You are on page 1of 4

Opinion

Climate emergency
Planning application
Reusingprocedures
foundations

4.Zero waste team. The structural and geotechnical


designers will need to work closely
together on the engineering aspects,

A short guide to
alongside the client, contractor and third
parties such as Building Control or future
owners/tenants.
Generally, building refurbishments

reusing foundations
are carried out after original design/
construction defects periods or
warranties have expired. However,
for more recent buildings, it may be
possible to approach the original team
to extend the period and take on the
Henry Tayler takes readers through the key considerations for risk of performance under new loading.
reusing foundations, including potential benefits, risks and For older projects, it may be most
investigations required. effective to approach the original design/
consultant team for engineering advice
and assistance locating any archive
information, if this is possible.
Introduction and materials, together with improved Where limited information is available
Almost 15 years since the construction project sustainability credentials. on existing foundations, it is common
industry began developing guidance Space added to existing structures practice for the project team or original
on foundation reuse, Arup has been can make an attractive development designer/contractor to carry out a due
overcoming perceived and real difficulties opportunity, particularly when combined diligence review and foundation reuse
to successfully apply this approach on with improvements to fit-out within the assessment. However, this ultimately
projects. This article shares some typical existing structure. requires the client to hold the necessary
opportunities for reusing foundations, Arup has recently completed insurance for the performance of reused
risk management processes and options a significant refurbishment and structural elements for the new design
if limited archive/record data is available. foundation reuse project at 1 Triton life. It is important that responsibilities
Square, London, enabling savings of and insurance needs are identified
Opportunities an estimated 35 000t of concrete, early to allow for engagement with the
As existing building stock moves 840t of reinforcement and 340t of insurance market and any independent
towards modern desired standards, the steel, targeting a BREEAM outstanding engineering review by insurers or
opportunity for building refurbishment classification (Box 1). Reuse of the piled development investors.
over demolition and rebuild has never foundations contributed approx. 25% of
been more present. Chapman et the reused structure. Typical reuse considerations
al.1 highlighted that the presence of Boxes 2–6 provide further examples A successful foundation reuse scheme
old foundations in the ground is an of foundation reuse on projects. depends on the relationship between the
increasing problem and will ultimately existing configuration and future needs,
inhibit future development on valuable Design responsibility particularly:
urban sites. and insurance | building height/number of storeys and
Reuse of key structural elements To reuse existing foundations, the risks massing
such as foundations can lead to need to be identified and addressed | structural grid and core provision
significant savings in cost, programme at an early stage by the whole project requirements, including fire and
escape requirements
| existing use in relation to proposed
use (floor-to-ceiling height and
Box 1. 1 Triton Square, London loading)
| ability of the foundations to support
The scheme to modify the 1995 structure additional or different loading
storey
added three storeys and a five-storey requirements.
infill to a central atrium area. Thee
foundation scheme for the six-storeytorey The feasibility of reuse fundamentally
-level
commercial building with a one-level depends on the load-carrying capacity
aight-
basement comprised single straight-
of the existing foundations; and
2m/1.8m
shafted London clay piles of 1.2m/1.8m
assurance that foundation movements
diameter up to 18m in length. As s the
new loads for the scheme were greater under the new load are acceptable.
than the capacity of the existing g piles, This is a function of:
tilising
a retrofitted raft was installed utilising | the available records on site
the existing piles and a small investigations, foundation design and
number of new small-diameter as-built construction for the existing
piles were installed in reduced structure
headroom. This was possible | the geotechnical capacity of the
with minimal site investigations
foundations based on current design
due to the comprehensive record rd
practice, and any load tests carried
information available from the
original construction and use of a ëAdditional out
commercial space | the new building loads required in
ARUP

mate the
3D finite-element model to estimate added at 1 Triton
performance of the strengthened d system. Square
comparison to those experienced by
the foundations to date

20
November/December 2020 | thestructuralengineer.org

Reusing foundati_TSE Nov Dec 2020_The Structural Engineer 20 05/11/2020 14:17


Reusing foundations Climate emergency

under-reamed piles), may allow


reappraisal of the design capacity.
New design load íFIGURE 1: Risk assessment | There may have been provision for
process for foundation reuse future modifications to the structure
assessment as space demand increased or
Yes development funding became
≤ Existing available.
Minimal risk
load?
Structural design
Design for reuse As with reuse of any structural element,
Yes assessment should reflect the available
≤ Original Low risk materials and design/construction
capacity approaches of the time. For example,
and dependent on age, it is likely that
∆δ concrete of lower strength grade than
Yes acceptable in current practice would have been
≤ Reassessed Medium risk
capacity used in foundations such as pads/
strips or even piles. Reinforcement in
foundations is likely to be less than
No current design approaches, and piles
High risk Reduce loads or add were routinely only nominally reinforced
new foundations to to approx. 3–5m below trim level or
ARUP

mitigate risk into a competent stratum. It is not


uncommon for concrete piles to have
steel casings to facilitate construction,
which may have been left in situ.
| the condition and future durability of Where an adequate geotechnical
the existing foundations factor of safety cannot be demonstrated
| the anticipated performance under in the existing foundations under new
the new temporary and permanent TO REUSE loads, it may be necessary to augment
loads (i.e. settlement performance). EXISTING the existing system with structural

