No URAIAN PEKERJAAN KODE SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

A. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilsasi ls 1.00 174,400,000.00 174,400,000.00
2 Pengukuran dan positioning WM01 ls 1.00 11,250,000.00 11,250,000.00
3 Direksi Keet m2 100.00 120,000.00 12,000,000.00
4 Air kerja ls 1.00 2,000,000.00 2,000,000.00
5 Penerangan dan Keselamatan Kerja WM02 ls 1.00 32,415,000.00 32,415,000.00
6 Dokumentasi/Administrai/As built drawing WM03 ls 1.00 11,135,000.00 11,135,000.00
243,200,000.00
B. PEK.REKLAMASI , TANGGUL / CAUSEWAY ( 5700 M2 )
1 Urugan tasirtu
- Urugan Pasir WT02 m3 8,747.00 112,625.00 985,130,875.00
- Urugan Tanah WT03 m3 8,600.00 211,100.00 1,815,460,000.00
2 Pasangan batu kosong
- Batu ukuran 20 - 40 kg/unit WT05 m3 1,233.00 212,000.00 261,396,000.00
- Batu ukuran 80 -100 kg/unit WT06 m3 1,075.00 331,250.00 356,093,750.00
3 Geotextile WT01 m2 752.74 57,430.00 43,229,858.20
4 Kubus Beton Cyclop (1x1x1) bh 600.00 2,000,000.00 1,200,000,000.00
4,661,310,483.20
C. PEMB. TRESTLE ( 402 M2 )
1 Beton
- Beton bertulang K.225 untuk plat lantai WC08 m3 100.43 5,773,207.75 579,774,388.29
- Beton bertulang K.225 untuk balok WC09 m3 55.58 6,745,545.25 374,944,387.18
- Beton bertulang K.225 untuk pile cap WC10 m3 11.90 6,089,551.50 72,490,021.06
- Beton bertulang K.225 untuk tiang railling WC13 m3 3.00 6,322,701.50 18,968,104.50
- Beton bertulang K.225 untuk cansteen WC11 m3 5.41 5,242,326.50 28,347,880.55
- Beton bertulang K.225 untuk pengisi tiang pancang WC06 m3 1.71 6,993,814.00 11,975,269.32
- Beton bertulang K.225 untuk selimut tiang pancang WC07 m3 5.87 9,145,676.50 53,664,921.55
- Beton tumbuk K.175 untuk trotoir WC02 m3 3.40 1,360,939.00 4,625,831.66
2 Lapisan pasir untuk trotoir WT02 m3 6.80 112,625.00 765,624.75
3 Tiang Pancang
- Tiang pancang D=406 mm, t=9,0 mm WP1-03 ton 64.31 21,850,000.00 1,405,182,240.00
- Pemancangan tiang + transport ke titik pancang WP2-01 m' 487.20 351,166.67 171,088,400.00
- Pengecatan tiang ( 12m bagian teratas) WP2-05 m2 183.85 70,312.50 12,927,025.45
- Penyambungan tiang setiap 12 m WP2-03 buah 36.00 772,500.00 27,810,000.00
- Pemotongan tiang WP2-02 buah 12.00 411,500.00 4,938,000.00
- Plat penutup tiang WP2-04 buah 12.00 592,500.00 7,110,000.00
5 Railing GSP 2 x f = 2,5" , t = 3 mm WM04 m' 247.20 315,460.00 77,981,712.00
6 Angker untuk dudukan tiang listrik WM05 buah 6.00 227,783.52 1,366,701.09
7 Baja siku untuk delatasi WM06 kg 200.00 817,180.17 163,436,034.67
3,017,396,542.06
D PEMB.DUDUKAN TRESTLE / ABUTMENT ( 1 BUAH )
1 Beton
- Beton bertulang K.225 untuk pile cap WC10 m3 18.43 6,089,551.50 112,215,210.27
- Beton bertulang K.225 untuk plat injak WC08 m3 4.49 5,773,207.75 25,892,836.76
- Beton bertulang K.225 untuk dinding sayap WC14 m3 3.80 5,782,514.00 21,944,640.63
- Beton bertulang K.225 untuk pengisi tiang pancang WC06 m3 0.43 6,993,814.00 2,993,817.33
- Beton bertulang K.225 untuk selimut tiang pancang WC07 m3 1.47 9,145,676.50 13,416,230.39
2 Tiang Pancang
- Tiang pancang D=406 mm, t=9,0 mm WP1-03 ton 14.65 21,850,000.00 320,146,200.00
- Pemancangan tiang + transport ke titik pancang WP2-01 m' 111.00 351,166.67 38,979,500.00
- Pengecatan tiang ( 12m bagian teratas) WP2-05 m2 45.96 70,312.50 3,231,756.36
- Penyambungan tiang setiap 12 m WP2-03 buah 9.00 772,500.00 6,952,500.00
- Pemotongan tiang WP2-02 buah 3.00 411,500.00 1,234,500.00
- Plat penutup tiang WP2-04 buah 3.00 592,500.00 1,777,500.00
3 Baja siku untuk delatasi dan penutup trench WM06 m 300.00 817,180.17 245,154,052.00
793,938,743.73

