DAFTAR HARGA

TAHUN ANGGARAN 2020

NO URAIAN UPAH SATUAN HARGA SATUAN (RP) KET


1 Pekerja Hari 99,000.00
2 Tukang Batu/Besi Hari 115,000.00
3 Kepala Tukang Batu Hari 124,000.00
4 Tukang Kayu/Cat Hari 115,000.00
5 Kepala Tukang Kayu/Cat Hari 124,000.00
6 Mandor Hari 125,000.00
7 Pekerja Galian Tanah Hari 99,000.00
8 Penjaga Malam Hari 99,000.00

NO URAIAN BAHAN SATUAN HARGA SATUAN (RP) KET


1 Abu Batu (Dust) M3 810,695.00
2 Arang Kg 6,285.00
3 Asbes 3 mm Uk. 100 x 100 cm Lembar 21,369.00
4 Asbes Quality 1 x 1 cm Lembar 22,626.00
5 Aspal Kg 19,484.00
6 Air Liter 189.00
7 Atap Bitumen M2 314,250.00
8 Atap Gelombang Kecil 8 Kaki Lembar 66,621.00
9 Atap Multiroof M2 87,990.00
10 Atap Polycarbonat M2 128,214.00
11 Atap Seng Super Deck 0.25 mm M1 53,674.00
12 Atap Seng Super Deck 0.30 mm M1 75,420.00
13 Atap Ulizine Polos Lembar 85,476.00
14 Atap Uluzine Warna Lembar 93,018.00
15 Baja Struktur Kg 35,196.00
16 Baja Tulangan (Besi Polos) Kg 12,120.00
17 Baja Tulangan (Besi Ulir) Kg 12,439.00
18 Bak Air Fiberglas Buah 300,046.00
19 Bak Cuci Tangan/Wastafel Keramik Buah 624,792.00
20 Batako Uk 20 x 40 x 10 cm Buah 11,313.00
21 Batang Kelapa M1 37,710.00
22 Batu Alam Templet M2 160,896.00
23 Batu Andesit Bakar M2 384,642.00
24 Batu Andesit Sisir M2 384,642.00
25 Batu Andesit Bintik M2 384,642.00
26 Batu Bata Buah 754.00
27 Batu Belah M3 268,998.00
28 Batu Candi M3 213,690.00
29 Batu Kali M3 213,690.00
30 Batu Ukuran (50 - 250 kg) M3 495,258.00
31 Batu Ukuran (250 - 1000 kg) M3 536,739.00
32 Batu Ukuran (1000 - 1500 kg) M3 578,220.00
33 Batu Pecah 2 - 3 cm M3 406,011.00
34 Besi Baut (Kuda - Kuda) 5/8 - 10" Buah 10,056.00
35 Besi Kg 12,120.00
36 Besi Hollow M2 643,217.00
37 Besi Siku 50 x 50 Batang 407,017.00
38 Besi Siku 70 x 70 Batang 988,631.00
39 Bentonite Kg 6,236.00
40 Bambu Batang 25,140.00
41 Buis Beton dia 40 cm Buah 392,334.00
42 Buis Beton dia 50 cm Buah 412,296.00
43 Buis Beton dia 60 cm Buah 515,370.00
44 Buis Beton dia 80 cm Buah 762,999.00
45 Buis Beton dia 100 cm Buah 1,548,624.00
46 BRC M2 123,186.00
47 Bubungan Asbes Gelombang M1 263,970.00
48 Bubungan Genteng Plentong "S" M1 54,051.00
49 Bubungan Seng 6 Kaki Lembar 38,339.00
50 Cat Besi Kg 69,135.00
51 Cat Kayu Dasar Kg 56,565.00
52 Cat Minyak Kg 59,079.00
53 Clay Pack Sak 9,182.00
54 Cat Tembok Setara ICI Kg 30,168.00
55 Dempul Beton Kg 22,626.00
56 Dempul Kayu Kg 22,626.00
57 Engsel Jendela 3" Pasang 31,425.00
58 Engsel Pintu 4" Pasang 46,509.00
59 Filler Kg 880.00
60 Floor Drain Stainless Buah 71,900.00
61 Gemuk (Grease) Kg 33,939.00
62 Grease Kg 33,939.00
63 Gebalan Rumput M2 69,135.00
64 Genteng Keramik Buah 25,150.00
65 Genteng Metal Setara Emeral Lembar 96,147.00
66 Genteng Plentong "S" Buah 47,766.00
67 Giotextile M2 26,397.00
68 Granit Jeruk uk 60 x 60 cm M2 233,802.00
69 Granit Uk 60 x 60 cm M2 219,975.00
70 Granit Uk 60 x 120 cm Keping 502,800.00
71 Gravel Pak M3 150,840.00
72 Grendel Jendela / Pintu Buah 27,654.00
73 Gypsum ( 120 x 240 cm) Lembar 75,420.00
74 Hak Angin Buah 35,192.00
75 Hendle Pasang 201,120.00
76 Ijuk Kg 25,140.00
77 Jaring Kawat Baja Kg 22,123.00
78 Kabel NYA 2 mm M 3,143.00
79 Kabel NYA 3 mm M 7,291.00
80 Kaca Bening 5 mm M2 94,526.00
81 Kaca Reyband Uk 3 mm M2 82,335.00
82 Kaca Reyband Uk 5 mm M2 106,845.00
83 Kapur M3 268,741.00
84 Kawat Beton Kg 18,855.00
85 Kawat Bronjong Kg 25,140.00
86 Kawat Bronjong Digalvano dia. 3 mm Kg 31,425.00
87 Kawat Bronjong Digalvano dia. 4 mm Kg 36,453.00
88 Kawat Bronjong Pabrik Uk (2 x 1 x 0,5) dia. 3 mm Bh 835,676.00
89 Kawat Bronjong Pabrik Uk (3 x 1 x 0,5) dia. 3 mm Bh 979,203.00
90 Kawat Duri Kg 18,855.00
91 Karung Goni bh 6,285.00
92 Kayu Balok Kelas I (Seumantok / Ulim / dll) M3 8,547,600.00
93 Kayu Balok Kelas II (Kamper / Kruing / dl) M3 7,290,600.00
94 Kayu Dolken dia 8 - 10 cm Panjang 4 meter Batang 20,122.00
95 Kayu Papan Kelas II Lembar 140,784.00
96 Kayu papan Kelas III (Borneo/dll) Lembar 109,359.00
97 Kayu Papan Kelas IV (Sengon/dll) Lembar 90,504.00
98 Kayu Perancah M3 5,656,500.00
99 Kayu Sembarang untuk Perancah M3 5,656,500.00
100 Kayu Bekisting M3 5,656,500.00
101 Keramik Uk 20 x 20 cm M2 75,420.00
102 Keramik Uk 20 x 20 cm Anti Slip M2 79,820.00
103 Keramik Uk 20 x 25 cm M2 75,420.00
104 Keramik Uk 20 x 25 cm anti Slip M2 79,757.00
105 Keramik Uk 25 x 40 cm M2 85,475.00
106 Keramik Uk 30 x 30 cm M2 75,420.00
107 Keramik Uk 40 x 40 cm M2 81,705.00
108 Kerikil Beton Uk. 3 cm s/d 4 cm M3 203,634.00
109 Kertas Amplas M 12,570.00
110 Kloset Duduk Keramik Buah 1,508,400.00
111 Kloset Jongkok Keramik Standar Buah 490,230.00
112 Kran Air Buah 28,660.00
113 Kuda - kuda Baja Ringan Kanal C.75 M2 150,600.00
114 Kunci Pintu Dua Kali Putar Buah 226,260.00
115 Kuas 4" Buah 26,271.00
116 Kotak Sampel Unit 330,340.00
117 Lampu Downligt 75,420.00
118 Lampu Pijar 40 Watt Buah 22,626.00
119 Lampu Reflektor Buah 106,845.00
120 Lampu Sorot Buah 125,700.00
121 Lampu Taman Buah 471,375.00
122 Lem Kayu Kg 18,855.00
123 Lem Pipa Kg 19,773.00
124 List Profil M1 10,056.00
125 List Profil Gypsum M1 30,168.00
126 Marmer M2 854,760.00
127 Minyak Cat Liter 16,341.00
128 Minyak Final Drive Liter 72,906.00
129 Minyak Transmisi Liter 72,906.00
130 Minyak Bekisting Liter 70,392.00
131 Minyak Hidrolik Liter 71,649.00
132 Minyak Pelumas / Oli Liter 51,537.00
133 Multipleks 3 mm Lembar 72,906.00
134 Multipleks 4 mm Lembar 84,733.00
135 Multipleks 6 mm Lembar 160,784.00
136 Multipleks 9 mm Lembar 175,980.00
137 Multiplek Jati Lembar 138,270.00
138 Nok / Rabung Seng 0,35 Cat Pabrik Lembar 56,565.00
139 Nok / Rabung Seng 0,35 Tidak di Cat Lembar 37,710.00
140 Pacok Buah 8,799.00
141 Paku Kg 18,855.00
142 Paku Kayu 2" - 5" Kg 18,855.00
143 Paku Asbes Kg 22,626.00
144 Paku Beton Kotak 96,783.00
145 Paku Reng Kg 37,710.00
146 Paku Seng Kg 32,662.00
147 Papan List Plank M3 7,266,717.00
148 Pasir M3 149,583.00
149 Pasir Urug M3 69,115.00
150 Pasir Beton M3 253,411.00
151 Pasir Pasang M3 193,578.00
152 Paving Block 7 cm M2 120,672.00
153 Pelumas Gardan Liter 57,068.00
154 Pelurus (Sentralizer) Buah 98,863.00
155 Pintu Aluminium Uk. 70 x 210 cm Buah 942,750.00
156 Pintu Aluminium Uk. 80 x 210 cm Buah 1,068,450.00
157 Pintu Fiber Uk. 70 x 210 cm Buah 238,830.00
158 Pintu Kayu Uk. 70 x 210 cm Buah 817,050.00
159 Pintu Kayu Uk. 80 x 210 cm Buah 879,900.00
160 Pintu Triplek Uk. 70 x 210 cm Buah 314,250.00
161 Pintu Triplek Uk. 80 x 210 cm Buah 377,100.00
162 Pintu Air b = 0.80 h = 1.50 m Unit 30,972,480.00
163 Pintu Air b = 1.00 h = 1.50 m Unit 37,169,490.00
164 Pintu Air b = 1.50 h = 1.50 m Unit 51,624,990.00
165 Pintu Air b = 2.00 h = 1.50 m Unit 72,624,930.00
166 Pipa Besi dia 3" Batang 564,750.00
167 Pipa Galvanis dia 1" Batang 157,125.00
168 Pipa Galvanis dia 2" Batang 314,250.00
169 Pipa Galvanis dia 3" Batang 1,020,885.00
170 Pipa PVC Ø 1/2" M1 11,464.00
171 Pipa PVC Ø 3/4" M1 7,743.00
172 Pipa PVC Ø 2" M1 25,844.00
173 Pipa PVC Ø 3" M1 45,956.00
174 Pipa PVC Ø 4" M1 74,792.00
175 Pipa PVC Ø 4" Batang 389,620.00
176 Plafond PVC Polos M2 251,400.00
177 Plafond PVC Warna M2 406,011.00
178 Plamur Kg 60,336.00
179 Plint Keramik Uk. 15 x 30 cm M1 42,738.00
180 Profil PVC Polos M1 35,196.00
181 Profil PVC Warna M1 38,967.00
182 Rangka Metal Furing M1 6,285.00
183 Residu Kg 37,710.00
184 Sakelar Tunggal Buah 15,054.00
185 Sakelar Ganda Buah 17,598.00
186 Seal Tape Buah 5,331.00
187 Sealant Kg 27,654.00
188 Semen PC (40 Kg) Zak 67,878.00
189 Semen PC (40 Kg) Kg 1,703.00
190 Semen PC (50 Kg) Zak 100,560.00
191 Semen Putih @ 50 Kg Zak 182,265.00
192 Semen Warna @ 50 Kg Zak 149,583.00
193 Seng Datar BJLS 0.3 mm M1 119,415.00
194 Seng Gelombang Kecil Lembar 74,163.00
195 Seng Plat Lembar 82,660.00
196 Sirtu M3 64,358.00
197 Solar Liter
198 Stop Kontak Titik 15,084.00
199 Teralis Besi M2 481,431.00
200 Thinner Liter 27,564.00
201 Thinner (Cobra Merah 1 Liter) Kaleng 51,537.00
202 Timbunan Biasa M3 65,238.00
203 Timbunan Pilihan M3 87,990.00
204 Titik Lampu Titik 116,901.00
205 Urinoir Buah 908,811.00
206 Kerikil Sungai Royalty 58,000.00
207 Batu Kali Royalty 64,000.00
208 Batu Pecah 1 - 2 cm 680,000.00
209 Sirtu Royalty 64,000.00
210 Aluminium Composit Panel 1,400,000.00
211 Kaca One Way 5 mm 1,550,000.00
212 Alat - alat Bantu (unit @3 alat) 284,000.00

