Professional Documents
Culture Documents
Preface
These operating instructions show general procedures and
guidelines that must be observed when installing and using the
product. These operating instructions makes no claim for
completeness and possibly does not cover all the activities that
can occur during the installation, operation, or maintenance, as
there can be special variations of this product. It is highly
recommended that all the necessary information and drawings
are obtained before the installation and use. If in doubt or in need
of additional information, please contact High Voltage
Components at ABB Switzerland Ltd or your local ABB partner
for further information.
General Information
Micafil bushings are designed specifically for mineral oil-filled IEC
60296 transformers and chokes for oil-outdoor applications. Our
bushings comply with the standards IEC 60137, IEEE C57.19.00
and C57.19.01. Additionally, they must be qualified according to
strict internal guidelines. Micafil bushings are produced
exclusively at the ABB industrial site in Zurich, Switzerland.
Table of contents
Measurement terminal
Oil-side shielding
Fig.1: Structure of an AirRIP bushing with cable bolt for rope conductors
Storage duration Outdoor, protected against rain Indoor space, dry (not condensing)
Up to 6 months In original box, packed with PE tubular film. In original box and original packaging.
Recommended: Additional humidity
protection of the body with a second
Polyethylene (PE) tubular film and desiccant
Up to 24 months No possible => Risk of irreparable damage In original box and original packaging.
Only in dry rooms (relative air humidity <50%) at a temperature that is as constant as
possible.
Conduct regular inspections (at least once a year)
If the humidity indicator inside the sealed PE foil colors itself in the pink direction, at least
an equal quantity of desiccant units must be replaced. Within 24 hours, the indicator will
change back in the blue direction (relative air humidity < 40 %).
Long-term storage, No possible => Risk of irreparable damage Protect the unshielded parts of the bushing in the storage container:
more than 24 Bushing in protective layer material (PETP/Alu/PE) together with desiccant:
months - Conduct regular inspections (at least once a year)
- If the humidity indicator inside the sealed PE foil colors itself in the pink direction, at
least an equal quantity of desiccant units must be replaced. Within 24 hours, the
indicator will change back in the blue direction (relative air humidity < 40 %).
- For bushings that are stored for more than a year, we highly recommend a reference
measurement No. 1 (see Chapter 8).
- Desiccant amount/air conditioning: 2½ TME/m2 (moderate) and 25 TME/m2 (extreme)
- TME/m2: Desiccant units per m2 of the barrier layer surface.
Desiccant according to the standard:
1 Unit (DIN 55473A) = 1 Unit (MILD 3464 E) = 1/16 Unit (NF H-320 & 321)
Bushing with oil storage container:
- Conduct regular inspections (at least once a year)
- The oil level should be levelled between the 2 oil sight glasses (see Fig. 3).
insulator should be laid out until the Diameter of the shields Ø [mm]
commissioning in order to avoid partial [kV] [kV] Ø109 Ø134 Ø180 Ø160 Ø180 Ø230 Ø292
discharges trough fingerprints. ≤52 ≤105 80 95 - - - - -
NOTE
140 90 105 - 120 - - -
72.5
160 100 105 - 125 - - -
185 115 115 - 130 130 - -
123
5.1. Recommended distance from the transformer wall 230 145 145 - 145 145 - -
The bushings are developed and tested for mineral oil 275 - 170 - 170 170 - -
145
applications. The field strengths in oil in the lower part of the 310 - 200 - 200 200 - -
bushing depend on the form of the surrounding parts as well as 325 - 210 - 210 210 - -
170
on the transformer oil. 365 - 230 - 230 230 - -
245 460 - - 300 300 300 - -
The corresponding gaps (A) to the earthed structures under 300 510 - - - - - 330 330
standard conditions are listed as a guideline in the following Tab. 630 - - - - - - 450
420
2. This concerns the oil-side ends of the bushings according to 680 - - - - - - 500
the data of the dimension sheet for the bushing. Due to framework 750 - - - - - - 550
550
conditions, additional insulation measures and/or greater 790 - - - - - - 600
distances can be necessary. If necessary, the distance can also Tab. 2: Recommended distances A from earthed parts
be reduced.
Non-insulated edges may only appear in the permitted area and 5.2. Lifting the bushing
should have a Rmin. = 5 mm.
Smaller bushings (< 20 kg) can be removed by hand from the
wooden crate, larger bushings require textile slings and lifting
A possible current transformer must be
means (crane, hoist, etc.). To move the bushing from the
not be longer than L6 (see Fig. 5 and
horizontal to the vertical position, two textile slings (3) shall be
dimension sheet of the bushing), as the
fastened on each lifting eye (1) mounted on the flange of the
field is disrupted, and a destruction of
bushing, then put through the lifting eye (2) mounted on the head
CAUTION the bushing is possible.
of the bushing, and connected to the hook of the first lifting gear.
