You are on page 1of 8

Duane K. Miller, Sc.D, P.E.

the main steel member itself, at a dis-


Introduction tance removed from the connection.
“I specified the use of AWS D1.1 – what
Connections often involve significant
else do you expect me to do?”
changes in load paths. In other cases,
“I don’t know anything about welding connections are the points of highest
– and I don’t want to know anything about load concentration. The method of
welding.” making the connection may introduce
“Maybe I’m supposed to do something stress concentrations. Welding intro-
as it relates to welding, but I don’t have the duces residual stresses, new materials
foggiest idea of what’s right and wrong.” (the deposited weld metal, as well as
Perhaps in jest, maybe with a bit of the heat-affected zones), and potential
intentional sarcasm, or perhaps with an stress raisers. For all of these reasons,
honest expression of a heartfelt atti- the engineer must become involved
tude, in one way or another, all of the with certain aspects of welding in a
preceding have been expressed by en- structural steel system.
gineers working on projects involving Codes and specifications, particu-
Duane K. Miller, Sc.D, P.E., is larly in a mature industry such as steel
the welding of structural steel. Regard-
Manager of The Welding Technology less of a given engineer’s level of expe- construction, do a good job of address-
rience with welding, the AWS D1.1 ing most routine applications. Codes,
Center The Lincoln Electric Com- Structural Welding Code – Steel re- however, will never be able to address
quires the engineer’s interaction on a the issues arising from innovative de-
pany Cleveland, OH. signs that press the envelope of what
variety of fabrication and erection is-
sues. This paper aims to identify exam- was considered by the code writers.
ples of such instances, and to provide Moreover, the code writers identify a
practical insights into the issues that range of options that are applicable
need to be considered when addressing only when specified by the engineer,
circumstances requiring the engineer’s knowing that they are not justified in
participation. all applications. Only the engineer is in
The need for the engineer’s involve- a position to understand the unique de-
ment in welding should not come as a mands upon a new structure, and
surprise to anyone with even a casual therefore, code writers, including those
knowledge of steel construction. Signif- of AWS D1.1, rely upon these individu-
icant effort and resources are expended als to identify specific requirements for
in determining structural systems and unique structures.
member sizes. However, in those few
situations where failures occur, they in- Unfortunate Use of Terms
evitably involve connections, whether Most code users are familiar with
the connections be riveted, bolted, or provisions that “require the approval
welded. Rarely do failures occur within of the engineer” as well as those that

Modern Steel Construction / May 2001


are applicable “when specified by the CONTRACT DOCUMENTS not mean that such prequalified details
engineer”. Unfortunately, in D1.1, The engineer is responsible for the are suitable for all applications. Specif-
sometimes the wording describing the creation of the general contract docu- ically, it states that prequalified joints “.
engineer’s responsibilities is not as de- ments that will govern the fabrication . .have repeatedly demonstrated their
finitive as it should be. and erection of a structure, and devel- adequacy in providing the conditions
The following are just a few exam- opment of the documents that address and clearances necessary for deposit-
ples in which the wording of D1.1 is welding-related issues is no different. ing and fusing sound weld metal to
weak or tentative when addressing the The engineer has the latitude, and the base metal. However, the use of these
duties of the engineer: responsibility, to add to the contract details in prequalified WPSs shall not
• “[All provisions are applicable], ex- documents any provisions not ad- be interpreted as implying considera-
cept those that the engineer specif- dressed in the code, but necessary for tion to the effects of the welding
ically modifies or exempts…” (1.1) the specific project. process on material beyond the fusion
• “The engineer shall use” (2.39.2.1) Six major topics are required by boundary, or suitability for a given ap-
• “…performance shall otherwise be to D1.1 to be addressed in contract docu- plication.” (Subsection 3.1 goes further
the satisfaction of the engineer…” ments, as follows: and states that a prequalified joint de-
(6.27.2) 1) Complete and detailed drawings tail should not be used without the ap-
• “…provided the contractor demon- 2) Determination of whether the struc- plication of engineering judgment).
strates to the engineer … ture is statically or dynamically Provision 2.2.4.3 requires that spe-
“(5.15.4.1) loaded cial joint details be shown on drawings,
• “…when requested by the 3) Inspection issues and special inspection applied to spe-
engineer…“ (5.3.1.1) 4) Alternate acceptance criteria (if ap- cific joints is required to be shown on
• “…shall be brought to the attention plicable) the drawings per provision 2.2.5.
of the engineer…“ (6.27.4) 5) Impact testing (if applicable) Skewed T-joints are required to have
• “…the engineer should evaluate …“ 6) Criteria for welding on existing special details outlined on the draw-
(C 7.6.1) structures (when applicable) ings according to provision 2.11.1.
• “The engineer may choose…“ (C It should be noted that failure to When cyclic loading is applied, subsec-
5.15.4.3) specify some of the above issues results tion 2.21 states that the engineer “. .
