No Deskripsi No kontrak Nilai kontrak Biaya real Selisih Fee Mandor Total Selisih Keterangan

1 Pulling cable & termination TPSS Kuningan 155 537.683.342 420.000.000 117.683.342 40.326.250,65 77.357.091,35 final account done
2 Remaining Pulling cable Line 3 205A 288.039.456 158.761.989,979 129.277.466,021 21.602.959,2 107.674.506,821 final account done
3 Remaining Pulling cable Line 3 205B 607.737.600 334.973.659,863 272.763.940,137 45.580.320 227.183.620,137 final account done
4 Remaining Pulling cable Line 3 205C 638.712.160 352.046.261,14 286.665.898,86 47.903.412 238.762.486,86 final account done
5 Remaining Pulling cable Line 3 205D 611.223.750 254.218.089,018 357.005.660,982 24.448.950 332.556.710,982 final account done
6 Pulling cable & termination TPSS Dukuh Atas 204 589.007.800 420.000.000 169.007.800 23.560.312 145.447.488 final account done

Total 3.272.404.108 1.940.000.000 1.332.404.108 203.422.203,85 1.128.981.904,15