ √ √ √ √ √ √
Measurement and √ √ √
Verification
Operation and √ √ √ √
maintenance
1
Without considering risks, 2 did not divide retrofit measures into different levels.
there is no discussion regarding financing barrier to retrofitting in the previous studies [9].
mechanism for funding t he retrofitting project, The level of retrofitting to be carried out will be
M&V and O&M strategies for post-ret rofitted decided depending on the available finance.
buildings. In Australia, the retrofit proc ess The risk analysis step calculates the possible
developed by 1200 buildings program includes uncertainties and minimizes the gap bet ween
financing, M&V and O&M strategies. However, predicted and actual savings. In this guideline,
their proposed retrofit process does not include the optimum ret rofit measure is selected based
any methodologies for risk analysis and on stakeholders’ preferences, life cycle cost
selection of optimum retrofit measures. The benefit analysis, and probabilistic energy
retrofit guideline of India has touched almost savings. In other words, a multi-criteria
every step of the proposed retrofit guideline decision making tool should be used for
except, risk analysis, financing and M&O selecting optimum ret rofit measures. The next
strategies. Although the guideline discussed step is the implementation of retrofit measures
the selection of different retrofit measures, no which requires a management plan to manage
differentiation was made between the levels of the contractors, suppliers, and building tenants
retrofit options as it is in the case of the USA during the implement ation process. A proper
and other ARUP based guidelines. retrofit management plan can overcome the
uncertainties/risks that may arise from
Finally, the retrofitting guideline proposed by inaccurat e installation of retrofit measures as
Ma et al [2] based on existing research, is well as minimize the interruption to building
found to cover every component except occupants. The final steps are measurement
financing. The inclusion of financing and verification (M&V) and operation and
mechanism in retrofitting guideline is very maintenance (O&M).
important bec ause the lack of financing is a
strong barrier to the uptake of energy Several case studies are recommended to test
retrofitting as reported in section 2. Also, the the applicability of this new guideline. It should
guideline does not include any discussion be noted that although the existing research
regarding different levels of ret rofitting has developed a number of models for
measures. The inclusion of different levels of retrofitting existing building, uptake of these
retrofit in a retrofitting guideline is important, models in the ret rofitting industry is rare. This
particularly, when there is a budget constraint. is because, very rarely, these models are
tested to see whether it is feasible or not to use
6. Development and in a real retrofitting project. Zou and Sunindijo
implementation of a new [31] presented researc h-practise nexus
guideline approach to promote the findings from
research in to existing industrial practise. This
From the review of available ret rofitting approach can be followed here to ensure that
guidelines adopted in different countries, the the proposed retrofit guideline is suitable for
guidelines in the existing research and barriers industrial application. Figure 8 shows the
to uptake energy retrofitting, a new retrofit framework of research practise nexus
guideline has been proposed. In the proposed approach proposed by Zou and Sunindijo [31].
guideline, an attempt has been made to In the current res earc h, Steps 1 to 3 has
overcome barriers to retrofitting as well as already been completed. Figure 7 shows the
include all necessary steps mentioned in Table proposed retrofit guideline (Step 3) which was
2. The proposed guideline has been presented developed based on past studies (Step 1) and
in Figure 7. It shows the need to introduce industry needs (Step 2). According to the
policies to overcome knowledge barriers and framework, Step 4 is action research which
help stakeholders in establishing ret rofit targets means the proposed guideline will be put into
and goals. It also shows policy requirements practise in real building retrofitting project. The
for auditing and performance monitoring of the findings from the action research will be used
building. This can be in the form of training to modify and improve t he proposed guidelines
materials to generate skilled professional in Step 5. Step 6 is the integration of modified
which will make sure that the auditing and final retrofitting guideline relevant policies to
performance monitoring are carried out in ensure its maximum usage. A training module
accurate and consistent manner. The may need to be developed to train the us ers to
proposed guideline also shows policy use this guideline. The final step is the
requirements for finance mechanism to fund periodical review of the guideline for further
the retrofit project which is reported to be No. 1 improvement when necessary.
Figure 7 Proposed building energy efficiency retrofit guideline

Figure 8 Research-practise nexus approach[31]