A third textile sling (4) must be fastened too on each lifting eye (1)
and connected to the hook of the second lifting gear. This lifting
configuration allows to install the bushing in the transformer turret
at a certain angle or vertically after removing the textile sling (4).
processed.
NOTE
Tube diameter Max. hole diameter Cable bolt diameter Max. drilling
d3 (6) (1) (2) [mm] depth
[mm] [mm] (3)
[mm]
40 35 38 (4) minus 20
50 40 45 (4) minus 20
Fig. 12: Rope conductor insulation. At least 1 mm insulation material
65 55 60 (4) minus 20
thickness
80 70 75 (4) minus 20
100 90 95 (4) minus 20
Tab. 3: Recommended maximum drilling depth and hole diameter for a
standard cable bolt
of shields.
The fixture ring is screwed onto the conductor and secured with
a locking screw. The shield has three mounting holes and is
5.15. Head shield from 420 kV
affixed with springs via a bayonet lock.
Bushings of 420—550 kV have an air-side shield for preventing
Dismounting of the shield from the mounting ring: press the corona discharges.
shield lightly against the bushing, rotate it (approx. 12°), then The air-side shield can be mounted on the head fitting with the
pull it off. delivered screws and washers. Threaded holes are provided for
The shielding can temporarily be inserted under the bushing this purpose on the head fitting. Depending on the bushing type,
with a power cable. two spacing sleeve variants are provided: (See Fig. 16 and
The terminal is then freely accessible and can be connected details A / B).
to the connection pieces. It must be in any case made sure
that the contact resistance is kept as low as possible.
Bring the shield back to its original position. It must be made
sure that the 3 holes are positioned over the hexagon socket
screws. The screws are inserted through the holes, and with
some pressure against the bushing, the shield can be turned
in the original secure position (approx. 12°) until it locks in
place again with spring load.
3
2
6 4
5
The use of the possible thread for the lifting eye is always
the best option to lift the bushing and install it.
After the installation, the possibly used lifting eyes must be
removed again.
It is recommended that the corresponding threads for the
lifting eyes are closed, e.g. with blind plugs.
Conductor
5.22. Reverse-controlled bushings with rope conductor
Conductor
insulation
For reverse-controlled bushings, the oil side of the insulating
Extension of the rope conductor
body (IKP) is designed specifically for applications in the narrow
before the bend (L1/2)
space of the transformer dome. In this case, 2/3 of the voltage
that is brought from the surface of the oil-side IKPs is still at the
lower end of the bushing. The other third of the voltage
(between the IKP end and conductor) must be borne through
the insulation of the rope conductor.
Fig. 20: Lower part of a reverse-controlled bushing with conductor rope
Sealing
Spring
Protective cover
Protective cover
The bushing must never be commissioned
DANGER
without installing the protective cover on
the measurement terminal or connecting a
monitoring system.
The correct function of the spring contact
in the measurement terminal must always
be tested before locking the bushing.
If this is not observed, the bushing or the
transformer can suffer severe damage. Under
unfavourable conditions, heavy personal
injuries are also not out of the question.
Life-threatening voltages
The described measurements take place
under dangerously high measuring
voltages. The local safety regulations
DANGER must be observed. 1 Bushing C1: Capacity - high-voltage conductor tapping
layer
C2: Capacity - tapping layer flange
2 Reference condenser CN
3 Schering bridge R3, R4, C4: Bridging elements
7.2. Measurement terminal purpose of use
N: Null indicator
The measuring connection serves for the measurement of the C1 = CNR4 / R3; tan δ 1 = R42πfC4
main capacity C1 of the bushing and the loss factor tan. The most
common test circuit is shown below. Fig. 28: Measuring setup
UN
Cz min C1 1 C2
3 U 2
The values for C1 and C2 can be found in the test report for the
bushing in question.
U
C z C1 N 1 C2 C z min
3 U
P
U N / 3
2
1 7.3. Voltage terminal configuration
Rz a b2
2 The bushing can be provided with a voltage terminal described in
the IEEE C57.19.01 standard. The terminal (pin) is connected to
an internal high-voltage foil of the capacitor. In normal operation,
with: the terminal is earthed through a spring inside the cover.
C2
a 1
C1 Sealing
and
Spring
1
b
C1 Rz Protective
cover
U / 3 cover
U N2 2 a 2 b 2 U 2
a b If the voltage terminal is used with a monitoring system, the
voltage between the terminal and the earth must be limited to 8
kV. Additionally, if there is monitoring, the housing of the voltage
Secondary voltage U2 (300 V or 1.5 kV)
terminal must be filled with transformer oil. To do this, remove the
When using the transition plug type N filling plug on the top side of the housing and fill it with clean dry
or type UHF by ABB, the secondary transformer oil (Fig. 30). Fill until 5 mm below the filling chamber
voltage must be limited to 300 V. to reserve space for expansion (Fig. 31). The thread of the filling
When using an external transition plug, plug should be sealed with an appropriate sealant and locked
the secondary voltage must be limited back with the filling plug.