557830138.xlsx / 1 / 3
No URAIAN PEKERJAAN KODE SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

E. PEMBUATAN PELENCENGAN ( 346 M2 )


1 Beton
- Beton bertulang K.225 untuk plat lantai WC08 m3 86.50 5,773,207.75 499,382,470.38
- Beton bertulang K.225 untuk balok WC09 m3 52.85 6,745,545.25 356,488,575.37
- Beton bertulang K.225 untuk pile cap WC10 m3 50.54 6,089,551.50 307,790,291.02
- Beton bertulang K.225 untuk pengisi tiang pancang WC06 m3 3.43 6,993,814.00 23,976,326.59
- Beton bertulang K.225 untuk selimut tiang pancang WC07 m3 6.72 9,145,676.50 61,444,762.96
- Beton bertulang K.225 untuk cansteen WC11 m3 2.28 5,242,326.50 11,926,292.79
- Beton tumbuk K.175 untuk trotoir WC02 m3 1.10 1,360,939.00 1,497,032.90
2 Lapisan pasir untuk trotoir WT02 m3 2.20 112,625.00 247,775.00
3 Tiang Pancang
- Tiang pancang D=457 mm, t=12,0 mm WP1-03 ton 102.38 21,850,000.00 2,236,927,836.00
- Pemancangan tiang + transport ke titik pancang WP2-01 m' 775.58 351,166.67 272,357,843.33
- Pengecatan tiang ( 12m bagian teratas) WP2-05 m2 327.34 70,312.50 23,016,191.35
- Penyambungan tiang setiap 12 m WP2-03 buah 57.00 772,500.00 44,032,500.00
- Pemotongan tiang WP2-02 buah 19.00 411,500.00 7,818,500.00
- Plat penutup tiang WP2-04 buah 19.00 592,500.00 11,257,500.00
3 Fender karet tipe V-500 x 2500 L WD07 buah 3.00 75,270,000.00 225,810,000.00
4,083,973,897.69
F. PEMB. MOORING DOLPHIN ( 3 BUAH )
1 Beton
- Beton bertulang K.225 untuk pile cap WC10 m3 71.25 6,089,551.50 433,880,544.38
- Beton bertulang K.225 untuk pengisi tiang pancang WC06 m3 4.43 6,993,814.00 30,974,201.82
- Beton bertulang K.225 untuk selimut tiang pancang WC07 m3 8.50 9,145,676.50 77,762,556.58
2 Tiang Pancang
- Tiang pancang D=457 mm, t=12,0 mm WP1-03 ton 97.42 21,850,000.00 2,128,539,600.00
- Pemancangan tiang + transport ke titik pancang WP2-01 m' 738.00 351,166.67 259,161,000.00
- Pengecatan tiang ( 12m bagian teratas) WP2-05 m2 310.11 70,312.50 21,804,812.86
- Penyambungan tiang setiap 12 m WP2-03 buah 54.00 772,500.00 41,715,000.00
- Pemotongan tiang WP2-02 buah 18.00 411,500.00 7,407,000.00
- Plat penutup tiang WP2-04 buah 18.00 592,500.00 10,665,000.00
3 Bollard WD05 buah 3.00 39,368,762.80 118,106,288.40
4 Bracing baja pengikat sementara tiang pancang WM11 kg 900.00 21,497.22 19,347,499.54
5 Angker dudukan tiang listrik WM05 buah 2.00 227,783.52 455,567.03
3,149,819,070.61
G BREASTING DOLPHIN ( 3 BUAH )
1 Beton
- Beton bertulang K.225 untuk pile cap WC10 m3 128.67 6,089,551.50 783,542,591.51
- Beton bertulang K.225 untuk pengisi tiang pancang WC06 m3 5.91 6,993,814.00 41,298,935.76
- Beton bertulang K.225 untuk selimut tiang pancang WC07 m3 11.34 9,145,676.50 103,683,408.77
2 Tiang Pancang
- Tiang pancang D=457 mm, t=12,0 mm WP1-03 ton 142.56 21,850,000.00 3,114,936,000.00
- Pemancangan tiang + transport ke titik pancang WP2-01 m' 1,080.00 351,166.67 379,260,000.00
- Pengecatan tiang ( 12m bagian teratas) WP2-05 m2 413.48 70,312.50 29,073,083.81
- Penyambungan tiang setiap 12 m WP2-03 buah 72.00 772,500.00 55,620,000.00
- Pemotongan tiang WP2-02 buah 24.00 411,500.00 9,876,000.00
- Plat penutup tiang WP2-04 buah 24.00 592,500.00 14,220,000.00
3 Bracing baja pengikat sementara tiang pancang WM11 kg 1,200.00 21,497.22 25,796,666.06
4 Bollard WD05 buah 9.00 39,368,762.80 354,318,865.20
5 Frontal frame WD06 buah 3.00 45,362,500.00 136,087,500.00
6 Fender karet tipe cell 630 WD03 buah 6.00 34,770,000.00 208,620,000.00
7 Anker untuk dudukan tiang listrik WM05 buah 1.00 227,783.52 227,783.52
5,256,560,834.62