NO URAIAN SEWA PERALATAN SATUAN HARGA SATUAN (RP) KET

1 Peralatan Perakitan Besi Jam 150,000.00


A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
A. 2.2.1.4 Pengukuran dan Pemasangan 1m' Bouwplank

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.100 99,000.00 9,900.00
Tukang kayu L.02 OH 0.100 115,000.00 11,500.00
Kepala Tukang L.03 OH 0.010 124,000.00 1,240.00
Mandor L.04 OH 0.005 125,000.00 625.00
Jumlah Tenaga Kerja 23,265.00
B BAHAN
Kayu Balok 5/7 m3 0.012 5,656,500.00 67,878.00
Paku 2"-3" Kg 0.020 18,855.00 377.10
Kayu Papan 3/20 m3 0.007 4,706,208.00 32,943.46
Jumlah Harga Bahan 101,198.56
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 124,463.56
E Harga Satuan Pekerjaan 124,463.00
A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
A. 2.3.1.1 Penggalian 1 m3 Tanah Biasa sedalam 1 m
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.750 99,000.00 74,250.00
Mandor L.04 OH 0.025 125,000.00 3,125.00
Jumlah Tenaga Kerja 77,375.00
B BAHAN

Jumlah Harga Bahan


C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 77,375.00
E Harga Satuan Pekerjaan 77,375.00

A. 2.3.1.2 Penggalian 1 m3 Tanah Biasa sedalam 2 m


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.900 99,000.00 89,100.00
Mandor L.04 OH 0.045 125,000.00 5,625.00
Jumlah Tenaga Kerja 94,725.00
B BAHAN

Jumlah Harga Bahan


C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 94,725.00
E Harga Satuan Pekerjaan 94,725.00
A.4.1.1 HARGA SATUAN PEKERJAAN BETON
Catatan : Bobot isi pasir = 1400 kg/m3 , Bobot isi kerikil = 1350 kg/m3

A. 4.1.1.1 Membuat 1 m3 beton mutu f'c = 7.4 Mpa (K 100),slump (12 ± 2) cm, w/c = 0.87
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.650 99,000.00 163,350.00
Tukang batu L.02 OH 0.275 115,000.00 31,625.00
Kepala Tukang L.03 OH 0.028 124,000.00 3,472.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 208,822.00
B BAHAN
Semen Portland kg 247 1,703.00 420,641.00
Pasir Beton kg 869 181.01 157,295.83
Kerikil (Maks 30 mm) kg 999 150.84 150,689.16
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 769,260.99
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 978,082.99
E Harga Satuan Pekerjaan 978,082.00

