You are on page 1of 8

ROBIN ANAND PATROL INSPECTION REPORT

INDUSTRIES DRAWING NO
PRODUCT NAME INPUT SHAFT (REGULAR PLUS) DATE

PROCESS 3RD SETUP SHIFT

M/C NO CNC- OPERATOR NAME

INSPECTION ACTUAL OBSERVATION


S NO PARAMETER SPECIFICATION REMARK
METHOD 1 2 3 4

1 OD1 DVC 35.20 +0.1

2 OD-L DVC 91.0±0.1

3 OD 2 DVC 35.30 +0.1

4 OD 2- L DVC 19.0 ±0.1

5 OD 3 DVC 40.30+0.1

6 OD3 -L DVC 24.0±0.1

7 GROOVE OD 1 DVC 29.40 +0.1

8 GROOVE WIDTH DVC 12.0 ±0.1

9 GROOVE DISTANCE DVC 33.0 ±0.1

10 GROOVE OD2 DVC 46.20±0.1

11 GROOVE WIDTH DVC 1.50

12 GROOVE DISTANCE DVC 9.50

13 CHAMFER ON OD1 A.GAUGE 5X30*

14 OTHER CHAMFER A.GAUGE 1X45*

15 VISUAL APPERANCE OPEN EYE OK/NOT OK


CODE = RAI-PI- CYCLE TIME WT BEFORE
REV = 00 IDLE TIME WT AFTER
DATE = 16/08/19 TOTAL TIME
INPECTOR NAME & SIGN- HOD QA-
ROBIN ANAND INDUSTRIES-LUDHIANA
INCOMING INSPECTION REPORT
DRAWING NO

PARTY NAME DATE

CHALLAN/BILL NO ITEM NAME

QUANTITY

INSPECTION ACTUAL OBSERVATION


S NO PARAMETER SPECIFICATION REMARK
METHOD
1 2 3 4

CYCLE TIME WT BEFORE


IDLE TIME WT AFTER
TOTAL TIME

INPECTOR NAME & SIGN- HOD QA-


INPECTOR NAME & SIGN- HOD QA-
ROBIN ANAND INDUSTRIES-LUDHIANA
FINAL INSPECTION REPORT
DRAWING NO

PARTY NAME DATE

CHALLAN/BILL NO ITEM NAME

QUANTITY

INSPECTION ACTUAL OBSERVATION


S NO PARAMETER SPECIFICATION REMARK
METHOD
1 2 3 4

CYCLE TIME WT BEFORE


IDLE TIME WT AFTER
TOTAL TIME

INPECTOR NAME & SIGN- HOD QA-


INPECTOR NAME & SIGN- HOD QA-
ROBIN ANAND INDUSTRIES-LUDHIANA
CUSTOMER RETURN REPORT
DRAWING NO

PARTY NAME DATE

CHALLAN/BILL NO ITEM NAME

QUANTITY

INSPECTION ACTUAL OBSERVATION


S NO PARAMETER SPECIFICATION REMARK
METHOD
1 2 3 4

CYCLE TIME WT BEFORE


IDLE TIME WT AFTER
TOTAL TIME

INPECTOR NAME & SIGN- HOD QA-


INPECTOR NAME & SIGN- HOD QA-

You might also like