The contract may state the date for possession of the site by the contractor (or commencement date),
or, if not, then the site must be handed over to the contractor within a reasonable time after signing of
the contract.
Handover keys.
Discuss issues related to continued occupation of any part of the site (particularly
on refurbishment projects) such as access.
Discuss security.
Issue any significant information about the site (such as site services, tree preservation
orders, etc.).
Discuss ongoing maintenance, operation and protection issues regarding
existing structures, landscape or other features to be retained.
Discuss noise and dust reduction measures.
Verify insurance provisions.
Read meters.
Provide contact details for key personnel on both sides.
Discuss access for client's personnel and representatives or other client contractors.