A. 4.1.1.2 Membuat 1 m3 beton mutu f'c = 9.8 Mpa (K 125),slump (12 ± 2) cm, w/c = 0.78

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.650 99,000.00 163,350.00
Tukang batu L.02 OH 0.275 115,000.00 31,625.00
Kepala Tukang L.03 OH 0.028 124,000.00 3,472.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 208,822.00
B BAHAN
Semen Portland kg 276 1,703.00 470,028.00
Pasir Beton kg 828 181.01 149,874.51
Kerikil (Maks 30 mm) kg 1,012 150.84 152,650.08
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 813,187.59
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,022,009.59
E Harga Satuan Pekerjaan 1,022,009.00
A. 4.1.1.3 Membuat 1 m3 beton mutu f'c = 12.2 Mpa (K 150),slump (12 ± 2) cm, w/c = 0.72
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.650 99,000.00 163,350.00
Tukang batu L.02 OH 0.275 115,000.00 31,625.00
Kepala Tukang L.03 OH 0.028 124,000.00 3,472.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 208,822.00
B BAHAN
Semen Portland kg 299 1,703.00 509,197.00
Pasir Beton kg 799 181.01 144,625.28
Kerikil (Maks 30 mm) kg 1,017 150.84 153,404.28
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 847,861.56
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,056,683.56
E Harga Satuan Pekerjaan 1,056,683.00

A. 4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f'c = 7.4 Mpa (K 100),slump (3 - 6) cm, w/c = 0.87

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.200 99,000.00 118,800.00
Tukang batu L.02 OH 0.200 115,000.00 23,000.00
Kepala Tukang L.03 OH 0.020 124,000.00 2,480.00
Mandor L.04 OH 0.060 125,000.00 7,500.00
Jumlah Tenaga Kerja 151,780.00
B BAHAN
Semen Portland kg 230 1,703.00 391,690.00
Pasir Beton kg 893 181.01 161,640.02
Kerikil (Maks 30 mm) kg 1,027 150.84 154,912.68
Air Liter 200 189.00 37,800.00
Jumlah Harga Bahan 746,042.70
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 897,822.70
E Harga Satuan Pekerjaan 897,822.00
A. 4.1.1.5 Membuat 1 m3 beton mutu f'c = 14.5 Mpa (K 175), slump (12 ± 2) cm, w/c = 0.66

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.650 99,000.00 163,350.00
Tukang batu L.02 OH 0.275 115,000.00 31,625.00
Kepala Tukang L.03 OH 0.028 124,000.00 3,472.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 208,822.00
B BAHAN
Semen Portland kg 326 1,703.00 555,178.00
Pasir Beton kg 760 181.01 137,565.97
Kerikil (Maks 30 mm) kg 1,029 150.84 155,214.36
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 888,593.33
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,097,415.33
E Harga Satuan Pekerjaan 1,097,415.00

A. 4.1.1.6 Membuat 1 m3 beton mutu f'c = 16.9 Mpa (K 200), slump (12 ± 2) cm, w/c = 0.61
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.650 99,000.00 163,350.00
Tukang batu L.02 OH 0.275 115,000.00 31,625.00
Kepala Tukang L.03 OH 0.028 124,000.00 3,472.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 208,822.00
B BAHAN
Semen Portland kg 352 1,703.00 599,456.00
Pasir Beton kg 731 181.01 132,316.74
Kerikil (Maks 30 mm) kg 1,031 150.84 155,516.04
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 927,923.78
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,136,745.78
E Harga Satuan Pekerjaan 1,136,745.00
A. 4.1.1.7 A. 4.1.1.7. Membuat 1 m3 beton mutu f'c = 19.3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0.58
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.650 99,000.00 163,350.00
Tukang batu L.02 OH 0.275 115,000.00 31,625.00
Kepala Tukang L.03 OH 0.028 124,000.00 3,472.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 208,822.00
B BAHAN
Semen Portland kg 371 1,703.00 631,813.00
Pasir Beton kg 698 181.01 126,343.48
Kerikil (Maks 30 mm) kg 1,047 150.84 157,929.48
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 956,720.96
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,165,542.96
E Harga Satuan Pekerjaan 1,165,542.00

A. 4.1.1.8 Membuat 1 m3 beton mutu f'c = 21.7 Mpa (K 250), slump (12 ± 2) cm, w/c = 0.56

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.650 99,000.00 163,350.00
Tukang batu L.02 OH 0.275 115,000.00 31,625.00
Kepala Tukang L.03 OH 0.028 124,000.00 3,472.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 208,822.00
B BAHAN
Semen Portland kg 384 1,703.00 653,952.00
Pasir Beton kg 692 181.01 125,257.44
Kerikil (Maks 30 mm) kg 1,039 150.84 156,722.76
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 976,567.20
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,185,389.20
E Harga Satuan Pekerjaan 1,185,389.00
A. 4.1.1.9 Membuat 1 m3 beton mutu f'c = 24 Mpa (K 275), slump (12 ± 2) cm, w/c = 0.53

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.650 99,000.00 163,350.00
Tukang batu L.02 OH 0.275 115,000.00 31,625.00
Kepala Tukang L.03 OH 0.028 124,000.00 3,472.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 208,822.00
B BAHAN
Semen Portland kg 406 1,703.00 691,418.00
Pasir Beton kg 684 181.01 123,809.37
Kerikil (Maks 30 mm) kg 1,026 150.84 154,761.84
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 1,010,624.21
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,219,446.21
E Harga Satuan Pekerjaan 1,219,446.00

A. 4.1.1.10 Membuat 1 m3 beton mutu f'c = 26.4 Mpa (K 300), slump (12 ± 2) cm, w/c = 0.52

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 1.650 99,000.00 163,350.00
Tukang batu L.02 OH 0.275 115,000.00 31,625.00
Kepala Tukang L.03 OH 0.028 124,000.00 3,472.00
Mandor L.04 OH 0.083 125,000.00 10,375.00
Jumlah Tenaga Kerja 208,822.00
B BAHAN
Semen Portland kg 413 1,703.00 703,339.00
Pasir Beton kg 681 181.01 123,266.35
Kerikil (Maks 30 mm) kg 1,021 150.84 154,007.64
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 1,021,247.99
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,230,069.99
E Harga Satuan Pekerjaan 1,230,069.00
A. 4.1.1.11 Membuat 1 m3 beton mutu f'c = 28.8 Mpa (K 325), slump (12 ± 2) cm, w/c = 0.49
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 2.100 99,000.00 207,900.00
Tukang batu L.02 OH 0.350 115,000.00 40,250.00
Kepala Tukang L.03 OH 0.035 124,000.00 4,340.00
Mandor L.04 OH 0.105 125,000.00 13,125.00
Jumlah Tenaga Kerja 265,615.00
B BAHAN
Semen Portland kg 439 1,703.00 747,617.00
Pasir Beton kg 670 181.01 121,275.26
Kerikil (Maks 30 mm) kg 1,006 150.84 151,745.04
Air Liter 215 189.00 40,635.00
Jumlah Harga Bahan 1,061,272.30
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,326,887.30
E Harga Satuan Pekerjaan 1,326,887.00
A.4.5.1. HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)

A. 4.5.1.5 Pemasangan 1 m2 Langit-langit Triplex ukuran (120 x 240) cm, tebal 4 mm

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.100 99,000.00 9,900.00
Tukang Kayu L.02 OH 0.100 115,000.00 11,500.00
Kepala Tukang L.03 OH 0.010 124,000.00 1,240.00
Mandor L.04 OH 0.005 125,000.00 625.00
Jumlah Tenaga Kerja 23,265.00
B BAHAN
Triplex Lembar 0.375 84,733.00 31,774.88
Paku Triplex kg 0.030 18,855.00 565.65
Jumlah Harga Bahan 32,340.53
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 55,605.53
E Harga Satuan Pekerjaan 55,605.00
A. 4.5.1.7 Pemasangan 1 m2 Langit-langit Gypsum Board ukuran (120 x 240) cm, tebal 9 mm