As the preceding examples illus- in a default condition that, depending .shall provide either complete details,
trate, it is not sufficient to simply re- on the application, may or may not be including weld sizes, or shall specify
view the code for every mention of acceptable. When the engineer chooses the planned cycle life and the maxi-
“specify” or “approve”. A comprehen- not to address a specific area and the mum range of moments, shears, and
sive understanding of the code is nec- default condition results, the conse- reactions for the connections.” While it
essary in order to make certain that quences must be understood. is not specified that this must be incor-
every interaction the code expects of porated into the design drawings, it is
the engineer is accomplished. the normal convention to do so.
Fortunately, the D1 Structural Weld- Drawings For tubular T-, Y-, or K- connections
ing Committee has recognized the con- Drawings are one of the critical the “Z” loss dimensions (a function of
fusion that could result from the means by which important information the welding process, groove angle, and
unfortunate choice of words and a sys- relating to a specific project is commu- position of welding) are listed in Table
tematic review of the entire code is un- nicated to the parties involved. This in- 2.8. Provision 2.39.2.1 requires that
derway. The goal is to create a more cludes not only data that address the “The engineer shall use [Figure 3.5] in
uniform pattern throughout the code, materials involved, sizes of members, conjunction with Table 2.8 to determine
generally using the terms “when ap- length and locations of welds, etc., but the minimum weld size in order to de-
proved by the engineer”; or, “when also provides the opportunity to in- termine the maximum weld stress . . .”
specified by the engineer”, depending clude notes that communicate detailed For evaluating the suitability of spe-
on the nature of the provision. approaches to be used when fabricat- cific joint details, whether prequalified
ing the affected member(s). or not, the commentary to provision
THE ENGINEER’S INVOLVEMENT Drawings, whether physically pre- 2.1.3 is especially helpful. Lamellar
The code invokes the engineer’s in- pared by the engineer or by a detailer, tearing in particular is discussed in
volvement in the construction process or even when prepared by the contrac- great detail, providing valuable insight
in a variety of manners, but in general, tor, are ultimately the engineer’s re- into preferred practices.
the engineer’s responsibilities can be sponsibility and are a key ingredient in
placed into one of five categories as any successful project. Static versus Cyclic Loading
contained below: D1.1 has a specific subsection (2.2) D1.1 contains criteria for both stati-
1) The engineer establishes basic con- entitled “Drawings” that details most cally and cyclically loaded members.
struction contract documents. of the requirements. Provision 2.2.1 re- Nowhere in the code is there a direct
2) The engineer specifies that certain quires that the drawings contain “full statement requiring the contract docu-
options in the code are to be applied and complete information regarding ments to specify whether the structure
to the project. location, type, size, and extent of all is statically or dynamically loaded, but
3) The engineer approves various as- welds…” Field and shop welds are to there are provisions that imply this re-
pects of the construction process. be distinguished from each other. Pro- quirement. It is undebatable, however,
4) The engineer evaluates and may ap- vision 2.2.2 requires that weld joints re- that somehow this must be communi-
prove alternatives submitted by the quiring careful attention to welding cated to those involved in the construc-
contractor . sequence be so noted. Provisions 2.2.3 tion process. Provision 2.1.1 requires
5) The engineer addresses unexpected and 2.2.4 spell out specific require- that the “base-metal stresses shall not
fabrication difficulties. ments for different weld types; and exceed those specified in the applicable
2.2.4.2 warns that just because a weld design specifications.” Provision 2.1.2
detail may be prequalified, this does warns that any increase in allowable

May 2001 / Modern Steel Construction


stress not be extended “to the stress The code provides three bases for should not obscure the relative roles of
ranges permitted for base metal or qualification of inspectors in provision the engineer and the inspector.
