REMARK : : BEAM MATERIAL ON SITE 142/142 NOS (DONE FOR BEAM + 2.800) : BEAM HAS BEEN INSTALLED 142/142 NOS (DONE FOR BEAM +2.800) : JOINT BEAM HAS BEEN GROUTED 209/284 NOS REMARK : BEAM +8.750 MATERIAL ON SITE 60/60 NOS BEAM +8.750 HAS BEEN INSTALLED 10/60 NOS JOINT BEAM HAS BEEN GROUTED 6/120 NOS REMARK : : HALF SLAB MATERIAL ON SITE 156/156 NOS (DONE) : HALF SLAB HAS BEEN INSTALLED 108/156 NOS REMARK : WALL MATERIAL ON SITE 111/111 NOS WALL HAS BEEN INSTALLED 14/111 NOS REMARK : HCS MATERIAL ON SITE 46/170 NOS HCS HAS BEEN INSTALLED 9/170 NOS