Exercise 12-37

1. Manufacturing cycle efficiency= Processing time


Processing time + Inspection time + Waiting time + Move time

= 8.5 Hours
8.5 hours + 0.5 hours + 0.5 hours + 0.5 hours

= 85%

2. Manufacturing cycle time = Total production time per batch


Units per batch

= 10 Hours
20 Units per batch

= 0.5 hour (or 30 minutes) per unit

3. Velocity = Units per batch


Total production time per batch

= 20 units
10 hours

= 2 units per hour