Nama : Siti Alfia Ayu Rohmayanti Dosen : Prof. Dr.Ir.

Suparno, MSIE
NIM : 042114353040 Kelas : Manajemen Operasional (Jumat)
Nama : Siti Alfia Ayu Rohmayanti Dosen : Prof. Dr.Ir. Suparno, MSIE
NIM : 042114353040 Kelas : Manajemen Operasional (Jumat)

S=4
S=4 S=4

S=0

S=0
S=0
S=0
S=0

S=0

S=0

S=6
S=6

Keterangan : Lama durasi proyek

 A + D + E + K + DF = 2+ 4 +1 + 3 + 0 = 10 hari
 B + F + G + K + DF = 2 +5 +4 +3 +0 = 14 Hari
 B + H + J + DF = 2 + 8 + 5 + 0 = 15 Hari (LINTASAN KRITIS)
 C + H + J + DF = 1 + 3 + 5 + 0 = Hari
DS = Dummy Start
DF = Dummy Finish S = Slack time
ES = Early Star LS = Late Start
EF = Early Finish LF = Late Finish
METODE AOA
Nama : Siti Alfia Ayu Rohmayanti Dosen : Prof. Dr.Ir. Suparno, MSIE
NIM : 042114353040 Kelas : Manajemen Operasional (Jumat)
Nama : Siti Alfia Ayu Rohmayanti Dosen : Prof. Dr.Ir. Suparno, MSIE
NIM : 042114353040 Kelas : Manajemen Operasional (Jumat)

D (4) E (1)
A (2)
G (4)
K (3)
B (2) F (5)
H (8)

C (1)
J (5)

I (3)

LINTASAN KRITIS = B + H + J = 2 + 8 + 5 = 15 Hari

Keterangan : S = Slack time

ES = Early Star LS = Late Start


EF = Early Finish LF = Late Finish