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.100 99,000.00 9,900.00
Tukang Kayu L.02 OH 0.050 115,000.00 5,750.00
Kepala Tukang L.03 OH 0.005 124,000.00 620.00
Mandor L.04 OH 0.005 125,000.00 625.00
Jumlah Tenaga Kerja 16,895.00
B BAHAN
Gypsum Board Lembar 0.364 75,420.00 27,452.88
Paku Skrup kg 0.110 37,710.00 4,148.10
Jumlah Harga Bahan 31,600.98
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 48,495.98
E Harga Satuan Pekerjaan 48,495.00

A. 4.5.1.9 Pemasangan 1 m' List Langit-langit kayu profil

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.050 99,000.00 4,950.00
Tukang Kayu L.02 OH 0.050 115,000.00 5,750.00
Kepala Tukang L.03 OH 0.005 124,000.00 620.00
Mandor L.04 OH 0.003 125,000.00 375.00
Jumlah Tenaga Kerja 11,695.00
B BAHAN
List Kayu Profil m' 1.050 10,056.00 10,558.80
Paku kg 0.010 18,855.00 188.55
Jumlah Harga Bahan 10,747.35
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 22,442.35
E Harga Satuan Pekerjaan 22,442.00
A. 4.5.1.9a Pemasangan 1 m' List Langit-langit Gypsum profil
No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.050 99,000.00 4,950.00
Tukang Kayu L.02 OH 0.050 115,000.00 5,750.00
Kepala Tukang L.03 OH 0.005 124,000.00 620.00
Mandor L.04 OH 0.003 125,000.00 375.00
Jumlah Tenaga Kerja 11,695.00
B BAHAN
List Gypsum Profil m' 1.050 30,168.00 31,676.40
Paku Skrup kg 0.010 37,710.00 377.10
Jumlah Harga Bahan 32,053.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 43,748.50
E Harga Satuan Pekerjaan 43,748.00

A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP


A. 4.5.2.32 Pemasangan 1 m2 Genteng Metal

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.200 99,000.00 19,800.00
Tukang Kayu L.03 OH 0.100 115,000.00 11,500.00
Kepala Tukang L.11 OH 0.010 124,000.00 1,240.00
Mandor L.15 OH 0.010 125,000.00 1,250.00
Jumlah Tenaga Kerja 33,790.00
B BAHAN
Genteng Metal Lbr 1.020 96,147.00 98,069.94
Paku Seng kg 0.200 32,662.00 6,532.40
Jumlah Harga Bahan 104,602.34
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 138,392.34
E Harga Satuan Pekerjaan 138,392.00
A. 4.5.2.36 Pemasangan 1 m' Nok Genteng Metal

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.250 99,000.00 24,750.00
Tukang Kayu L.03 OH 0.150 115,000.00 17,250.00
Kepala Tukang L.11 OH 0.015 124,000.00 1,860.00
Mandor L.15 OH 0.013 125,000.00 1,625.00
Jumlah Tenaga Kerja 45,485.00
B BAHAN
Nok Genteng Metal Lbr 1.100 56,565.00 62,221.50
Paku Seng kg 0.050 32,662.00 1,633.10
Jumlah Harga Bahan 63,854.60
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 109,339.60
E Harga Satuan Pekerjaan 109,339.00
A. 4.5.2.38 Pemasangan 1 m2 Atap Seng Gelombang

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.120 99,000.00 11,880.00
Tukang Kayu L.03 OH 0.060 115,000.00 6,900.00
Kepala Tukang L.11 OH 0.006 124,000.00 744.00
Mandor L.15 OH 0.006 125,000.00 750.00
Jumlah Tenaga Kerja 20,274.00
B BAHAN
Seng Gelombang Lbr 0.700 74,163.00 51,914.10
Paku Seng kg 0.020 32,662.00 653.24
Jumlah Harga Bahan 52,567.34
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 72,841.34
E Harga Satuan Pekerjaan 72,841.00

A. 4.5.2.39 Pemasangan 1 m' Nok Atap Seng


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.150 99,000.00 14,850.00
Tukang Kayu L.03 OH 0.070 115,000.00 8,050.00
Kepala Tukang L.11 OH 0.007 124,000.00 868.00
Mandor L.15 OH 0.006 125,000.00 750.00
Jumlah Tenaga Kerja 24,518.00
B BAHAN
Seng Plat 3 x kk bjls 30 Lbr 0.300 82,660.00 24,798.00
Paku Seng kg 0.040 32,662.00 1,306.48
Jumlah Harga Bahan 26,104.48
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 50,622.48
E Harga Satuan Pekerjaan 50,622.00
A.4.6.1. HARGA SATUAN PEKERJAAN KAYU

A. 4.6.1.1 Pembuatan dan Pemasangan 1m3 kusen pintu dan kusen jendela, kayu kelas I
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 7.000 99,000.00 693,000.00
Tukang Kayu L.03 OH 21.000 115,000.00 2,415,000.00
Kepala Tukang L.03 OH 2.100 124,000.00 260,400.00
Mandor L.04 OH 0.350 125,000.00 43,750.00
Jumlah Tenaga Kerja 3,412,150.00
B BAHAN
Balok Kayu m3 1.100 8,547,600.00 9,402,360.00
Paku kg 1.250 18,855.00 23,568.75
Lem Kayu kg 1.000 18,855.00 18,855.00
Jumlah Harga Bahan 9,444,783.75
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 12,856,933.75
E Harga Satuan Pekerjaan 12,856,933.00

A. 4.6.1.2 Pembuatan dan Pemasangan 1m3 kusen pintu dan kusenjendela, kayu kelas II
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 6.000 99,000.00 594,000.00
Tukang Kayu L.03 OH 18.000 115,000.00 2,070,000.00
Kepala Tukang L.03 OH 1.800 124,000.00 223,200.00
Mandor L.04 OH 0.300 125,000.00 37,500.00
Jumlah Tenaga Kerja 2,924,700.00
B BAHAN
Balok Kayu m3 1.200 7,290,600.00 8,748,720.00
Paku kg 1.250 18,855.00 23,568.75
Lem Kayu kg 1.000 18,855.00 18,855.00
Jumlah Harga Bahan 8,791,143.75
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 11,715,843.75
E Harga Satuan Pekerjaan 11,715,843.00
A. 4.6.1.5 Pembuatan dan Pemasangan 1m2 Daun Pintu Panel, kayu kelas II
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 1.000 99,000.00 99,000.00
Tukang Kayu L.03 OH 3.000 115,000.00 345,000.00
Kepala Tukang L.03 OH 0.300 124,000.00 37,200.00
Mandor L.04 OH 0.050 125,000.00 6,250.00
Jumlah Tenaga Kerja 487,450.00
B BAHAN
Papan Kayu m3 0.040 7,320,768.00 292,830.72
Lem Kayu kg 0.500 18,855.00 9,427.50
Jumlah Harga Bahan 302,258.22
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 789,708.22
E Harga Satuan Pekerjaan 789,708.00

A. 4.6.1.6 Pembuatan dan Pemasangan 1m2 pintu dan jendela kaca, kayu kelas II
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.800 99,000.00 79,200.00
Tukang Kayu L.03 OH 2.400 115,000.00 276,000.00
Kepala Tukang L.03 OH 0.240 124,000.00 29,760.00
Mandor L.04 OH 0.040 125,000.00 5,000.00
Jumlah Tenaga Kerja 389,960.00
B BAHAN
Papan Kayu m3 0.024 7,320,768.00 175,698.43
Lem Kayu kg 0.300 18,855.00 5,656.50
Jumlah Harga Bahan 181,354.93
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 571,314.93
E Harga Satuan Pekerjaan 571,314.00
A. 4.6.1.10 Pemasangan 1m2 jalusi kusen, kayu kelas II

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.670 99,000.00 66,330.00
Tukang Kayu L.03 OH 2.000 115,000.00 230,000.00
Kepala Tukang L.03 OH 0.200 124,000.00 24,800.00
Mandor L.04 OH 0.335 125,000.00 41,875.00
Jumlah Tenaga Kerja 363,005.00
B BAHAN
Papan Kayu m3 0.060 7,320,768.00 439,246.08
Lem Kayu kg 0.150 18,855.00 2,828.25
Jumlah Harga Bahan 442,074.33
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 805,079.33
E Harga Satuan Pekerjaan 805,079.00