weld metal subject to cyclic loading.” 6.1.4.1, which also states that, “If the
Since otherwise identical steel mem- engineer elects to specify the basis of Alternate Acceptance Criteria
bers can be applied to both statically inspector qualification, then it shall be D1.1 is a workmanship standard,
and cyclically loaded applications, and so stated in contract documents.” Pro- not a fitness-for-service document. This
yet the fabrication conditions are dif- vision 6.1.4.5 authorizes the engineer to attitude is conveyed in the Commen-
ferent, this detail must be communi- verify the qualification of inspectors. tary where C5.1 states “The criteria
cated to the contractor; contract As previously mentioned in the sec- contained in Section 5, are intended to
documents are the appropriate vehicle tion on drawings, provision 2.2.5 re- provide definition to the producer, su-
for this purpose. quires “any special inspection pervisor, engineer and welder of what
requirements” to be noted on the draw- constitutes good workmanship during
ings or in the specifications. fabrication and erection.” This is fur-
Inspection ther amplified upon in C6.8, which
For those who think the engineer When the engineer specifies radi-
ographic inspection (RT), he/she may says, “The criteria in section 5 should
has no welding-related role in steel not be considered as a boundary of
construction, consider this: when the need to approve alternate locations for
image quality indicators (IQIs) [Figures suitability for service. Suitability for
engineer specifies nothing regarding service analysis would lead to widely
inspection in the contract documents, 6.11 - 6.14 and C6.17.7] , as well as al-
ternate radiographic sources (C6.17.6). varying workmanship criteria unsuit-
all that he/she will get is visual inspec- able for a standard code.” The code
tion, performed by the contractor’s in- Ultrasonic inspection (UT), when
specified by the engineer, raises a num- does permit the engineer to specify al-
spector. There will be no ternate acceptance criteria (provision
nondestructive testing, no independent ber of opportunities for the engineer’s
involvement. For example, annex “K” 6.8), providing they are “suitably docu-
verification inspection – just the code- mented by the proposer and approved
mandated visual inspection performed contains alternate techniques for UT of
welds, but the use of the annex proce- by the engineer.” The proposer could
by (typically) an employee of the con- be the engineer, and this can be speci-
tractor. dures is subject to approval by the en-
gineer. Annex “K” allows for fied in the contract documents. As will
Should the engineer subsequently be discussed later, the proposer could
elect to perform some nondestructive inspection of welds beyond the condi-
tions stated in part “F” of Section 6, and be the contractor, in which case the en-
testing when it was not originally spec- gineer would be called upon to evalu-
ified in the contract documents, then includes variations such as other weld
geometries, transducer sizes, frequen- ated and approve the suitability of the
the owner “shall be responsible for all alternate criteria.
the associated costs including han- cies, couplants, painted surfaces, and
testing techniques, but such variations The alternate criteria can be either
dling, surface preparation, nondestruc- more or less demanding than the stan-
tive testing, and repair of the must be approved of in the contract
documents, according to 6.20.2. dard criteria in the code. More
discontinuities at rates mutually agree- demanding criteria may be important
able between the owner and the con- For T-, K-, and Y- tubular connec-
tions, and when such joints are to be ul- for new and unproven designs, higher
tractor,” according to provision 6.6.5. strength materials, extremely thick
The only relief afforded the owner is trasonically inspected, provision 6.27.1
requires that, “Prior to use on produc- material, very rigid structures, extreme
that, “If such testing should disclose an operating temperatures, high loading
attempt to defraud or gross nonconfor- tion welds, the procedure and accept-
ance criteria shall be approved by the conditions, applications involving little
mance to this code, repair work shall be redundancy, and other factors.
done at the contractor’s expense.” A engineer . . . ” The acceptance criteria
for all tubular connections is to be iden- Conversely, well understood applica-
much better situation exists if the engi- tions with a long history of satisfactory
neer considers inspection issues where tified in the contract documents, ac-
cording to provision 6.13.3. performance may be instances where
the contract documents are being cre- the engineer would use the option of
ated. Part G of Section 6 deals with “other
examination methods,” permitting the 6.8 to permit less rigorous acceptance
In provision 6.1.1, the code requires criteria, providing their use can be
that nondestructive testing (NDT) use of less conventional nondestructive
testing methodologies. Subsection 6.34 justified.
requirements be stated in the bid docu-
ments, including the types of welds to requires that all NDT methods in part
G have “specific written approval of Impact Testing
be examined, the extent of examina- Provision 4.1.1.3 states: “When re-
tion, and the method or methods of the engineer.” The code recognizes ra-
diation imaging systems, including quired by contract documents or speci-
testing. The code automatically fications, impact tests shall be included
requires fabrication/erection inspec- real-time imaging, and such NDT may
be used when so approved by the engi- in the WPS qualification. The impact
tion, which are the responsibilities of tests, requirements, and procedures
the contractor unless the contract docu- neer, in conformance with provision
6.35.1. Provision 6.35.2 outlines twelve shall be in conformance with the provi-
ments indicate otherwise. The engineer sions of Annex III, or as specified in the
is obligated in 6.1.2.2 to determine specific essential variables that are to
be addressed in the written procedures. contract documents.” Annex III con-
whether verification inspection is tains a variety of details regarding the
required – the type of inspection that is The specifics of many of the nonde-
structive testing techniques may be location of the Charpy impact testing
independent of the contractor, and the specimen, the number of required
results of which are reported to the quite foreign to the typical Structural
engineer, but the independent testing specimens, the procedures of retests
engineer. Provision 6.1.2.2 permits the and other details. What is not con-
engineer to waive verification inspec- laboratories that commonly are
charged with executing these assign- tained therein, however, is the testing
tion, perform all inspection functions temperature or the minimum average
with the verification inspector, or use ments are usually highly cognizant of
these details and can provide the nec- energy level. Annex III 1.3 makes this
both fabrication/erection and verifica- the responsibility of the engineer. Also,
tion inspection. essary help for such situations. Re-
liance on these other experts, however, the engineer is to “consider the effects
of welding position as it may relate to Visual inspection is required for the
heat input on the heat-affected zone work performed to strengthen or repair
(HAZ) test results….” a structure, in accordance with provi-
The role of impact properties, frac- sion 8.6.1. However, such visual in-
ture toughness, and the requirements spection is also subject to conforming
for minimum specification of proper- with the “engineer’s comprehensive
ties as they relate to these issues is be- plan.” Nondestructive testing criteria
yond the scope of this paper. Excellent are required to be specified in contract
references are available that address documents as well (8.6.2).