Foundation design
FOUNDATIONS, connections to new foundations. Early
consideration of connection detailing
CIRIA publication C6532 introduces THE RISKS NEED between existing and new construction
reuse ‘load factors’ to relate the demand
to the allowable capacity and quantify
TO BE IDENTIFIED is important.
Shear transfer at the construction
the opportunity for reuse. The existing AND ADDRESSED joint between the new and existing
foundation capacity is considered AT AN EARLY concrete may be achieved through
as: the original capacity from archive
records, the capacity based on a later
STAGE BY THE a combination of Coulomb friction,
interlocking and reuse of existing
assessment of the as-built foundation WHOLE PROJECT reinforcement continuous through the
geometry; or the existing realistic load
to which foundations have been proven
TEAM joint and new dowels. Examples of
structural details for strengthening of
to perform adequately. The thresholds single piles and pile grounds are shown
can be used to define risk categories for in Figure 2.
reuse (Figure 1). such as piled foundations beneath
The greatest uncertainty is usually isolated columns. Intrusive investigations
in estimating the existing capacity, There may be opportunities to find Key unknowns are typically the
so it is essential to understand the additional foundation capacity from the foundation element dimensions,
likely construction methodologies and original construction when compared unidentified construction defects and
design approaches available at the with the demands placed by the new any possible deterioration that may have
time, together with available project structure. Possible reasons for this are happened since original construction.
records. Where limited information is set out below: Investigations are an important tool to
available, it may be invaluable to seek | For simplicity of original construction, fill in gaps in information to complete
specialist advice on heritage buildings foundations may have been grouped the design. The ground environment or
and historical engineering works, into types geometrically where the poor specification and workmanship of
together with local or metropolitan maximum loading applies to only the original construction can also give
archive searches to determine if any some locations. rise to serious hidden defects, such as
photographs or records exist. | Due to design/construction/ those encountered in the substructure
It is commonly cited that existing procurement timescales and of a 1960s era building during
foundation loads may generally be separation of design responsibility, investigations by Arup (Figure 3).
increased by 10% without experiencing contingency may have been left in the Depending on the availability and
unacceptable settlement or ultimate loading or foundations to allow the confidence level in archive data and
performance. While there may be cases piling package to be released ahead potential benefits of the reuse scheme
where this is a reasonable starting point, of completion of the structural design. versus the viability of alternatives,
it likely originates from experience of | Greater understanding of the investigations can be designed to
shallow foundations for simple low-rise performance of foundations, or more reduce uncertainties on:
structures with inherent redundancy and sophisticated analysis approaches | foundation dimensions (width,
may not be appropriate for all systems, (may include raft foundations or diameter, depth) – observation

21
thestructuralengineer.org | November/December 2020

Reusing foundati_TSE Nov Dec 2020_The Structural Engineer 21 05/11/2020 08:18


Opinion
Climate emergency
Planning application
Reusingprocedures
foundations
New RC Column

New RC Raft Slab

pitting, structural coring, directional


íFIGURE 2:
Example pile
drilling
strengthening details | pile length or under-reamed bell
investigation (rotary drilling, concrete
Waterproofing coring, parallel seismic testing)
Detail 3
| presence of reinforcement or toe
a) Pile strengthening of steel piles (cover meter survey,
Retained and dowelling detail fluxgate gradiometry)
Pile to new raft | concrete or reinforcement testing
(unconfined compressive strength,
yield strength)
| concrete durability testing (cement
content, petrographic analysis,
carbonation, chloride content)

Foundation investigations may be


phased with geotechnical investigations
for design and assessment of
foundations. However, as they contain
specialist works, budget allowances
should be made and timescales agreed
early in the process. It is typical for the
existing building to be in place and
even occupied at this stage; therefore,
careful planning is needed, and possible
b) Piled foundation
ARUP

strengthening detail for consideration of working out of hours.


existing pile cap Where little information is available
on the existing foundations, an
intensive investigation to reduce risk
to acceptable levels may be costed
Box 2. Imperial College sports centre, London against the benefits and risks of reuse.
Consideration of the redundancy of
îImperial College
foundation elements under the new
sports centre, loading is key to the decision to proceed
completed 2005 with reuse, and investigations may
indicate a change in strategy for the
foundations.