A. 4.6.1.13 Pemasangan 1 m3 Konstruksi Kuda-Kuda Konvesional, Kayu Klas II

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 4.000 99,000.00 396,000.00
Tukang Kayu L.03 OH 12.000 115,000.00 1,380,000.00
Kepala Tukang L.03 OH 1.200 124,000.00 148,800.00
Mandor L.04 OH 0.200 125,000.00 25,000.00
Jumlah Tenaga Kerja 1,949,800.00
B BAHAN
Balok Kayu m3 1.100 7,290,600.00 8,019,660.00
Besi Strip kg 15.000 12,120.00 181,800.00
Paku kg 5.600 18,855.00 105,588.00
Jumlah Harga Bahan 8,307,048.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 10,256,848.00
E Harga Satuan Pekerjaan 10,256,848.00
A. 4.6.1.15 Pemasangan 1 m3 Konstruksi Gording Kayu Klas II

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 6.700 99,000.00 663,300.00
Tukang Kayu L.03 OH 20.100 115,000.00 2,311,500.00
Kepala Tukang L.03 OH 2.010 124,000.00 249,240.00
Mandor L.04 OH 0.335 125,000.00 41,875.00
Jumlah Tenaga Kerja 3,265,915.00
B BAHAN `
Balok Kayu m3 1.100 7,290,600.00 8,019,660.00
Besi Strip kg 15.000 12,120.00 181,800.00
Paku kg 3.000 18,855.00 56,565.00
Jumlah Harga Bahan 8,258,025.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 11,523,940.00
E Harga Satuan Pekerjaan 11,523,940.00

A. 4.6.1.17 Pemasangan 1 m2 rangka atap genteng beton, kayu Klas II


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.100 99,000.00 9,900.00
Tukang Kayu L.03 OH 0.100 115,000.00 11,500.00
Kepala Tukang L.03 OH 0.010 124,000.00 1,240.00
Mandor L.04 OH 0.005 125,000.00 625.00
Jumlah Tenaga Kerja 23,265.00
B BAHAN `
Kaso 5 x 7 cm m3 0.014 7,290,600.00 102,068.40
Reng (3 x 4) cm m3 0.057 7,290,600.00 415,564.20
Paku kg 0.250 18,855.00 4,713.75
Jumlah Harga Bahan 522,346.35
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 545,611.35
E Harga Satuan Pekerjaan 545,611.00
A. 4.6.1.20 Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas I atau II
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.200 99,000.00 19,800.00
Tukang Kayu L.03 OH 0.300 115,000.00 34,500.00
Kepala Tukang L.03 OH 0.030 124,000.00 3,720.00
Mandor L.04 OH 0.010 125,000.00 1,250.00
Jumlah Tenaga Kerja 59,270.00
B BAHAN `
Kaso 5 x 7 cm m3 0.0163 7,290,600.00 118,836.78
Paku kg 0.250 18,855.00 4,713.75
Jumlah Harga Bahan 123,550.53
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 182,820.53
E Harga Satuan Pekerjaan 182,820.00

A. 4.6.1.22 Pemasangan 1 m' Listplank ukuran (3 x 30) cm, Kayu Klas II


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.100 99,000.00 9,900.00
Tukang Kayu L.03 OH 0.200 115,000.00 23,000.00
Kepala Tukang L.03 OH 0.020 124,000.00 2,480.00
Mandor L.04 OH 0.005 125,000.00 625.00
Jumlah Tenaga Kerja 36,005.00
B BAHAN `
Papan Kayu m3 0.0110 7,320,768.00 80,528.45
Paku kg 0.050 18,855.00 942.75
Jumlah Harga Bahan 81,471.20
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 117,476.20
E Harga Satuan Pekerjaan 117,476.00
A. 4.6.1.23 Pemasangan 1 m2 rangka dinding pemisah (60 x 120)cm kayu kelas III
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.150 99,000.00 14,850.00
Tukang Kayu L.03 OH 0.450 115,000.00 51,750.00
Kepala Tukang L.03 OH 0.045 124,000.00 5,580.00
Mandor L.04 OH 0.008 125,000.00 1,000.00
Jumlah Tenaga Kerja 73,180.00
B BAHAN `
Balok Kayu m3 0.028 5,656,500.00 158,382.00
Paku kg 0.150 18,855.00 2,828.25
Jumlah Harga Bahan 161,210.25
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 234,390.25
E Harga Satuan Pekerjaan 234,390.00

A. 4.6.1.26 Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas II


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.600 99,000.00 59,400.00
Tukang Kayu L.03 OH 1.800 115,000.00 207,000.00
Kepala Tukang L.03 OH 0.180 124,000.00 22,320.00
Mandor L.04 OH 0.030 125,000.00 3,750.00
Jumlah Tenaga Kerja 292,470.00
B BAHAN `
Papan Kayu m3 0.007 7,320,768.00 51,245.38
Paku 5 dan 10 kg 0.100 18,855.00 1,885.50
Paku skrup 10 cm kg 0.150 37,710.00 5,656.50
Jumlah Harga Bahan 58,787.38
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 351,257.38
E Harga Satuan Pekerjaan 351,257.00
A. 4.6.1.27 Pemasangan 1 m2 dinding lambrisering dari plywood (120 x 240) cm
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.025 99,000.00 2,475.00
Tukang Kayu L.03 OH 0.075 115,000.00 8,625.00
Kepala Tukang L.03 OH 0.008 124,000.00 992.00
Mandor L.04 OH 0.001 125,000.00 125.00
Jumlah Tenaga Kerja 12,217.00
B BAHAN `
Plywood 4 mm Lembar 0.400 84,733.00 33,893.20
Paku kg 0.050 18,855.00 942.75
Jumlah Harga Bahan 34,835.95
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 47,052.95
E Harga Satuan Pekerjaan 47,052.00
A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN

A. 4.7.1.4 Pengecatan 1 m2 bidang kayu baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.070 99,000.00 6,930.00
Tukang Cat L.02 OH 0.009 115,000.00 1,035.00
Kepala Tukang L.03 OH 0.006 124,000.00 744.00
Mandor L.04 OH 0.003 125,000.00 375.00
Jumlah Tenaga Kerja 9,084.00
B BAHAN
Cat Menie kg 0.200 69,135.00 13,827.00
Plamur kg 0.150 60,336.00 9,050.40
Cat Dasar kg 0.170 56,565.00 9,616.05
Cat Penutup kg 0.260 30,168.00 7,843.68
Kuas Bh 0.010 26,271.00 262.71
Thinner Ltr 0.030 27,564.00 826.92
Amplas Lbr 0.200 12,570.00 2,514.00
Jumlah Harga Bahan 43,940.76
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 53,024.76
E Harga Satuan Pekerjaan 53,024.00
A. 4.7.1.8 Pelaburan 1 m2 bidang kayu dengan cat residu dan Ter
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.100 99,000.00 9,900.00
Mandor L.04 OH 0.006 125,000.00 750.00
Jumlah Tenaga Kerja 10,650.00
B BAHAN
Residu atau ter Liter 0.350 37,710.00 13,198.50
Jumlah Harga Bahan 13,198.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 23,848.50
E Harga Satuan Pekerjaan 23,848.00

A. 4.7.1.10 Pengecatan 1 m2 tembok baru (1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.020 99,000.00 1,980.00
Tukang Cat L.02 OH 0.063 115,000.00 7,245.00
Kepala Tukang L.03 OH 0.0063 124,000.00 781.20
Mandor L.04 OH 0.003 125,000.00 375.00
Jumlah Tenaga Kerja 10,381.20
B BAHAN
Plamur kg 0.100 60,336.00 6,033.60
Cat Dasar kg 0.100 56,565.00 5,656.50
Cat Penutup kg 0.260 30,168.00 7,843.68
Jumlah Harga Bahan 19,533.78
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 29,914.98
E Harga Satuan Pekerjaan 29,914.00
A. 4.7.1.11 Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup)

