Project Name Work Type Resource Status Remarks Time

1 BWDB-Pani Bhabon CCTV+LAN 2 Running Continue


2 BWDB-Banani CCTV+LAN 4 Running 1.5 month
3 Beximco LAN 3 Running 7 day
4 Sumantra-02 CCTV+LAN 4 Running add at least 02 person 1.5 month
5 Incepta-Savar Phase-01 LAN 2 Running 7 days
6 DGDP DC DC 4 Running 2 month
7 Pubali Bank ACS 2 Running Continue
8 SKF-Tongi LAN 4 Hold Site Readiness
9 BWDB-WAPDA DC+Power 1 Need to Start will start from Friday
10 Renata-Dinajpur CCTV+LAN 3 Need to Start 18-Nov depot opening
11 Sumantra-01 LAN 6 Need to Start
12 Incepta-Savar Phase-02 LAN 4 Need to Start
13 Incepta- Dhamrai LAN 3 Need to Start
14 BWDB/Nagod ACS/CCTV 2 Need to Start
Plan Date Proposed Team
Mir Shakil
azad Zahangir 2 OT
Hossain Maeenuddin Shakil sm
Kamrul Zashim kalim Saiful CTG OT 2
Appal Shohel 1 OT
Shopon Mamun shahidul Milon
Shahin 1 OT
Hossain Shakil sm 2 OT
12-Nov Shopon Tajul
team will move 12-Nov Hossain Shakil sm
14-Nov Mithu Arif 2 OT
14-Nov Appal Shohel
15-Nov Harun Maeenuddin 1 OT
Moktadir 1 OT