the complex issues involved. (2.) How- Strengthening existing structures is
ever, the engineer must understand a challenge. Repairing damaged struc-
that, when no impact requirements are tures is an even greater challenge. Per- Figure 1
specified in contract documents, there forming such procedures on structures lows: “for cyclically-loaded non-tubu-
is no minimum level of notch tough- with materials that were not welded in lar connections, there shall be no tem-
ness that can be assumed for the weld the first place compounds the problem porary welds in tension zones or
metal, heat-affected zone, or the base further. Under such circumstances, the members made of quenched-and-tem-
metal. engineer should seek out the experts pered steels except at locations more
with experience in this particular field. than 1/6 of the depth of the web from
Welding on Existing Structures These unique situations are prime ex- tension flanges of beams or girders…”
When one is strengthening and re- amples of circumstances that codes For architecturally exposed steel, or for
pairing an existing structure, the num- cannot be expected to address suffi- other conditions of dynamic loading,
ber of situations that conceivably could ciently. Job-specific specifications need such temporary welds may be unac-
be encountered is practically endless. to be developed by the engineer in ceptable. In such circumstances, the en-
Thus, it is impossible for any code to order to address these unique circum- gineer can specify their removal.
provide specific requirements applica- stances. Tack welds are to be incorporated
ble to every situation that could arise. into the final welds. Provision 5.18.2.3
D1.1 Section 8 is devoted to the subject requires that tack welds not incorpo-
OPTIONS TO BE ORDERED rated into the final welds be removed.
of welding on existing structures, and
so issues requiring the engineer’s in- BY THE ENGINEER This provision, however, does not
volvement are concentrated in this sec- The code tries to provide general re- apply to statically loaded structures,
tion for this topic. The specific plans quirements that are applicable to most unless required by the engineer. With-
drawn up by the engineer constitute situations. There are other conditions out the engineer’s involvement, there-
the means by which the code writers that are made available as “options” to fore, tack welds need not be
have addressed these situations. the engineer, fully described, but not incorporated, and they need not be re-
D1.1 Section 8 obligates the engi- made universally applicable. Rather, moved from statically loaded struc-
neer to prepare “a comprehensive plan the code relies upon the engineer to de- tures. This may be undesirable for
for the work”, with plans that include termine when these options should be architecturally exposed steel, and may
“but are not limited to, design, work- specified for a specific application. not be considered a conservative ap-
manship, inspection, and documenta- Such specification is typically done in proach for higher-strength steels.
tion” (8.1). The base metal type used in the contract documents. There are no secondary members in
the original structure is to be deter- 1) Options that the engineer may spec- welded design, and therefore, attach-
mined before drawings and specifica- ify fit into four categories: ments such as steel backing may affect
tions are developed (8.2.1), and the 2) Structural details the performance of the overall struc-
suitability of welding of the base metal 3) Certifications for welding materials ture. Provision 5.10.4 requires the re-
is to be established (8.2.2). For base 4) Qualification of weld details moval of backing from joints that are
metals other than those that are pre- 5) Stud welding activities transverse to the direction of computed
qualified and listed in Table 3.1, “Spe- stress, but permits steel backing of
cial consideration by the engineer must Structural Details welds that are parallel to the direction
be given to the selection of filler metal There are a variety of structural de- of stress to stay in place, unless their re-
and WPSs” (8.2.3). tails that the engineer may elect to re- moval is specified by the engineer
Provision 8.3.5 requires that, “The quire for a specific project. What is an (5.10.4). Additionally, the longitudinal
engineer shall determine the extent to acceptable detail for one type of struc- welds that attach backing are required
which a member will be permitted to ture may not be acceptable for another. to be welded full length for cyclically-
carry loads while heating, welding, or The type of loading may be a major fac- loaded structures, but for statically-
thermal cutting is performed.” tor in determining such acceptability. loaded structures, provision 5.10.5
If fatigue life enhancement is re- The engineer must evaluate these de- permits intermittent welds, and allows
quired, provision 8.4.1 identifies meth- tails and the structural requirements all the backing to stay in place, regard-
ods that can be used, when approved and order the optional details appro- less of the direction of loading, unless
by the engineer. The engineer is obli- priate for the specific application. required to be removed by the engi-
gated to determine appropriate in- Provision 5.18.1 requires that tem- neer.
creases in the allowable stress range, porary welds be made to the same Weld tabs permit groove welds to be
according to 8.4.2. When members are quality criteria as final welds. Even made in a manner that will ensure
to be “heat straightened”, the provi- though the quality should be the same weld soundness to the end of the joint.