No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga

A TENAGA
Pekerja L.01 OH 0.028 99,000.00 2,772.00
Tukang Cat L.02 OH 0.042 115,000.00 4,830.00
Kepala Tukang L.03 OH 0.0042 124,000.00 520.80
Mandor L.04 OH 0.003 125,000.00 375.00
Jumlah Tenaga Kerja 8,497.80
B BAHAN
Cat Dasar kg 0.120 56,565.00 6,787.80
Cat Penutup kg 0.180 30,168.00 5,430.24
Jumlah Harga Bahan 12,218.04
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 20,715.84
E Harga Satuan Pekerjaan 20,715.00

A. 4.7.1.16 Pengecatan 1 m2 permukaan baja dengan meni besi


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.020 99,000.00 1,980.00
Tukang Cat L.02 OH 0.200 115,000.00 23,000.00
Kepala Tukang L.03 OH 0.020 124,000.00 2,480.00
Mandor L.04 OH 0.003 125,000.00 312.50
Jumlah Tenaga Kerja 27,772.50
B BAHAN
Meni Besi kg 0.100 69,135.00 6,913.50
Kuas Bh 0.010 26,271.00 262.71
Jumlah Harga Bahan 7,176.21
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 34,948.71
E Harga Satuan Pekerjaan 34,948.00
A.5.1.1 HARGA PEKERJAAN SANITASI DALAM GEDUNG

A. 5.1.1.1 Pemasangan 1 Buah kloset duduk/monoblock


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 3.300 99,000.00 326,700.00
Tukang Batu L.02 OH 1.100 115,000.00 126,500.00
Kepala Tukang L.03 OH 0.010 124,000.00 1,240.00
Mandor L.04 OH 0.160 125,000.00 20,000.00
Jumlah Tenaga Kerja 474,440.00
B BAHAN
Kloset duduk Unit 1.000 1,508,400.00 1,508,400.00
Perlengkapan Ls 0.060 90,504.00 5,430.24
Jumlah Harga Bahan 1,513,830.24
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,988,270.24
E Harga Satuan Pekerjaan 1,988,270.00

A. 5.1.1.2 Pemasangan 1 Buah kloset jongkok


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 1.000 99,000.00 99,000.00
Tukang Batu L.02 OH 1.500 115,000.00 172,500.00
Kepala Tukang L.03 OH 0.150 124,000.00 18,600.00
Mandor L.04 OH 0.160 125,000.00 20,000.00
Jumlah Tenaga Kerja 310,100.00
B BAHAN
Kloset jongkok Unit 1.000 490,230.00 490,230.00
Pasir Pasang M3 0.010 193,578.00 1,935.78
Semen Portland Kg 6.000 1,703.00 10,218.00
Jumlah Harga Bahan 502,383.78
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 812,483.78
E Harga Satuan Pekerjaan 812,483.00
A. 5.1.1.4 Pemasangan 1 Buah Urinoir
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 1.000 99,000.00 99,000.00
Tukang Batu L.02 OH 1.000 115,000.00 115,000.00
Kepala Tukang L.03 OH 0.100 124,000.00 12,400.00
Mandor L.04 OH 0.050 125,000.00 6,250.00
Jumlah Tenaga Kerja 232,650.00
B BAHAN
Urinoir Unit 1.000 908,811.00 908,811.00
Semen Portland Kg 6.000 1,703.00 10,218.00
Pasir Pasang M3 0.010 193,578.00 1,935.78
Perlengkapan Ls 0.300 272,643.30 81,792.99
Jumlah Harga Bahan 1,002,757.77
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,235,407.77
E Harga Satuan Pekerjaan 1,235,407.00

A. 5.1.1.5 Pemasangan 1 Buah Wastafel


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 1.200 99,000.00 118,800.00
Tukang Batu L.02 OH 1.450 115,000.00 166,750.00
Kepala Tukang L.03 OH 0.150 124,000.00 18,600.00
Mandor L.04 OH 0.060 125,000.00 7,500.00
Jumlah Tenaga Kerja 311,650.00
B BAHAN
Wastafel Unit 1.200 624,792.00 749,750.40
Semen Portland Kg 6.000 1,703.00 10,218.00
Pasir Pasang M3 0.010 193,578.00 1,935.78
Perlengkapan Ls 0.120 74,975.04 8,997.00
Jumlah Harga Bahan 770,901.18
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,082,551.18
E Harga Satuan Pekerjaan 1,082,551.00
A. 5.1.1.8 Pemasangan 1 Buah Bak mandi batu bata 0.3 M3
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 6.000 99,000.00 594,000.00
Tukang Batu L.02 OH 3.000 115,000.00 345,000.00
Kepala Tukang L.03 OH 0.300 124,000.00 37,200.00
Mandor L.04 OH 0.030 125,000.00 3,750.00
Jumlah Tenaga Kerja 979,950.00
B BAHAN
Bata Merah M3 150.000 754.00 113,100.00
Semen Portland Kg 120.000 1,703.00 204,360.00
Pasir Pasang M3 0.300 193,578.00 58,073.40
Keramik 20 x 20 Bh 110.000 3,016.80 331,848.00
Semen warna Kg 6.000 2,991.66 17,949.96
Jumlah Harga Bahan 725,331.36
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 1,705,281.36
E Harga Satuan Pekerjaan 1,705,281.00

A. 5.1.1.10 Pemasangan 1 buah bak bak air fibreglass vol 1m3


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.300 99,000.00 29,700.00
Tukang Batu L.02 OH 0.450 115,000.00 51,750.00
Kepala Tukang L.03 OH 0.045 124,000.00 5,580.00
Mandor L.04 OH 0.015 125,000.00 1,875.00
Jumlah Tenaga Kerja 88,905.00
B BAHAN
Bak Air Fiberglas Bh 1.000 300,046.00 300,046.00
Perlengkapan Bh 0.025 7,501.15 187.53
Jumlah Harga Bahan 300,233.53
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 389,138.53
E Harga Satuan Pekerjaan 389,138.00

A. 5.1.1.14 Pemasangan 1 Buah Floor drain


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.010 99,000.00 990.00
Tukang Batu L.02 OH 0.100 115,000.00 11,500.00
Kepala Tukang L.03 OH 0.010 124,000.00 1,240.00
Mandor L.04 OH 0.005 125,000.00 625.00
Jumlah Tenaga Kerja 14,355.00
B BAHAN
Floor drain Unit 1.000 71,900.00 71,900.00
Jumlah Harga Bahan 71,900.00
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 86,255.00
E Harga Satuan Pekerjaan 86,255.00
A. 5.1.1.17 Pemasangan 1 Buah bak kontrol pasangan bata 60 x 60cm tinggi 65 cm
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 3.200 99,000.00 316,800.00
Tukang Batu L.02 OH 1.150 115,000.00 132,250.00
Kepala Tukang L.03 OH 0.011 124,000.00 1,364.00
Mandor L.04 OH 0.016 125,000.00 2,000.00
Jumlah Tenaga Kerja 452,414.00
B BAHAN
Bata merah Bh 123.000 754.00 92,742.00
Semen Portland Kg 114.000 1,703.00 194,142.00
Pasir pasang M3 0.184 193,578.00 35,618.35
Pasir Beton M3 0.120 253,411.00 30,409.32
Kerikil M3 0.033 203,634.00 6,719.92
Besi tulangan Kg 4.850 12,120.00 58,782.00
Jumlah Harga Bahan 418,413.59
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 870,827.59
E Harga Satuan Pekerjaan 870,827.00