7. Conclusion other ret rofit guidelines except the USA did not
include some important retrofitting steps in
In this paper, existing building energy their guidelines. The review of existing
retrofitting guidelines, and research progress in research showed the benefits of the ret rofitting
the field were reviewed. In addition, potential existing buildings using different energy
barriers to the uptake of energy efficiency efficient measures. In addition, the existing
retrofitting were explored. Four categories of research also showed a number of different
barriers were identified which either prohibits decision-making models to select the optimum
or slows down the uptak e of energy efficient retrofitting methods. The most important
retrofitting. These are Economic, Regulatory, finding from the existing research is the need
Knowledge and Social barriers. The evaluation for risk assessment of building ret rofitting
of existing retrofitting guidelines from different project. None of the existing guidelines from
countries showed t hat the guideline of USA is different countries include risk assessment
superior then others and includes all the steps although a review of existing researc h have
of a required guideline components presented pointed out the importance of considering the
in Table 2 except risk assessment. In addition, risk assessment, particularly in t he cases
where investments are made through financing [6] IEA. 16.06.2016]; A vailable from:
such as Environmental Upgrade Agreements http://www.iea-ebc.org/projects/ .
(EUAs) and Energy Performance Contracting [7] Department of the Environment and
(EPCs).
Water Resources, ENERGY EFFICIENCY
Considering the deficiencies of existing IN GOVERNMENT OPERATIONS (EEGO)
guidelines, research progress and barriers to POLICY 2007.
uptake energy retrofitting, a new retrofit [8] The City of Melbourne. [cited
guideline was proposed. In the proposed 16.06. 2016; A vailable from:
guideline, the effort was made to identify the http://www.melbourne. vic.gov.au/busin
areas where policies are required to overcome ess/sustainable-business/1200-
barriers to retrofitting, how risk assessment buildings/Pages/1200-buildings.aspx .
may be conducted and to include all necessary
[9] BPIE (Buildings Performance Institute
steps mentioned in Table 2. In order to finalise
Europe), Europe’s buildings under the
the proposed ret rofit guideline and ensure its
microscope - A country-by-country
maximum effectiveness in the industry, use of
review of the energy performanc e of
research-practise nexus approach has been
buildings. 2011.
recommended.
[10] Initiative), C.C.P., Buildings Energy
8. Acknowledgement Efficiency in China, Germany, and the
United States. 2013.
The authors would like to acknowledge the [11] Ernst & Young, Mid-tier commercial
Sustainable Built Environment National office buildings in Australia. 2015.
Research Centre (SBEnrc) and its partners for
funding this project under SBEnrc Project 1.43 [12] U.S Department of Energy, Advanced
“Ret rofitting Public Buildings for Energy and Energy Retrofit Guide for Office
Water Efficiency”. Buildings- Practical Ways to Improve
Energy Performance. 2011.
[13] Arup United Kingdom, Existing
9. References Buildings Survival Strategies: A
[1] United Nations Environment Toolbox for Re-energising Tired
Programme. Sustainable Buildings and Assets and reducing operating cost.
2008.
Climate Initiative. 2016; A vailable from:
http://www.unep.org/sbci/AboutSBCI/B [14] Building and Construction A uthority
ackground.asp. (BCA) Singapore, Existing B uilding
Retrofit. 2010.
[2] Ma, Z., et al., Existing building retrofits:
[15] Arup and Property Council of A ustralia,
Methodology and state-of -the-art.
Existing Buildings Survival Strategies:
Energy and Buildings, 2012. 55: p.
A Toolbox for Re-energising Tired
889-902.
Assets, Victorian Division. 2008.
[3] Chidiac, S.E., et al., A screening
[16] The energy and resource institute
methodology for implementing cost
effective energy retrofit measures in (TERI), Roadmap for Incorporating
Canadian office buildings. Energy and Energy Efficiency Retrofits in Existing
Buildings, 2011. 43(2–3): p. 614-620. Buildings. 2013: New Delhi.
[4] MOF and MOHURD. Notification on [17] Griego, D., M. Krarti, and A.
Further Implementation of Energy- Hernandez-Guerrero, Energy
efficiency Retrofits in P ublic Buildings. . efficiency optimization of new and
2011; Available from: existing office buildings in Guanajuato,
http://www.gov.cn/zwgk/2011- Mexico. Sustainable Cities and Society,
05/11/content_1861716.htm. 2015. 17: p. 132-140.
[5] DECC. Warmer homes, greener [18] Aste, N. and C. Pero, Energy retrofit of
homes: a strategy for household commercial buildings: case study and
energy management, UK Department applied methodology. Energy
of Energy and Climat e Change. Efficiency, 2012. 6(2): p. 407-423.
10.01. 12]; Available from: [19] Fiaschi, D., R. Bandinelli, and S. Conti,
http://www.decc.gov.uk . A case study for energy issues of
public buildings and utilities in a small
municipalit y: Investigation of possible building energy simulation. Energy and
improvements and integration with Buildings, 2016. 110: p. 1-12.
renewables. Applied Energy, 2012. 97: [26] Hong, T., et al., Commercial Building
p. 101-114. Energy Saver: An energy retrofit
[20] Virote, J. and R. Neves-Silva, analysis toolk it. Applied Energy, 2015.
Stochastic models for building energy 159: p. 298-309.
prediction based on occupant behavior [27] Hillebrand, G., et al., Development and
assessment. Energy and Buildings, design of a ret rofit matrix for office
2012. 53: p. 183-193. buildings. Energy and Buildings, 2014.
[21] Hopfe, C.J. and J.L.M. Hensen, 70: p. 516-522.
Uncertainty analysis in building [28] Shao, Y., P. Geyer, and W. Lang,
performance simulation for design Integrating requirement analysis and
support. Energy and Buildings, 2011. multi-objective optimization f or office
43(10): p. 2798-2805. building energy ret rofit strategies.
[22] Silva, A.S. and E. Ghisi, Uncertaint y Energy and Buildings, 2014. 82: p.
analysis of user behaviour and 356-368.
physical parameters in residential [29] Almeida, R.M.S.F., N.M.M. Ramos,
building performance simulation. and S. Manuel, Towards a
Energy and Buildings, 2014. 76: p. methodology to include building
381-391. energy simulation uncertainty in the
[23] Wang, L., P. Mathew, and X. Pang, Life Cycle Cost analysis of
Uncertainties in energy consumption rehabilitation alternatives. Journal of
introduced by building operations and Building E ngineering, 2015. 2: p. 44-51.
weat her for a medium-size office [30] Hopfe, C.J., G.L.M. Augenbroe, and
building. Energy and Buildings, 2012. J.L.M. Hensen, Multi-criteria decision
53: p. 152-158. mak ing under uncertainty in building
[24] Daly, D., P. Cooper, and Z. Ma, performance assessment. Building and
Understanding the risks and Environment, 2013. 69: p. 81-90.
uncertainties introduced by common [31] Zou, P.X.W. and R.Y. Sunindijo,
assumptions in energy simulations for Research Methodology and Research–
Australian commercial buildings. Practice Nexus, in Strategic Safety
Energy and Buildings, 2014. 75: p.
382-393.
Management in Construction and
[25] Sun, S., et al., A method of Engineering. 2015, John Wiley & Sons,
probabilistic risk assessment for Ltd. p. 180-213.
energy performance and cost using

You might also like