sions of 8.5.5 apply; and, additionally, as a final weld, when the engineer so
requires, the temporary welds are to be
Visit InfoExpress No. 48
8.5.2 requires the engineer to determine
whether unacceptable discontinuities removed. Conversely, when the engi- at www.modernsteel.com
are to be repaired prior to heat straight- neer does not require their removal, Provision 5.31.2 permits weld tabs to
ening or welding. they may remain in place except as fol- remain in place (and this is typical

May 2001 / Modern Steel Construction


practice) unless the engineer requires will permit the structure to perform in New Materials and Processes
them to be removed. Aesthetics may its intended manner. The code provides for methods of
dictate their removal, and AISC re- Approval or denial of these alterna- allowing new welding and cutting
quires the removal of weld tabs from tives may significantly affect the con- processes, new base metals and new
jumbo section splices (AISC LRFD J15). tractor’s cost. Not knowing whether an filler metals. New developments will
When removal is required as in these alternative will be approved or not always precede code changes that re-
examples, D1.1 stipulates that the engi- places a contractor in a difficult posi- flect such advances. If such provisions
neer must specify it. tion during the bidding process. To did not exist, progress would be im-
eliminate this risk, some contractors peded as innovations are put “on-
Certification of Materials will submit bids contingent upon ap-
If the engineer desires certification hold,” waiting for incorporation into
proval of certain code-permitted alter- the governing specifications.
of certain welding materials, these natives that are subject to the
must be requested. This would include The code lists welding processes
engineer’s approval. In accepting the that may be used for prequalified
welding filler materials (5.3.1.1), weld- bid, the engineer agrees to also ap-
ing shielding gas (5.3.1.3), and welding WPSs, as well as welding processes
prove such alternatives. If the contract that may be used for construction
stud certification (7.3.3). is modified later, the contractor is then under the code. The code further ex-
in a position to renegotiate the financial tends the opportunity for the use of
Qualification of Welding Joints aspects of the project. other welding processes, when the en-
The weld throat in a flair groove Sometimes, after the contract is let, gineer (3.2.3, 4.15.2) approves these
weld is dependent upon the actual cost-saving alternatives are identified other methods. Alternate processes
groove geometry and the welding pro- which still require the engineer’s ap- could involve a variety of new or dif-
cedures employed. As such, provision proval. In order to make the situation ferent controls that need to be moni-
4.10.5 permits the engineer to order into a ‘win-win’ proposition, “value- tored, and the evaluation of such
tests that are used to verify that the re- engineering” can be applied, and the variables is part of the alternate process
quired weld throat is consistently ob- savings divided between the contractor approval activity.
tained. The engineer must specify the and the owner. Regardless of any pos- The code approves specific thermal
extent of testing, the sizes of members sible financial incentives, the integrity cutting processes including electric arc
involved, etc. of the project cannot be sacrificed. cutting and gouging, and oxyfuel cut-
In most situations, the contractor ting. Provision 5.15.4.1 permits other
Stud Welding Operations makes the request to the engineer to thermal processes to be used for cut-
The engineer has a variety of op- approve an alternative. When the op- ting, provided the engineer approves
tions with regard to stud welding. Pro- tion is not granted, a default position the method.
vision 7.3.5 allows the engineer to exists and the project can progress ac- The code lists various base metals
select the studs that will be used for cordingly, utilizing the standard prac- that can be used for construction, but
testing. The studs are supplied at the tice identified in the code. materials that are not listed in Table 3.1
contractor’s expense, although the test- There is one known exception to the or Annex M can be used if the WPSs
ing is done at the owner’s expense. Re- general pattern where the default posi- are qualified by test, and are approved
garding stud bases, 7.2.4 permits the tion exists: provision 4.1.1 requires the by the engineer (4.7.3).
engineer to request descriptive infor- engineer to approve WPSs that have
mation on the stud and arc shield, cer- been qualified by test, and if the WPSs
tification from the stud manufacturer are not approved, there is no default Routine Items
regarding the stud base qualification, status presented in the code. Provision While nothing should be viewed as
and qualification test data. In all of 4.1.1 clearly states that this is applicable truly routine, the code contains some
these situations, the engineer must to WPSs that are qualified by test, and a provisions that are generally accepted
evaluate the option’s significance and similar, clear-cut statement cannot be by engineers for most projects, and
relative applicability to a specific proj- found in Section 3 regarding welding these have been placed into this cate-
ect. There is generally some degree of procedures that are prequalified. This gory.