A. 5.1.1.19 Pemasangan 1 Buah Kran diameter 1/2" atau 3/4"


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.010 99,000.00 990.00
Tukang Batu L.02 OH 0.400 115,000.00 46,000.00
Kepala Tukang L.03 OH 0.040 124,000.00 4,960.00
Mandor L.04 OH 0.005 125,000.00 625.00
Jumlah Tenaga Kerja 52,575.00
B BAHAN
Kran air Bh 1.000 28,660.00 28,660.00
Sealtape Bh 0.025 5,331.00 133.28
Jumlah Harga Bahan 28,793.28
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 81,368.28
E Harga Satuan Pekerjaan 81,368.00
A. 5.1.1.25 Pemasangan 1 m' pipa PVC tipe AW diameter 1/2"
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.036 99,000.00 3,564.00
Tukang Batu L.02 OH 0.060 115,000.00 6,900.00
Kepala Tukang L.03 OH 0.006 124,000.00 744.00
Mandor L.04 OH 0.002 125,000.00 250.00
Jumlah Tenaga Kerja 11,458.00
B BAHAN
Pipa PVC 1/2" M 1.200 11,464.00 13,756.80
Perlengkapan 35% 4,012.40 1,404.34
Jumlah Harga Bahan 15,161.14
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 26,619.14
E Harga Satuan Pekerjaan 26,619.00

A. 5.1.1.26 Pemasangan 1 M' pipa PVC tipe AW diameter 3/4"


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.036 99,000.00 3,564.00
Tukang Batu L.02 OH 0.060 115,000.00 6,900.00
Kepala Tukang L.03 OH 0.006 124,000.00 744.00
Mandor L.04 OH 0.002 125,000.00 250.00
Jumlah Tenaga Kerja 11,458.00
B BAHAN
Pipa PVC ¾" M 1.200 7,743.00 9,291.60
Perlengkapan harga Pipa 35% 2,710.05 948.52
Jumlah Harga Bahan 10,240.12
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 21,698.12
E Harga Satuan Pekerjaan 21,698.00
A. 5.1.1.29 Pemasangan 1 m' pipa PVC tipe AW diameter 2"
No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.081 99,000.00 8,019.00
Tukang Batu L.02 OH 0.135 115,000.00 15,525.00
Kepala Tukang L.03 OH 0.014 124,000.00 1,674.00
Mandor L.04 OH 0.004 125,000.00 500.00
Jumlah Tenaga Kerja 25,718.00
B BAHAN
Pipa PVC 1/2" M 1.200 25,844.00 31,012.80
Perlengkapan 35% 9,045.40 3,165.89
Jumlah Harga Bahan 34,178.69
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 59,896.69
E Harga Satuan Pekerjaan 59,896.00

A. 5.1.1.31 Pemasangan 1 M' pipa PVC tipe AW diameter 3"


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.081 99,000.00 8,019.00
Tukang Batu L.02 OH 0.135 115,000.00 15,525.00
Kepala Tukang L.03 OH 0.014 124,000.00 1,674.00
Mandor L.04 OH 0.004 125,000.00 500.00
Jumlah Tenaga Kerja 25,718.00
B BAHAN
Pipa PVC 3" M 1.200 45,956.00 55,147.20
Perlengkapan harga Pipa 35% 16,084.60 5,629.61
Jumlah Harga Bahan 60,776.81
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 86,494.81
E Harga Satuan Pekerjaan 86,494.00

A. 5.1.1.32 Pemasangan 1 M' pipa PVC tipe AW diameter 4"


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.081 99,000.00 8,019.00
Tukang Batu L.02 OH 0.135 115,000.00 15,525.00
Kepala Tukang L.03 OH 0.014 124,000.00 1,674.00
Mandor L.04 OH 0.004 125,000.00 500.00
Jumlah Tenaga Kerja 25,718.00
B BAHAN
Pipa PVC 4" M 1.200 74,792.00 89,750.40
Perlengkapan harga Pipa 35% 26,177.20 9,162.02
Jumlah Harga Bahan 98,912.42
C PERALATAN
Jumlah Harga Alat
D Jumlah (A + B + C) 124,630.42
E Harga Satuan Pekerjaan 124,630.00

SNI DT-91-0010-2007-6.31 Pemasangan Paving Block


No. Uraian Kode Satuan Koeefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.156 99,000.00 15,444.00
Tukang Batu L.02 OH 0.156 115,000.00 17,940.00
Kepala Tukang L.03 OH 0.100 124,000.00 12,400.00
Mandor L.04 OH 0.100 125,000.00 12,500.00
Jumlah Tenaga Kerja 58,284.00
B BAHAN
Paving Block Type Hexagonal Bh 36.000 3,352.00 120,672.00
Pasir Urug M3 0.100 69,115.00 6,911.50
Jumlah Harga Bahan 127,583.50
C PERALATAN

Jumlah Harga Alat


D Jumlah (A + B + C) 185,867.50
E Harga Satuan Pekerjaan 185,867.00
BACK - UP DATA

PEKERJAAN : PEMBANGUNAN BALAI PENGAJIAN BUSTANUL ALFALAH


LOKASI : KECAMATAN PEULIMBANG
TAHUN ANGGARAN : 2020

PEKERJAAN PERSIAPAN

1 Pengukuran dan Pemasangan Bouwplank

2 Pembuatan Papan Nama Proyek

3 Administrasi dan Dokumentasi

PEKERJAAN GALIAN DAN PONDASI

1 Galian Tanah
Panjang x Lebar x Tinggi X Jlh. Pondasi
= 0.50 x 0.50 x 0.10 x 8.00 0.20 M3

Jumlah = 0.20 M3

2 Pekerjaan Pondasi Umpak


Lebar atas + Lebar bawah x Tinggi x Panjang x Jlh
= 0.30 + 0.50 x 0.50 x 0.50 x 8.00 0.80 M3
2

Jumlah = 0.80 M3

3 Besi Strip + Terpasang


8.00 Bh

Jumlah = 8.00 Bh
4 Beton Cor Alas Tangga
Panjang x Lebar x Tinggi
= 1.00 x 0.60 x 0.05 0.03 M3

Jumlah = 0.03 M3

PEKERJAAN KAYU
1 Pekerjaan Kolom Kayu
Panjang x Lebar x Tinggi Jlh. Kolom
= 0.13 x 0.13 x 3.70 x 8.00 0.50 M3
= M3

Jumlah = 0.50 M3

2 Pekerjaan Balok Kayu


Panjang x Lebar x Tinggi Jlh. Balok
Memanjang Bawah = 3.20 x 0.05 x 0.08 x 4.00 0.05 M3
atas 3.00 x 0.05 x 0.10 x 4.00 0.06 M3
Melintang Bawah = 7.00 x 0.05 x 0.08 x 10.00 0.28 M3
T.Kitab = 2.30 x 0.05 x 0.05 0.01 M3

Jumlah = 0.40 M3

`
3 Pekerjaan Lantai Papan
Panjang x Lebar
= 6.00 x 6.00 36.00 M2

Jumlah = 36.00 M2

4 Pekerjaan Rangka Dinding Papan


Panjang x Tinggi x Jumlah
= 0.01 x 0.90 x 20.00 0.18 M3

Jumlah = 0.18 M3
5 Pekerjaan Dinding Papan
Panjang x Tinggi
Dinding 1 = 3.00 x 0.90 x 1.00 = 2.70 M2
Dinding 2 = 7.00 x 0.90 x 1.00 = 6.30 M2
Dinding 3 = 3.00 x 0.90 x 1.00 = 2.70 M2
Dinding 4 = 6.10 x 0.90 x 1.00 = 5.49 M2
Tombak Layar = 3.13 x 1.08 x 2.00 = 6.76

Jumlah = 23.95 M2

6 Pekerjaan Tangga Kayu + Pegangan


1.00 Bh

Jumlah = 1.00 Bh

PEKERJAAN ATAP

1 Pekerjaan Kuda-Kuda Kayu


Panjang x Lebar x Tinggi Jumlah
Kaki Kuda-kuda = 2.18 x 0.05 x 0.07 x 4.00 0.03 M3
Balok Gapit = 0.00 x 0.00 x 0.00 x 0.00 0.00 M3
Sokong = 0.73 x 0.05 x 0.07 x 4.00 0.01 M3
Tiang Kuda - Kuda = 1.07 x 0.05 x 0.07 x 4.00 0.01 M3
Gapit = 3.15 x 0.05 x 0.07 x 4.00 0.04 M3