NOTE
to 1.5 kV.
Fig. 30: Filling the voltage terminal with transformer oil for monitoring
The voltage terminal can also be used to determine the loss factor
and capacity of the bushing online. A connection to the terminal
can be implemented with a suitable connector. The voltage
between the terminal and the earth must be limited to 5 kV, as the
housing of the voltage terminal is not filled with transformer oil.
Hazardous voltage
The measurements are performed using
high voltage. The local safety
regulations of high voltage installation
DANGER must be observed.
The bushing should be lifted at least 1.5 m above ground to reduce Fig. 33: Typical measurement of C1 and tan1
parasitic influences when measuring main capacity C1, capacity
C2 and loss factors tan 1 & tan 2. 8.3. C2 and tan 2 measurement (reference n°1)
The purpose of the measurements is to test the condition of the
bushing. The results must be compared with the ABB test report.
3000 100
6000 200
9000 500
12000 1000
Tab. 5: C1 and tan 1 measurement overview 1000
2000
The values of the measurements shall
3000
be compared with those indicated in
the ABB test report (for 10 kV). 6000
NOTA 10000
1500
2000
DANGER
20 1.00
30 0.85
40 0.77
50 0.75
60 0.77
70 0.82
80 0.90
∆T = T bushing - 20 [°C]
Tab. 9: Tolerances
100
200
500
1000
1500
9.4.1. Capacity C1 and loss factor tan1 Tab. 11: C2 and tan 2 measurement overview
500
1000
2000
3000
100
2000
3000
6000
10000
1. While the measurement, record ambient and oil C 20°C = C measured * (1 - ∆T * 0.0004)
temperature, and calculate the temperature of the condenser 9.7. Site-dependent correction for C1
core:
The measurement of the C1 capacity of installed bushings on site
is always smaller than in the test area. The difference is ∆C inst
T bushing = (2 * T air + T oil) / 3 [°C]
[pF].
Ur ∆C installed
[kV] [pF]
2. With the curve or the table specified below, the
≤ 123 approx. 4
correction factor fc can be determined at the corresponding
ambient temperature, with which tan relative can be calculated ≤ 245 approx. 6
with the following formula: ≤ 420 approx. 8
Tab. 14: Capacity corrections
tan relative = tan measured / fc
These values are based on conservative empirical values. ∆C inst
depending on the type of the bushing and its lower part, the length
of the current transformer (for transformers) can deviate from
these values
20 1.00
50 0.75
+/- 3 % +/- 0.05 % +/- 20 % +/- 0.15 %
(Relative) (Absolute) (Relative) (Absolute)
60 0.77
70 0.82
Tab. 15: Tolerances
80 0.90
Tab. 13: Correction factors If the measured values do not fit with
the set tolerances, please contact High
Voltage Components at ABB
Switzerland Ltd or your local ABB
NOTE partner.
Maintenance
Ans
End of
waranty Service
Prevention of falling accidents, chemical Depending on the damage case, a repairs kit can be provided. For
hazards, cutting injuries, electric shock, this reason, in every case please consult High Voltage
slipping and tripping accidents Components at ABB Switzerland Ltd before repairs.
The work area must be marked and kept
In case of repairs, the surfaces of the interfaces and their
clear.
environment must be cleaned with lint-free cloth soaked in
All the activities must be supervised by a
acetone; alternatively, a narrow piece can be cut out from the
qualified person.
damaged area with a knife to reach a clean surface.
Appropriate climbing aids and
supporting structures should be used.
Apply the repair compound and vulcanize.
The personnel should be authorized to
work at height.
The personnel should have appropriate For further information, please contact
DANGER
training for work with dangerous High Voltage Components at ABB
voltages. Switzerland Ltd or your local ABB
The system is switched-off, secured and partner.
NOTE
tested.
The primary and secondary side of the
transformer or the switchgear is short-
circuited and earthed.
The work can only be started after a
complete electric discharge of the
system.
Wear appropriate PPE.
HLAB200456-AI
High Voltage Components, Micafil Bushings
Badenerstrasse 780
8048 Zurich, Switzerland
www.abb.com/electricalcomponents
Customer Service
Hotline for technical issues, 24h a day including weekends
Mobile: +41 (0)58 586 07 70
E-mail: ch-service.micafil@abb.com
Note
We reserve the right to technical modifications or changes to the
contents of this document without prior notice. In case or placing
orders, the agreed terms and conditions shall apply. We reserve
all rights in this document and the items and illustrations
contained therein. Any reproduction, transfer to third parties or
the utilization of the contents, in part or in whole, shall be
prohibited without the prior approval by ABB in writing.