SCHEDULE FOR 6TH SEM MCA PROJECT/INTERNSHIP Jan 2021-June 2021)


JANUARY 2021 Project Activity
THURSDAY 21 Semester Started
SATURDAY 30 Project Identification
FEBRUARY 2021 Project Activity
SUNDAY 7 14 21 28 6th – Project Orientation
MONDAY 1 8 15 22 13th – Weekly Review (PROJ) and (INT)
TUESDAY (Submission of Project Abstract)
2 9 16 23 20 – Weekly Review (PROJ) and (INT)
th
WEDNESDAY 3 10 17 24 (Submission of Synopsis – Approval Screening)
THURSDAY 4 11 18 25 27 – Weekly Review (PROJ) and (INT) & Monthly Review 1
th

FRIDAY 5 12 19 26 (Presentation of Final Approved Synopsis)


SATURDAY 6 13 20 27
MARCH 2021 Project Activity
SUNDAY 7 14 21 28 20th – Weekly Review (PROJ) and (INT)
MONDAY 1 8 15 22 29 (Literature Review)
TUESDAY 27 th
– Weekly Review (PROJ) and (INT) & Monthly Review 2
2 9 16 23 30 (Presentation Panel Discussion- 1)
WEDNESDAY 3 10 17 24 31
THURSDAY 4 11 18 25
FRIDAY 5 12 19 26
SATURDAY 6 13 20 27
APRIL 2021 Project Activity
SUNDAY 4 11 18 25 10th – Weekly Review (PROJ) and (INT)
5 12 19 26 24 – Weekly Review (PROJ) and (INT) & Monthly Review 3
th
MONDAY
TUESDAY (Presentation Panel Discussion - 2)
6 13 20 27
WEDNESDAY 7 14 21 28
THURSDAY 1 8 15 22 29
FRIDAY 2 9 16 23 30
SATURDAY 3 10 17 24
MAY 2021 Project Activity
SUNDAY 30 2 9 16 23 8th – Weekly Review (PROJ) and (INT)
MONDAY 31 3 10 17 24 Project Implementation with code and datasets
TUESDAY 15 – Weekly Review (PROJ) and (INT)
th
4 11 18 25 Draft of Journal Article (Mandatory)
WEDNESDAY 5 12 19 26 22th – Weekly Review (PROJ) and (INT)
THURSDAY 6 13 20 27 Draft of Project Dissertation
FRIDAY 7 14 21 28 29th – Weekly Review (PROJ) and (INT) & Monthly Review 4
SATURDAY 1 8 15 22 29 (Final Panel Discussion – 3 Poster Presentation)
JUNE 2021 Project Activity
rd th
3 and 4 June 2021 Tentative External Viva Voce
th
29 May 2021 Poster Presentation / Project Exhibition
(Compulsory)
Note:
1. University Holidays are marked with ‘Color’
2. Review (INT) – means ‘Review for INTERNS’ and Review (PROJ) – means ‘Review for those doing
PROJECT WORK’.
3. For all weekly reviews student has to submit weekly work done report compulsorily.
4. A separate weekly review sheet for each student should be maintained: student copy and guide copy. A
student should sign in guides copy and obtain the signature of the guide in student copy at the same
time.
5. All documents should be kept up to date without any excuse by the student and guide as well. They
should submit the documents whenever asked.
6. Out of 16 weeks a student can take a leave for 2 days (Friday/Saturday) with a prior written permission
from the HOD. Unauthorized absence to any review will be considered seriously and student will be
penalized severely.
7. Documents to be submitted during each review mentioned below. Guides approval for submission of
corrected documents is mandatory.
8. Regular day to day contact with the guide throughout scheduled period is must. Student has to report
to the guide/ higher authorities as and when called without delay. They should not leave the station
without written permission from the HOD. The same should be informed to the Guide.
9. Punctuality in all aspects should be maintained by ALL.
10. Publication of Results of the project as Journal Article is mandatory.

DOCUMENTS TO BE SUBMITTED
SL# REVIEW WORK TO BE COMPLETED / DOCUMENTS TO BE SUBMITTED
1 MONTHLY 1. Approved Abstract
REVIEW-1 2. Approved Synopsis containing – Introduction, Problem Statement, Scope,
Requirements
3. Context Diagram, Sample Dataset, System Architecture, Module-wise
Description
2 MONTHLY 4. System Flowchart
REVIEW-2 5. Data Dictionary, Algorithms, Data structures, ER-Diagram
6. Table structure with constraints
7. Sequence Diagram
8. GUI design
9. Unit and Integration Test Plans
10. Partial Demonstration (60% Implementation should be completed)
3 MONTHLY 11. Complete Implementation and Submission of Executable code
REVIEW-3 12. Test cases for Unit and Integration Tests, Results (Snapshots of Output),
Conclusions
13. Demonstration of the project
14. Submission of Journal Manuscript
15. Submission of FINAL REPORT
4 PROJECT 29th MAY 2021 (COMPULSORY FOR ALL)