cost associated with these activities, topic has been previously discussed All welders, welding operators, and
and therefore, the Committee has not (see Funderburk & Miller, 1998) and tack welders who perform work gov-
chosen to make them universally appli- further details are beyond the scope of erned by the code must be qualified by
cable. It is the engineer’s obligation to this paper. In this situation, the engi- test as prescribed in the code. In most
determine when and where such op- neer must approve the WPS qualified situations, contractors will have previ-
tions should be applied. by test in order for welding to begin. ously qualified their work force in
When the engineer is called upon to other projects, and the code extends to
APPROVALS approve a request made by the contrac- the engineer the option of approving
The engineer is required to make a tor, it typically fits into one of the fol- the use of previous personnel qualifica-
significant number of evaluations of al- lowing general categories: tion tests, eliminating the need for re-
ternatives that the code permits. These 1) New materials and processes not testing (4.1.2.1).
are generally in response to requests by covered by the code. The engineer’s involvement in ap-
the contractor. Issues that require the 2) Routine items that are generally ap- proving the qualifications of personnel
engineer’s approval are concentrated proved but should be critiqued for goes beyond welders, and includes in-
in D1.1 Section 5, although such items anomalies. spectors (6.1.4.5).
are dispersed throughout the code. The 3) Practices that need careful review to Stud welding is covered in Section 7
relative suitability of these various al- make certain they are appropriate of the code, and there are a number of
ternatives must be considered by the for the application. situations where the engineer may be-
engineer, always with an eye to 4) Practices that may or may not be ac- come involved. Provision 7.2.1 permits
whether the alternatives being sought ceptable, depending on the specific alternate stud head configurations,
application. when approved by the engineer. Provi-

Modern Steel Construction / May 2001


sion 7.3.4 permits the use of studs that “agreed upon by the engineer and the dures that have been previously quali-
do not have quality control tests pro- fabricator.” fied, and can also approve the use of
vided the manufacturer of the studs standard welding procedures as pub-
performs mechanical tests. The engi- Practices Requiring lished in AWS B2.1.XXX-XX. In most
neer is to determine the number of tests Careful Review cases, the acceptance of previously
to be performed. To prove the suitabil- The following options need careful qualified welding procedures is a rou-
ity of stud welding procedures, “bend review since the test data that is re- tine practice, providing that these
tests” are performed and often can be quired to support these alternatives WPSs have the proper documentation,
used in the bent condition. When may not be applicable to the specific and are applicable to the proposed
straightening is required, provision project involved. In other words, the work. The use of standard welding
7.8.3 requires that it be done without tests may accurately demonstrate the procedures, a new provision in D1.1-
heating, except as otherwise provided capability of a concept to work under 2000, can be reviewed with the same
in the contract, and as approved by the test conditions, and yet it may not per- scrutiny, except that the supporting
engineer. form under actual fabrication condi- PQRs would not be available to the en-
When performing reduced section tions. This warning should not cause gineer for review. However, the AWS
tension tests, and when the steels in- the engineer to automatically reject B2 Committee has performed this task
volved are high strength, some tensile such options. Rather, they need to be already, simplifying the process, and
testing machines may be incapable of carefully reviewed, with the assistance perhaps adding another level of assur-
pulling the high strength specimen to of a consulting expert if necessary, to ance to the sequence.
destruction. Under these conditions, ensure the expected results will be Preheat for welding is an essential
Figure 4.14, Note 8, permits changes to achieved. variable of a WPS, and the code pro-
the specimen dimensions when According to provision 4.1.1.2, the vides minimum levels of preheat for
engineer can accept welding proce- prequalified WPSs. The code extends
the option of reduced preheats, based
upon the use of Annex XI; or, for SAW
welding,when hardness checks are
made in the HAZ. Also, WPSs could be
qualified by test with a reduced pre-
heat. In all three of these cases, the en-
gineer must approve the reduced
preheat before it can be used in pro-
duction (3.5.2, 3.5.3, 4.1.1).
The required level of preheat for a
project is a function of many variables,
including the actual composition of the
steel being used, the degree of restraint,
and the hydrogen content of the de-
posited weld metal. These conditions
may not be replicated under testing
conditions. Restraint is almost never
replicated with small test specimens,
and the engineer should carefully re-
view supporting data for the reduced
preheats in order to make certain that
the tests adequately represent the con-
ditions that will be encountered in pro-
duction.
Alternate acceptance criteria, previ-
ously discussed above under “Contract
Documents,” may also fit into the ap-
proval category when someone other
than the engineer proposes the alter-
nate criteria. Such options are ad-
dressed in subsection 6.8, and
provision 6.5.5. The code makes such
alternate criteria acceptable, providing
that certain stipulations are met, and
that the engineer approves of the alter-
native.

Practices That May or


May Not Be Acceptable
The acceptability of application-spe-
cific provisions may depend on the
structure, loading, specific location
within the structure, or other factors. It
is not a matter of “good practice” or
Table 6.1. Reprinted with permission of the American Welding Society, from AWS
D1.1: 2000, Structural Welding Code-Steel.
