TESTING & COMMISSIONING OF FIRE FIGHTING SYSTEM

HOSE REEL & SPRINKLER

The purpose of this procedure is to define the step by step method to implement the correct practices for the pre-
commissioning & commissioning of “Fire Fighting System” through the guidelines contained herein so as to ensure
that the job execution complies with the project requirements and serves the intended Function to satisfactory level.

Pre Commissioning Procedure or Fire Fighting System

1. Ensure that the system installation is complete and mechanical completion is approved.
2. Ensure that no damage has occurred between mechanical completions & pre-commissioning.
3. Repair all damages to the equipment & piping.
4. Check that the Fire Fighting piping network is complete with Fire hose reel, cabinet, pressure gauge, Fire
extinguishers proper valves, drains vents strainers pressure switches instruments & sprinklers drains, vents,
strainers, switches, in place as per Final approved shop drawing.
5. Ensure that the Fire Fighting network is hydraulically pressure tested and approved.
6. Ensure that the entire system is cleaned internally & externally.
7. Ensure that the Fire Fighting pumps are pre-commissioned & commissioned as per approved procedure.
8. Ensure all the pressure switches are installed & wired properly.
9. Ensure that all supervisory isolation valves & sectional control assembly valves are installed & wired.
10. Ensure that all drain valves & vents are installed.
11. Ensure that the identification of all valves & pipework is complete.
12. Ensure the wiring to the Fire Alarm From the pump panel is complete.
13. Ensure that the BMS connections are complete.
14. Ensure that the wiring diagram of pump set controls & schematic piping drawings are displayed near or inside
the pump panel.
Commissioning Procedure for Fire Fighting
System

1. Ensure that all the pre-commissioning checks are carried out successfully.
2. The Fire Fighting system shall be completed tested for proper sequence of operation as defined below.

System Description

1. The Fire-fighting system comprises of 3nos. (2 main & 1 standby) single suction, horizontal multi stage, multi
outlet pumps & 2nos. vertical multi-stage type jockey pumps (one for low zone and other for high zone) to
supply firewater to sprinkler and fire hose systems. All the pumps have dedicated control panel & pressure
switches.
2. The Sprinkler system in the Tower H and J are divided into two zones, low zone and high zone. Low zone
includes Car park and Ground floor to 15th floor of Towers & the High zone includes 16th Floor to roof of
Towers.
3. The Wet riser piping, which supplies Firewater to all hose reels and hose racks, is classified as high zone For
the complete project with PRV For all cabinets. The pre-commissioning & commissioning of Hose racks &
Hose reels shall be in line with the approved procedure

Sequence of operation

High Zone – 16th floor to Roof

1. System pressure will be maintained always at 16 bar. In the event of water consumption in the Fire protection
system high zone areas due to any reasons, the pressure in the high zone system piping will Fall down. When
the pressure reaches 15.00 bar, Pr. Switch HZPS4 will cut in and the high zone Jockey pump (FP-UG-04) will
start. IF pressure in the system piping reaches to the cut out pressure of HZPS4 (16.00 bar), then the high zone
Jockey pump will stop.
2. While the high zone Jockey pump is in operation, if the pressure drops Further to cut in pressure of HZPSI
(14.00 bar), then Main Fire Fighting pump (FP-UG-01) will start and jockey will stop Main Fire FP UG stop.
3. Fighting pump will continue to run till the pressure reaches the cut out pressure of HZPSI (16.0 bar).
4. While the main Fire Fighting pump (FP-UG-01) is in operation and if the pressure drops further to cut in
pressure of HZPS2 (13.00 bar), then t.1ain Fire Fighting pump (FP-{JG-02) will start and both the main
pumps will run. Main Fire Fighting pumps (FP-UG-02 and FP-UG-03) will continue to run till the pressure
reaches the cut out pressure of HZPS1 and HZPS2 (16.0 bar).
5. While both the Main Fire Fighting pumps (FP-UG-01 and FP-IJG-02) are in operation and due to any reasons
any one of the main pump fails to work, if the pressure drops further to cut in pressure of HZPS3 (12.50 bar),
then the Standby Fire Fighting pump (FP-UG-03) will start and both the Main Fire Fighting pump and
Standby Fire Fighting pump will continue to run tilt the pressure reaches the cut out pressure 16.0 bar.

Low Zone – Ground Floor, car park to 15th floor

1. System pressure will be maintained always at 10 bar. In the event of water consumption in the fire protection
system low zone areas due to any reasons, the pressure in the low zone system piping will fall down. When
the pressure reaches 9.00 bar, Pr. Switch LZPS4 will cut in and the low zone Jockey pump (FP-UG-05) will
start. If pressure in the system piping reaches to the cut out pressure of LZPS4 (10 bar), then the low zone
Jockey pump will stop.
2. While the Low zone Jockey pump is in operation, if the pressure drops Further to cut in pressure of LZPS1
(8.00 bar), then Main Fire-fighting pump (FP-UG-01) will start and jockey will stop. Main Fire Fighting
pump will continue to run till the pressure reaches the cut out pressure of LZPSI (10.0 bar).
3. While the Main Fire Fighting pump (FP-UG-01) is in operation and if the pressure drops further to cut in
pressure of LZPS2 (7.00 bar), then Main Fire Fighting pump (FP-UG-02) will start and both the main pumps
will run. Main Fire Fighting pumps (FP-UG-02 and FP-UG-03) will continue to run till the pressure reaches
the cut out pressure of LZPSI and LZPS2 (10.0 bar).
4. While both the .1ain Fire Fighting pumps (FP-UG-01 and FP-tJG-02) are in operation and due to any reasons
any one of the main pump fails to work, if the pressure drops further to cut in pressure of LZPS3 (6.50 bar),
then the Standby Fire Fighting pump (FP-UG-03) will start and both the Main Fire Fighting pump and
Standby Fire Fighting pump will continue to run till the pressure reaches the cut out pressure 10.0 bar.

Demonstration procedure

High Zone

1. The water in the system shall be allowed to drain vide the high zone Alarm Control Valve. This will reduce
the pressure in the system & the jockey pump will start.
2. More water shall be allowed to drain to further drop the pressure, then the Duty pump EP-UG 01will start, the
jockey pump will stop.
3. Upon confirming the start of the main pump, the discharge valve shall be throttled & the pump FP-UG-01 will
not be able to cater to the pressure drop in the system & the other duty pump FP UG-02 will start.
4. The discharge of the pump FP-UG-02 will also be throttled, which will initiate the starting of the stand-by
pump FP-UG-03.
5. The start & stop of the pumps shall be as per the pressure settings.

Low Zone

The Low zone shall be tested in the same way as high zone, but by using the Alarm Control Valve For the low zone.
Sprinkler System

1. The sprinkler system will be tested using the Sectional Control Assembly. The test & drain valve shall be
opened in each zone and the Following shall be verified.
a. Flow switch will activate & give signal to Fire Alarm System
b. Fire Alarm System will induce an audible alarm.
c. Jockey pump will start automatically.

SIGNALS TO BMS PANEL

a. Pump running status.


b. Pump trip status.

ATTACHMENTS

 Pre-commissioning check sheet For Fire Fighting System


 Commissioning check sheet For Fire Fighting System