557830138.xlsx / 2 / 3
No URAIAN PEKERJAAN KODE SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

H CATWALK (70 M)
1 Profil baja :
- Profil WF 450.250.9.12 MP02 kg 10,889.70 20,250.00 220,516,495.91
- Profil WF 200.200.6.9 MP02 kg 762.43 20,250.00 15,439,137.44
- Profil WF 100.50.5.7 (Tiang Railing) MP02 kg 458.60 20,250.00 9,286,748.21
2 Bondex WM09 m2 84.64 148,300.15 12,551,887.06
3 Beton bertulang K.225
- Beton plat diatas bondex WC15 m3 12.70 1,591,939.00 20,210,875.48
4 Railing GSP 2 x f = 2,5" , t = 3 mm WM04 m' 141.06 315,460.00 44,500,049.44
5 Tiang Pancang
- Tiang pancang D=406 mm, t=9,0 mm WP1-03 ton 5.45 21,850,000.00 119,117,460.00
- Pemancangan tiang + transport ke titik pancang WP2-01 m' 41.30 351,166.67 14,503,183.33
- Pengecatan tiang ( 12m bagian teratas) WP2-05 m2 15.32 70,312.50 1,077,252.12
- Penyambungan WP2-03 buah 3.00 772,500.00 2,317,500.00
- Pemotongan WP2-02 buah 1.00 411,500.00 411,500.00
- Plat penutup tiang WP2-04 buah 1.00 592,500.00 592,500.00
6 Beton
- Beton bertulang K.225 untuk pile cap WC10 m3 1.44 6,089,551.50 8,768,954.16
- Beton bertulang K.225 untuk pengisi tiang pancang WC06 m3 0.19 6,993,814.00 1,360,826.06
- Beton bertulang K.225 untuk selimut tiang pancang WC07 m3 0.46 9,145,676.50 4,248,472.96
474,902,842.17
I PERKERASAN JALAN & LAPANGAN PARKIR
Perkerasan jalan & lapangan parkir ( Aspal beton t = 5
1 cm) m2 2,896.39 200,000.00 579,278,000.00
2 Kansteen dari beton K.175 WC02 m3 40.00 1,360,939.00 54,437,560.00
3 Sistem drainase m3 1.00 20,000,000.00 20,000,000.00
653,715,560.00
J PAGAR ( 340 M ) m' 340.00 375,000.00 127,500,000.00

K RESERVOR AIR KAP 10 M3 ( 1 BUAH ) buah 1.00 75,000,000.00 75,000,000.00

L TANKI BBM KAP 10.000 L ( 1 BUAH ) buah 1.00 75,000,000.00 75,000,000.00

M PEMB. GEDUNG OPERASIONIL ( 400 M2 ) m2 400.00 1,250,000.00 500,000,000.00

N TIANG LISTRIK DAN INSTLASI ( 10 TITIK ) titik 10.00 4,000,000.00 40,000,000.00

O PINTU GERBANG & POS JAGA (1 UNIT) unit 1.00 25,000,000.00 25,000,000.00

P R.GENSET & GENSET 20 Kva ( 1 UNIT ) unit 1.00 125,000,000.00 125,000,000.00

Q PEMB. RUMAH OPERASIONIL TYPE 36 ( 1 UNIT ) unit 1.00 45,000,000.00 45,000,000.00