“bad practice,” but rather, what is right quires that the inspector check to make Provision 5.15.1 permits removal
for the particular conditions involved. certain “that no unspecified welds and repair of mill-induced discontinu-
Specific roughness requirements for have been added without approval.” ities on the surface of the material. The
various thermal cuts are outlined in While a citation to the engineer is not discontinuity is required to be removed
5.15.4.3, and gouges that exceed those made, 1.2 states that “the need for ap- and all welded repairs are required to
limits can be repaired under the provi- proval shall be interpreted to mean ap- be done in accordance to the code. The
sions of 5.15.4.4, which ends by stating proval by the building commissioner total length of repair welding may not
“In thermal-cut surfaces, occasional or the engineer.” exceed 20% of the length of the plate
notches or gouges may, with approval Weld tabs are required by 6.17.3.1 to surface being repaired, except with the
of the engineer, be repaired by weld- be removed prior to radiographic in- approval of the engineer. For edge dis-
ing.” The commentary applied to these spection unless otherwise specified by continuities that are discovered on cut
provisions specifically addresses the the engineer. material, provision 5.15.1.1 provides
topic of “occasional notches and For cyclically loaded structures, specific levels of acceptability and re-
gouges” by stating that the Committee thermal cutting is to be done in a mech- pair practices. If these limits are ex-
“refrained from assigning any numeri- anized or automatic manner unless the ceeded, the part “shall be rejected and
cal values on the assumption that the engineer approves of free-hand thermal replaced, or repaired at the discretion
engineer, being the one most familiar cutting 5.15.4.2). of the engineer.”
with the specific conditions of this During weld inspection, discontinu-
structure – will be a better judge of UNEXPECTED CIRCUMSTANCES ities in the base material may be ob-
what is acceptable. The engineer may Irregularities that may occur during served. Provision 6.20.4 deals with UT
choose to establish the acceptance crite- a project often present undesirable cir- inspection and requires that base metal
ria for occasional notches and gouges.” cumstances for both the contractor and discontinuities such as cracking, lamel-
Caulking involves the mechanical, the engineer, but they must be resolved lar tearing and delaminations that are
plastic deformation of weld metal and in order for the project to move ahead. discovered adjacent to the weld be re-
base metal and historically has been Time is of the essence, since while the ported to the engineer for disposition.
prohibited by the code since it can be engineer is evaluating such situations, For UT inspection of T-, Y-, and K- con-
used to fraudulently mask weld dis- projects are typically put on hold, re- nections in tubular steel, base metal
continuities. D1.1:2000 was changed to sulting in delays. Unlike situations in discontinuities detected are required to
permit caulking under certain condi- which the code has provided a default be “brought to the attention of the en-
tions because it may prevent failure of alternative, these circumstances require gineer or inspector.”
various coatings that are subsequently the engineer to act. Efforts at mutual
applied. Weld inspection must be com- cooperation on the part of the contrac-
pleted prior to the caulking treatment, Fit-up and Alignment Problems
tor and the engineer will facilitate When steel is assembled, fit-up be-
and “the technique and limitations on progress in difficult circumstances.
caulking are [to be] approved by the tween adjacent members may not be
When unexpected construction dif- what was expected on the drawings.
engineer” (5.28). ficulties arise, and when such difficul-
s various base metals that can be Such misalignment may be the result of
ties are potentially significant to the poor workmanship. It can also result
used for construction, but materials project and the performance of the
that are not listed in Table 3.1 or Annex from the accumulation of acceptable
structure, it is important for the engi- tolerance variations, whether in the as
M can be used if the WPSs are qualified neer to obtain the necessary technical
by test, and are approved by the engi- received materials, or in the fabricated
guidance in order to perform the code- pieces, resulting in dimensions that ex-
neer (4.7.3). mandated obligations. This expertise
Provision 6.5.6 requires the inspec- ceed code limits. Such variations may
frequently comes from consultants have no effect on the final structures
tor to identify parts that have been in- who have unique expertise in dealing
spected and accepted, but the method behavior, but in other situations, such
with such problems. differences may be critical. The engi-
of identification is not defined. How- Unexpected issues requiring the en-
ever, “die stamping” cannot be used on neer must make this evaluation.
gineer’s involvement fit into these cat- Provision 5.22.3.1 provides specific
cyclically loaded members, unless ap- egories:
proved by the engineer. girth weld alignment requirements for
1) Base metal discontinuities tubular members; additional tolerance
Provision 5.21.3 requires a distor- 2) Fit-up and alignment problems
tion control plan where “excessive relief is available for this alignment,
3) Welding problems when approved by the engineer.
shrinkage or distortion can be ex- 4) Post-welding corrections
pected.” The plan is to be submitted to Specific acceptable tolerances for
the engineer “. . . for information and groove weld root openings are given in
Base Metal Problems provision 5.22.4.3. If these tolerances
comment” before welding is per- During fabrication and erection, dis-
formed on the member in which the ex- are exceeded, they may be corrected by
continuities in base metals may be de- welding, but only when approved by
cessive shrinkage or distortion is tected. The shrinkage stresses induced
expected. The code provides no “de- the engineer (5.22.4.4).