Jumlah = 0.10 M3
x 3 buah = 0.31

2 Pekerjaan Gording
Panjang x Lebar x Tinggi Jumlah
= 8.15 x 0.05 x 0.07 x 8.00 0.23 M3

Jumlah = 0.23 M3
3 Pekerjaan Lisplank
Panjang Depan + Panjang Samping
= 8.84 + 8.15 16.99 M1

Jumlah = 16.99 M1

4 Pekerjaan Atap Seng BJLS


Panjang x Lebar x Jumlah
= 8.15 x 2.41 x 2.00 39.28 M2

Jumlah = 39.28 M2

5 Pekerjaan Rabung Seng BJLS


Panjang Rabung
= 8.15 8.15 M1

Jumlah = 8.15 M1

PEKERJAAN PLAFOND

1 Pekerjaan Rangka Plafond


Panjang x Lebar
= 6.00 x 6.00 36.00 M2

Jumlah = 36.00 M2

2 Pekerjaan Plafond
Panjang x Lebar
= 6.00 x 6.00 36.00 M2

Jumlah = 36.00 M2
PEKERJAAN PENGECATAN

1 Cat Listplank
Panjang x Lebar
= 16.99 x 0.22 3.74 M2

Jumlah = 3.74 M2

2 Cat Tiang dan Dinding


Panjang x Lebar
= 0.40 x 3.70 8.00 11.84 M2

= 23.95 23.95 M2

Jumlah = 23.95 M2
3 Cat Plafond
Panjang x Lebar
= 6.00 x 6.00 36.00 M2

Jumlah = 36.00 M2

PEKERJAAN INSTALASI LISTRIK

1 Titik Penerangan + Terpasang

4.00 TTk
Jumlah = 4.00 Tk

2 Lampu HE 28 Watt

4.00 Bh
Jumlah = 4.00 Bh
3 Saklar Ganda

2.00 Bh
Jumlah = 2.00 Bh

Mengetahui : Diperiksa Oleh Diperiksa Oleh :


Pejabat Pelaksana Teknis Kegiatan (PPTK) Konsultan Pengawas
CV. PILAR KONSULTAN Kontraktor Pelaksana
Dinas Pendidikan Dayah
Kabupaten Bireuen CV.WAHYU MOULANA

FADLI PEUSAN,ST
Direktur BUSTAMI ABDULLAH
FIRDAUS,SE Direktur
Penata / NIP . 19710623 200801 1 001
.
Kabupaten Bireuen

FADLI PEUSAN,ST
Direktur
FIRDAUS,SE
Penata / NIP . 19710623 200801 1 001
.
PEKERJAAN : PEMBANGUNAN BALAI PENGAJIAN MATHLUBUL ULUN AZIZIYAH GAMPONG SENEUBOK ACEH KEC. PEULIMBANG
LOKASI : KEC. PEULIMBANG
TAHUN ANGGARAN : 2020

JUMLAH
NO URAIAN PEKERJAAN VOLUME SATUAN ANALISA HARGA SATUAN
HARGA
(Rp.)
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank 1.00 Ls Taksir 650,000.00 650,000.00
2 Papan Nama Proyek 1.00 Ls Taksir 500,000.00 500,000.00
3 Adminitrasi dan Dokumentasi 1.00 Ls Taksir 635,000.00 635,000.00
SUB TOTAL A. 1,785,000.00
II PEKERJAAN GALIAN DAN PONDASI
1 Galian Tanah 0.20 M³ A. 2.3.1.1 77,375.00 15,475.00
2 Pekerjaan Pondasi Umpak 0.80 M³ A. 4.1.1.1 978,082.00 782,465.60
3 Besi Strip + Terpasang 8.00 Bh Taksir 50,000.00 400,000.00
4 Beton Cor Alas Tangga 0.03 M³ A. 4.1.1.1 978,082.00 29,342.46
SUB TOTAL A. 1,227,283.06
III PEKERJAAN KAYU
1 Pekerjaan Kolom Kayu 0.50 M³ A. 4.6.1.13 10,256,848.00 5,130,885.64
2 Pekerjaan Balok Kayu 0.40 M³ A. 4.6.1.13 10,256,848.00 4,083,534.28
3 Pekerjaan Lantai Papan 36.00 M² A. 4.6.1.26 351,257.00 12,645,252.00
4 Pekerjaan Rangka Dinding Papan 0.18 M³ A. 4.6.1.13 10,256,848.00 1,846,232.64
5 Pekerjaan Dinding Papan 23.95 M² A. 4.6.1.26 351,257.00 8,412,886.16
6 Pekerjaan Tangga Kayu + Pegangan 1.00 Ls Taksir 750,000.00 750,000.00
SUB TOTAL A. 32,868,790.72
IV PEKERJAAN ATAP
1 Pekerjaan Kuda-Kuda Kayu 0.31 M³ A. 4.6.1.13 10,256,848.00 3,176,804.13
2 Pekerjaan Gording 0.23 M³ A. 4.6.1.15 11,523,940.00 2,629,763.11
3 Pekerjaan Lisplank 16.99 M¹ Taksir 50,000.00 849,500.00
4 Pekerjaan Atap Seng BJLS 39.28 M² A. 4.5.2.38 72,841.00 2,861,413.00
5 Pekerjaan Rabung Seng BJLS 8.15 M¹ A. 4.5.2.39 50,622.00 412,569.30
SUB TOTAL A. 9,930,049.55
V PEKERJAAN PLAFOND
1 Pekerjaan Rangka Plafond 0.00 M² A. 4.6.1.20 182,820.00 -
2 Pekerjaan Plafond 0.00 M² A. 4.5.1.5 55,605.00 -
SUB TOTAL A. -
VI PEKERJAAN PENGECATAN
1 Cat Listplank 3.74 M² A. 4.7.1.4 53,024.00 198,193.11
2 Cat Tiang dan Dinding 23.95 M² A. 4.7.1.10 29,914.98 716,487.70
3 Cat Plafond 0.00 M² A. 4.7.1.10 29,914.00 -
SUB TOTAL A. 914,680.81
VII PEKERJAAN INSTALASI LISTRIK
1 Titik Penerangan + Terpasang 4.00 Ttk Taksir 120,000.00 480,000.00
2 Lampu HE 28 Watt 4.00 Bh Taksir 65,000.00 260,000.00
3 Saklar Ganda 2.00 Bh Taksir 17,500.00 35,000.00
SUB TOTAL A. 775,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA

Pekerjaan : PEMBANGUNAN BALAI PENGAJIAN MATHLUBUL ULUN AZIZIYAH GAMPONG SENEUBOK


: KEC. PEULIMBANG ACEH KEC. PEULIMBANG
Lokasi
Thn. Anggaran : 2020

NO URAIAN PEKERJAAN JUMLAH


1 2 3

I PEKERJAAN PERSIAPAN Rp 1,785,000.00


II PEKERJAAN GALIAN DAN PONDASI Rp 1,227,283.06
III PEKERJAAN KAYU Rp 32,868,790.72
IV PEKERJAAN ATAP Rp 9,930,049.55
V PEKERJAAN PLAFOND Rp -
VI PEKERJAAN PENGECATAN Rp 914,680.81
VII PEKERJAAN INSTALASI LISTRIK Rp 775,000.00

JUMLAH Rp 47,500,804.13
DIBULATKAN Rp 47,500,000.00
TERBILANG : Empat Puluh Dua Juta Tujuh Ratus Lima Puluh Ribu Rupiah

Mengetahui : Bireuen, 2020


Perencana :
Pejabat Pelaksana Teknis Kegiatan (PPTK) CV. ALFA KONSULTAN
Dinas Pendidikan Dayah
Kabupaten Bireuen

SUKIDI
Direktur
FIRDAUS, S.E
Pembina TK.I/ NIP . 19710623 200801 1 001
.

Mengetahui /Menyetujui :
Plt. Kepala Dinas Pendidikan Dayah
Kabupaten Bireuen

Muhammad Diah, S. Ag
Pembina TK.I/ NIP . 19701224 199911 1 001
.