Monitoring
While the risk of existing defects or
unexpected foundation performance
can be mitigated to an extent through
desk-based assessment and intrusive
The redevelopment of the sports centre for Imperial College in central London realised the benefit of under- investigation, it is rarely practical or cost-
reamed piles within the London clay, which curiously had not been loaded due to a 1962 building project effective to investigate each foundation
not being completed as a result of funding issues. An intrusive site investigation proved the foundation
element individually. Structural
dimensions at selected locations and that its condition had not degraded since the original construction.
movement and/or load monitoring
Through archive research and knowledge and experience of pile design and construction techniques at
is typically included within the risk
ARUP

the time, it was possible to gain confidence to reuse all the existing piles designed for the earlier structure,
mitigating the need for further piling within the limited available space. mitigation approach, e.g. by:
| precise levelling of BRE type bolts or
3D geodetic prisms on key structural
elements by manual survey

Box 3. Shell Centre/Southbank Place, London


ndon êFIGURE 3: Exposed pile cap indicating potentially
serious durability issue to steel reinforcement
The Southbank Place project by Braeburn Estates
redeveloped the Shell Centre in central London,
including retention of the iconic tower and the
construction of eight new commercial and residential
buildings. Parts of the original buildings were founded
on under-reamed piles in the London clay, which also
acted to restrain the long-term heave of the underlying
London Underground Bakerloo line tunnels. An intrusive
investigation proved the position, dimensions and
condition of a sample of piles to justify reuse for the
new buildings, augmented with new piles. Estimation
of the loads on the reused piles and demonstration of ëLS Dyna analysis model
satisfactory load-displacement behaviour was carried
ARUP

ARUP

and underlying Northern and


out using a sophisticated 3D finite-element analysis. Bakerloo line tunnels

22
November/December 2020 | thestructuralengineer.org

Reusing foundati_TSE Nov Dec 2020_The Structural Engineer 22 05/11/2020 08:19


Reusing foundations Climate emergency

| automated monitoring using


Box 4. Whitfield Street, London robotic total station or tilt meters/
hydrostatic cells.
íWhitfield Street As no records were available for this five-storey 1930s
buildings before building, intrusive investigations proved it was supported The number, location and frequency
foundation reuse by shallow footings approx. 3m deep. As the factor of monitoring measures is based
and facade
retention
of safety assessed under existing conditions was on confidence in the performance
scheme acceptable, an increase of 10% in load was proposed to of the existing foundations and the
support the new structure, which assisted with retention consequences of a potential defect. As
of a listed facade. Where new loads were in excess of loading from new structure is generally
10%, the footings were assessed for strength based
progressive, monitoring frequencies
on concrete investigations, bearing at the column/pad
should be appropriate to indicate a
interface and lightly/unreinforced concrete design to
justify sufficient capacity. Analysis confirmed settlements potential issue in a timely manner. Trigger
under new loads were acceptable, and the residual risk of values and emergency action plans then
defects or unexpected conditions was managed through respond to unexpected behaviour to
monitoring during the new construction. mitigate the risk of damage or an unsafe
ARUP

condition.

Specialist advice
Approaches for design and risk
mitigation of foundation reuse are not
Box 5. Unilever House, London typical of design of new foundation
í‘Raymond’ steel
systems. It is therefore recommended
piles installed in 19323 to seek advice from specialist
geotechnical/structural engineering
advisers at the project feasibility stage
EARLY when the options may be evaluated for
the particular site.
CONSIDERATION
‘Raymond’ steel OF CONNECTION
piles installed in
1932 in response
DETAILING Henry Tayler
MEng, CEng, MICE, MAPM
to unforeseen poor BETWEEN
ground conditions
were reused in EXISTING Henry Tayler is a senior geotechnical
combination with AND NEW engineer at Arup’s London office.
UNILEVER

new hand-dug
caisson piles. CONSTRUCTION REFERENCES
IS IMPORTANT
1) Chapman T., Marsh B. and Foster A.
(2001) ‘Foundations for the future’, Proc.
Box 6. Ropemaker Place, London ICE – Civ. Eng., 144 (1), pp. 36–41

2) Chapman T., Anderson S. and Windle


íBasement works at J. (2007) C653: Reuse of foundations,
Ropemaker Place
London: CIRIA

3) Toms C. and Patel D. (2010) ‘The


redevelopment of Unilever House utilising
hand dug caissons and the reuse of 1930s
foundations’, Proc. 11th International
Conference on Geotechnical Challenges
in Urban Regeneration, London, UK,
26–28 May

HAVE FURTHER READING


YOUR
SAY
Butcher A.P., Powell J.J.M. and Skinner
H.D. (eds.) (2006) Reuse of foundations
for urban sites: A best practice handbook,
Watford: BRE Press

Butcher A.P. Powell J.J.M. and Skinner


This 1970s building was refurbished to provide a 28-storey structure. The existing
tse@istructe.org H.D. (2007) BRE Information Paper 5/07:
single-level basement was formed by buttress perimeter walls which were reused
Principal drivers for reusing foundations,
as part of the foundation system supporting the new structure. Reuse of these
Watford: BRE Press
elements allowed for reduced requirements for new foundations and saved on
obstruction removal or piling through. A raft foundation was used within the new EFFC/DFI carbon calculator:
ARUP

basement areas. @IStructE www.effc.org/how-we-operate/


#TheStructuralEngineer eco%e2%82%82-foundations/

23
thestructuralengineer.org | November/December 2020

Reusing foundati_TSE Nov Dec 2020_The Structural Engineer 23 05/11/2020 08:19

You might also like