PTW CRITICAL ROLE- AREA OWNER.

1. HE IS THE PERSON WHO HAS OVERALL RESPONSIBILITY


OF THE SAFETY OF HIS AREA
2. HE IS THE ACCOUNTABLE OF THE SAFETY OF TRE
PEOPLE IN HIS AREA.
3. HE SIGN ON THE CONTRACTOR METHOD STATEMENT
AFTER REVIEVING THE WORK METHODOLOGY AND THE
RISK ASSESSMET ASSOCIATE WITH THIS
4. HE CONFIRMS THAT THE AREA CAN BE HANDOVER TO
THE CONTRACTOR TO PROCEED THE WORK
5. AREA OWNER APPROVE THE PTW EXEMPTION LIST
1. PTW CRITICAL ROLE- ISSUING AUTHORITY.
2. A COMPETENT PERSON POSSESING SKILLS, EXPERIENCE
AND TECHNICAL KNOWLEDGE AND APPOINTENT IN
WRITING TO ISSUE/CNACEL THE PERMIT WITHIN
HIS/HER AREA.
3. BEFORE SIGNING THE PERMIT, CONFIRMS ALL THE
HAZARDS ARE IDENTIFIED AND NECESSARY STEP HAS
TAKEN TO AVOID THEHAZARDS.
4. DISCUSS ALL ASPECTS OF WORKS TO VARIOUS
AUTHORITY FOR SAFE COMPLETION OF WORK
5. BEFORE SIGNING THE PERMIT, HE HAS TO GO FOR A
JOINT VISIT OF SITE WITH RECEIVING AUTHORITY.
6. DISCUSS WITH ALL THE PARTY AND AUTHORITY TO
SECURE THE SAFE ISOLATION.
7. PERIODICALLY MONITOR THE ACTIVITY AND CANCEL
THE PERMIT IF EGA SAFETY RULES ARE NOT
FOLLOWED.
PTW CRITICAL ROLE- RECIEVING AUTHORITY.

1. A COMPETENT PERSON WHO HAS THE EXPERIENCE,


SKILS AND TECHNICAL KNOWLEDGE AND APPOINTED
IN WRITING TO RECEIVE THE PERMIT AND EXECUTE
THE WORK SAFELY.
2. BEFORE GETTING PERMIT HE HAS TO CONDUT A JOINT
VISIT WITH ISSUIENG AUTHORITY.
3. HE HAS TO CONFIRM THAT ALL THE HAZARDS ARE
IDNTIFIED AND NECESSARY PRECAUTION HAS TAKEN
4. HE HAS TO EXPLAIN DETAILS ABOUT THE JOB TO THE
WORK PARTY FOR SAFE COMPLETION OF WORK.
5. CLOSE MONITORING OF THE SITE.
6. IF THE SITE CONDITION IS CHANGE, HE HAS TO STOP
THE WORK.
7. AFTER COMPLETION OF THE JOB TAKE CARE OF THE
HOUSEKEEPING.
PTW CRITICAL ROLE- ISOLATION AUTHORITY.

1. THE ISOLATION AUTHORITY WILL RECEIVE PRACTICAL


TRAINING BY THE AREA OF WHERE THE ISSOLATION
HAS TO CARRIED OUT.
2. RESPONSIBLE FOR ENSURING THE AREA IS SAFE FROM
THE HAZARDOUS ENERGY.
3. HE IS THE RESPONSIBLE PERSON WHO IS SIGNING ON
THE LOTO CERTIFICATE.