by welding are significant, and crack-
fault” position for the condition when ing or lamellar tearing may result. Cut-
the engineer does not supply com- ting of plates or shapes may expose Welding Problems
ments, nor is there a code-defined time- internal discontinuities within the base A crack in a weld, or in the adjacent
frame, or method for communication metals. Such discontinuities may or base metal, is a very serious issue that
of such comments. may not affect the performance of the needs to be addressed. The causes or
In addition to ascertaining that all final structure, and as such, the code re- implications of such cracking need to
required welds have been placed in the quires the engineer to evaluate any be understood, and the potential im-
proper location and are of the required non-routine imperfections in the base pact on the structure evaluated. When
size and length, provision 6.5.1 re- metal. major cracking occurs, the engineer is
to be notified so such an evaluation can applied in order to correct for camber Funderburk, R.S., and Miller, Duane
take place. variations. Provision 5.19.1 permits K., “Reviewing and Approving Weld-
When base metal is damaged be- such adjustments, but 5.19.2 requires ing Procedure Specifications,” AISC
cause of faulty welding, or when the that any corrections in the camber of National Steel Construction Confer-
base material is damaged by removal quenched-and-tempered steel mem- ence Proceedings, April 1-3, 1998, New
Orleans, pages 24-1—24-25.
of faulty welds for re-welding, and the bers be done only with the approval of
base metal is no longer “in accordance the engineer.
with the intent of the contract docu- Provision 5.26.2 prescribes the tem-
ments, the contractor shall remove and perature limits for heat straightening,
replace the damaged base metal or and quenched-and-tempered steels
shall compensate for the deficiency in have a lower approved temperature
a manner approved by the engineer” limit (1100ºF) than other steels (1200°F).
(6.6.3). This requires more careful monitoring
Provision 5.26.3 requires the engi- of the steel and thus requires the engi-
neer’s approval for “repairs to base neer’s involvement.
metal . . . repairs of major or delayed
cracks, repairs to electroslag and elec- Conclusion
trogas welds with internal defects, or As the preceding has demonstrated,
for a revised design to compensate for there are a host of situations that may
deficiencies.” This provision is in place require the engineer to become in-
because such defects can have a major volved with the construction process as
impact on the performance of the struc- it relates to welding. This involvement
ture and the repair techniques to deal can range from nearly routine events to
with such problems may be complex in major unexpected occurrences with po-
and of themselves. tentially monumental consequences.
When electroslag welding is per- The Structural Welding Code relies
formed, and if the welding is inadver- upon the engineer to use engineering
tently stopped, and then restarted, judgment in determining how specific
such restarts are required by Provision issues are to be addressed for individ-
5.4.4 to be reported to the engineer. ual applications. Particularly challeng-
Other criteria apply to these conditions ing circumstances may dictate that the
as well, including radiographic inspec- engineer consult with experts in the
tion. field in order to properly evaluate the
When unacceptable welds are situation and determine the correct
made, and further work is performed course of action to follow.
which makes access to the original de-
fective weld impossible, a plan must be DISCLAIMER
established to address the problems. If An attempt was made to compre-
the members are not cut apart in order hensively identify circumstances cited
to gain access to the original weld, the within AWS D1.1-2000 where the engi-
deficiency in the original weld “shall neer is required to interact in the fabri-
be compensated for by additional work cation and erection processes that
performed according to an approved, relate to welding. It is possible and
revised design” (5.26.4). The engineer even probable that provisions have
is responsible for this approval, consis- been missed. The author welcomes
tent with subsection 1.2. feedback regarding items that may
have been missed, and also strongly
Post-Welding Corrections encourages the user of this information
Before steel is cut apart for any rea- to perform his/her own independent
son, 5.26.3 requires that the engineer be review of the entire code to address all
notified. This is particularly important the issues that may be applicable to a
for structures during the erection stage, specific project. While the author is a
since the member being cut may be member of the AWS D1 Committee,
performing critical load-bearing func- opinions and views expressed in this
tions at that time. article are his alone, and not those of
When holes are mislocated, provi- the AWS D1 Structural Welding Com-
sion 5.26.5 provides a detailed se- mittee.
quence that must be followed. The
engineer must approve such proce-
dures when the base metal is subject to References
cyclic loading. In many cases, it is pre- American Welding Society. Struc-
ferred to leave the mislocated hole in tural Welding Code—Steel: AWS
place since welding under these condi- D1.1:2000, 17th ed., Miami, FL, 2000.
tions frequently introduces weld de- John M. Barsom and Stanley T.
Rolfe, Fracture and Fatigue Control in
fects that may be more harmful than Structures: Applications of Fracture Me-
the hole itself. chanics, 3rd ed., West Conshohocken,
When camber is incorrect on a built- PA: American Society for Testing and
up member, heat straightening can be Materials, 1999.

You might also like