Professional Documents
Culture Documents
ADU-ATMOSPHERIC HEATER
100-F-501
Antonio Navas
2013.12.13
17:30:59
+01'00'
Sections changed in last revision are identified by a vertical line in the margin
Doc. No. : RB-10009-WE-AL-SS-003
Rev. : 2
DRY OUT PROCEDURE Date : 26-Mar-13
Page : 2 of 9
CONTENTS
1. SCOPE
2. PRE-DRY OUT
3. PREPARATION
6. PROCEDURE
7. RECORDS
6JCK9QQ4GG'PIKPGGTKPI%Q.VF
Doc. No. : RB-10009-WE-AL-SS-003
Rev. : 2
DRY OUT PROCEDURE Date : 26-Mar-13
Page : 3 of 9
1 SCOPE
This procedure shall be applied to refractory dry out for Convection /Breeching/Stack/Flue Gas Duct
to be supplied for Rehabilitation & Adaptation Project Algiers Refinery, Algeria. Reference Document
and specification of manufacturer SIRC and code standard. See Attach #1
1.1 The refractory material was not normally thermally cured at the factory.
It is not uncommon for moisture to be absorbed by the refractory during final stages of in-
shop fabrication, transit to the job residual moisture and any absorbed moisture must be
removed after installation but prior to commencement of start-up operations. Otherwise,
trapped moisture will steam, causing cracking, and in many cases, the Refractory will separate
from the metal in large pieces. As a minimum, follow these Steps to protect the refractory
from damage.
2 PRE-DRY OUT
2.1 Pre-dry out shall be performed after completion of refractory curing and inspections.
2.2 The pre-dry out for the convection modules and breechings at the shop shall be done by
electric resistance heaters.
6JCK9QQ4GG'PIKPGGTKPI%Q.VF
Doc. No. : RB-10009-WE-AL-SS-003
Rev. : 2
DRY OUT PROCEDURE Date : 26-Mar-13
Page : 4 of 9
3 PREPARATION
3.1 Dry-out shall be performed after completion of refractory curing for specification
requirement Hour. and before coil installation.
3.3 During dry-out, contaminants such as grease, paint, oil, etc. on the surface of parts to be heat-
treated shall be removed.
3.6 All the equipment and devices to be used for dry-out shall be installed.
4.1 The equipment shall be heat-treated by electric heater with internal details as shown on Fig.1.
The drying equipments shall be used gas flame flow out method
*Should be operated gas burner flame and gas flow regulator with auto control valve Etc:
5.1 The calibrated temperature recorder shall be used for temperature control of the heat- treated
parts. The equipments used to verity the PWHT temperature shall have been calibrated within
six months of the performance of the heat treatment.
5.2 The thermocouple wire shall be used the nickel chrome/nickel aluminum (k-type) directly
capacitance discharge welded to the vessel.
5.3 Each temperature of the thermocouples will be recorded with automatic time temperature
recorder. The type of temperature recorder is strip chart type. The minimum chart speed of
strip chart shall not be less than 1 inch per hour.
6JCK9QQ4GG'PIKPGGTKPI%Q.VF
Doc. No. : RB-10009-WE-AL-SS-003
Rev. : 2
DRY OUT PROCEDURE Date : 26-Mar-13
Page : 5 of 9
5.4 Minimum holding time shall be considered as a period when all thermocouples recorded the
required holding temperature.
5.5 Thermocouples to measure and control the temperature of the heat-treated material shall be
located properly. The distance of thermocouple shall be max. 4.6 m. to each other.
6.1 The site supervisor shall be responsible for all document information, and ensuring
compliance with all procedure to met on specification requirements. Documentation shall
include:
1) Recording of calibration certificate
2) Thermocouple conformation certificate
3) Thermocouple allocation Map
4) Temperature monitored recorder and charts.
6.2 The pre-dry out curve for convection, stack and duct as follows. See Attach #1
1) Heating rate ; as per spec. require (ºF/Hr) (SIRC Dry out book)
2) Holding : as per spec. require (Hr/ inch) (SIRC Dry out book)
3) Heating up to as per spec. require ( ºF) (SIRC Dry out book)
4) Cooling rate up to spec. require ( ºF) (SIRC Dry out book)
5) Remove the heat source and allow the refractory to cool by natural radiation.
6) Do not introduce cold air with a fan.
7 RECORDS
7.1 The record and/or report of “DRY OUT “ result shall include the following information.
1) Recorder calibration certificate and thermocouple conformance certificate.
2) Heater No. and /or product No.
3) Time - temperature recorder No.
4) Number and placement of thermocouples.
5) Heating and cooling rates.
6) Holding time and temperature.
6JCK9QQ4GG'PIKPGGTKPI%Q.VF
Doc. No. : RB-10009-WE-AL-SS-003
Rev. : 2
DRY OUT PROCEDURE Date : 26-Mar-13
Page : 6 of 9
Please see dry out diagrams for convection, stack and duct in Attach #1
$FFRUGLQJ0)*VSHFLILFDWLRQ
(Hold 1Hr./inch)
500ºF Max 100ºF/Hr.
$FFRUGLQJ0)*63(&
(500ºF)
$FFRUGLQJ0)*VSHF
(300ºF)
Max 50ºF/Hr.
(Hold 1Hr./inch)
250ºF (250ºF)
Max 50ºF/Hr.
ą%*T
6JCK9QQ4GG'PIKPGGTKPI%Q.VF
Doc. No. : RB-10009-WE-AL-SS-003
Rev. : 2
DRY OUT PROCEDURE Date : 26-Mar-13
Page : 7 of 9
Location of Thermocouples
6JCK9QQ4GG'PIKPGGTKPI%Q.VF
Doc. No. : RB-10009-WE-AL-SS-003
Rev. : 2
DRY OUT PROCEDURE Date : 26-Mar-13
Page : 8 of 9
1. POWER ON
9. PRE-PURGE /5MIN.
11. FLAME ON
No direct flam on the refractory walls will be applied. And the Max. in creasing gradient
temperature is 20 ºC /Hr.
6JCK9QQ4GG'PIKPGGTKPI%Q.VF
Doc. No. : RB-10009-WE-AL-SS-003
Rev. : 2
DRY OUT PROCEDURE Date : 26-Mar-13
Page : 9 of 9
6JCK9QQ4GG'PIKPGGTKPI%Q.VF
General Refractory Procedure
____________________________________________________________________________________
Reference temperatures are generally temperatures of gas in contact with face rather than
castable temperatures. A thermocouple into castable near surface is a valid instrument to
measure castable temperatures. Always check heating diagram for the heater zones of
plant, remaining parts will be heated as consequence. In possible big blocks where source
of heat shall warm a big volume, it’s advisable to decrease the heat velocity into this “heat
zone”, this in order to keep the correct heat velocity into other zones.
Any casting could be heated at velocity lower than what recommended and however it’s
better to “make a mistake” using a lower velocity, if this could be accepted.
The heating program should occur without interruptions until ending.
A good air flow is essential into all phases to facilitate water elimination.
____________________________________________________________________________________
Page 3 of 3
ITT P.O. RB-10009-14/111 ALGIERS REFINERY PROJECT