Water Pipe Manufacturing completes job #727 on January 10. The job used 45 direct labor hours and 40 machine hours. The job consumed P3,200 worth of materials. The average direct labor rate is P70.00 per hour and the company uses the predetermined overhead rate of 8.50 per direct labor hour. Provide the following: (3 items x 10 points) A. Direct Labor B. Applied Overhead C. Total Cost of Job #727
DIRECT LABOR = Rate X Activity
= 70 Per direct labor hour X 45 Direct labor hour = 3,150 Applied Overhead = Predetermine overhead rate X Activity = 8.50 X 45 Direct labor hours = 382.5
Direct Materials P3,200.00
Direct Labor P3,150.00 Applied Overhead P382.5 Total = 6,732.5