CURVA S Implementación de Planta Industrial

You might also like

You are on page 1of 2

Tareas Todos

Datos
Año Trimestre Semana Día Valor acumulado Valor planeado AC
2020 T2 Semana 22 25 1872 2000 2884
26 3200 4000 4700
27 6160 6960 8616
28 8224 9920 10680
29 10312 12080 13592
30 11612 13830 15520
Total Semana 22 11612 13830 15520
Semana 23 31 11612 13830 15520
1 13890 16630 18358
2 15250 18980 19718
3 16132 20660 21800
4 17382 22150 23298
5 18884 23670 24800
6 19564 24620 25768
Total Semana 23 19564 24620 25768
Semana 24 7 19564 24620 25768
8 21084 26140 27288
9 22496 27660 28700
10 23476 29180 29800
11 24996 30700 31320
12 26516 32220 32840
13 27166 33170 33490
Total Semana 24 27166 33170 33490
Semana 25 14 27166 33170 33490
15 27886 34690 34210
16 27976 35510 34300
17 28606 36230 34938
18 29326 36950 35658
19 30046 37670 36378
20 30496 38120 36828
Total Semana 25 30496 38120 36828
Semana 26 21 30496 38120 36828
22 30928 38840 37748
23 31648 39560 38468
24 32080 40280 38900
25 32400 40960 39264
26 33040 41600 39904
27 33440 42000 40304
Total Semana 26 33440 42000 40304
Semana 27 28 33440 42000 40304
29 34080 42640 40944
30 34720 43280 41584
Total Semana 27 34720 43280 41584
Total T2 34720 43280 41584
T3 Semana 27 1 35360 43920 42224
2 35616 44560 42932
3 36904 45920 44572
4 37304 46320 44972
Total Semana 27 37304 46320 44972
Semana 28 5 37304 46320 44972
6 37944 46960 45612
7 38232 47600 45900
8 39312 48840 47184
9 40752 50280 48624
10 42048 51720 49920
11 42228 52350 50100
Total Semana 28 42228 52350 50100
Semana 29 12 42228 52350 50100
13 42228 52350 50100
14 42228 52350 50100
15 42228 52350 50100
16 42468 53040 49580
17 43108 53680 50220
18 43508 54080 50620
Total Semana 29 43508 54080 50620
Semana 30 19 43508 54080 50620
20 44148 54720 51260
21 44788 55360 51900
22 44788 56000 51900
23 44788 57520 51900
24 45268 59140 52868
Total Semana 30 45268 59140 52868
Total T3 45268 59140 52868
Total 2020 45268 59140 52868
Total general 45268 59140 52868