DISEÑO (READECUACIÓN), CONSTRUCCIÓN Y CONTROL DE CALIDAD DE LA CARRETERA

“EL ESPINO – CHARAGUA – BOYUIBE”


(CON FINANCIAMIENTO GESTIONADO POR EL PROPONENTE Y CONDICION SUSPENSIVA)

日计划活动表(二分部)

序号 施工日期 具体时间 里程 工作部位

1 06/11/2021 8:00-18:00 K58+701-K58+950

2 06/11/2021 8:00-18:00 K59+260-K59+282,K59+400-K59+518

3 06/11/2021 8:00 K58+726-K58+780

4 06/11/2021 8:00-18:00 K59+434-K59+514,K59+521-K59+624

5 06/11/2021 15:00 K67+340-K67+440


A-2-
4(0),2.120,6.2

6 06/11/2021 9:00 K65+600-K65+900; A-1a(0),2.227,5.4

7 06/11/2021 9:00 K65+900-K66+200; A-1a(0),2.225,5.1

8 06/11/2021 9:00 K66+200-K66+500; A-1a(0),2.235,5.0

9 06/11/2021 17:00 K66+200-K66+500;

10 06/11/2021 10:00 K66+500-K66+800;

11 06/11/2021 14:00 K66+800-K67+100;


12 06/11/2021 15:30 K67+100-K67+300;

13 06/11/2021 8:00 K67+479.55-K67+600;

14 06/11/2021 16:00 K67+600-K67+900;

15 06/11/2021 19:00 K67+900-K68+200;

16 06/11/2021 8:30 K69+100-K69+400;

17 06/11/2021 11:00 K69+400-K69+700;

18 06/11/2021 15:00 K69+700-K70+000;

19 06/11/2021 15:00 K70+000-K70+200;

20 06/11/2021 10:00 K72+142 CAPIGUAZUTI

21 06/11/2021 8:00:00-18:00 K76+150 CHARAGUA

22 06/11/2021 8:00:00-18:00 K82+747 MACHIPO

23 06/11/2021 8:00:00-18:00 K86+217

24 06/11/2021 15:00 K86+217

25 06/11/2021 15:00 K92+380.38


26 06/11/2021 8:00:00-18:00 K93+480 TIMBOY桥

27 06/11/2021 8:00:00-18:00 K93+500-K93+920

Ingeniero general de ejecucion: Xie


Control de calidad:VLADIMIR ORELLANA
TELE:73690697
Tele: 63528346
A CARRETERA
SUSPENSIVA)

日计划活动表(二分部)

施工内容 备注

挖方路基右侧边沟开挖

挖方路基右侧边沟开挖

挖方路基右侧边沟混凝土浇筑、H18混凝土7.5立方

拦水路缘石测量、安装

路床≥-60cm第3层压实度检测、宽度、高程 更改

路面(基层)高程、宽度、压实度检测报检

路面(基层)高程、宽度、压实度检测报检

路面(基层)高程、宽度、压实度检测报检

路面(基层)整平、碾压施工完毕 更新报检

路面(基层)整平、碾压施工 更新报检

路面(基层)整平、碾压施工 更新报检
路面(基层)整平、碾压施工 更新报检

路面(底基层)整平、碾压施工 更新报检

路面(基层)填筑、整平、碾压施工报检,试验室取样一份。

路面(基层)填筑、整平、碾压施工报检,试验室取样一份。

路面(底基层)整平、碾压施工 更新报检

路面(底基层)填筑、整平、碾压施工,试验室取样一份。 更新报检

路面(底基层)填筑、整平、碾压施工,试验室取样一份。 更新报检

路面(底基层)填筑、整平、碾压施工,试验室取样一份。

左右侧(各10.6m)人行道护栏钢筋、模板及混凝土浇筑(H21:1.5m³)

石笼及石笼垫土工布铺设及石笼安装

石笼及石笼垫土工布铺设及石笼安装

DTC4.0×2.0箱涵八字墙钢筋绑扎及模板安装

DTC4.0×2.0箱涵八字墙基础混凝土,设计H21,(2021.10.30-2021.11.06)7天抗压.

涵洞侧墙混凝土,设计H30,(2021.10.09-2021.11.06)28天抗压.
石笼及石笼垫土工布铺设及石笼安装

挖方路基左、右侧水沟开挖

Traducdor:JULIO
TELE:68780127
DISEÑO (READECUACIÓN), CONSTRUCCIÓN Y CONTROL DE CALIDAD DE LA CARRETERA
“EL ESPINO – CHARAGUA – BOYUIBE”
(CON FINANCIAMIENTO GESTIONADO POR EL PROPONENTE Y CONDICION SUSPENSIVA)

PROGRAMACIÓN DE ACTIVIDADES DIARIAS(FRENTE 2)

ORDEN FECHA DE PROGRESIVA ACTIVIDAD DE TRABAJO OBJETO


ACTIVIDAD HORA NOTA

8:00-18:
1 06/11/2021
00
K58+701-K58+950 EXCAVACION DE CUNETA DERECHA DE CORTE DE FUNDACION

8:00-18: K59+260-K59+282,K59+400-K59+518
2 06/11/2021
00
EXCAVACION DE CUNETA DERECHA DE CORTE DE FUNDACION

3 06/11/2021 8:00 K58+726-K58+780 HORMIGONADO DE CUNETA DERECHA DE CORTE DE FUNDACION(H18:7.5m³)

8:00-18:
4 06/11/2021
00
K59+434-K59+514,K59+521-K59+624 MEDICION,INSTALACION DE BORDILLOS

5 06/11/2021 15:00 K67+340-K67+440 A-2-4(0),2.120,6.2 SUBRASANTE≧-60cm Se solicita(cota,ancho) compactación para la capa N°3 MODIFICACION

6 06/11/2021 9:00 K65+600-K65+900; A-1a(0),2.227,5.4 SE SOLICITA CONTROL GEOMÉTRICO (ANCHO Y COTA)DE LA CAPA BASE Y EL ENSAYO DE COMPACTACION DE LA CAPA BASE

7 06/11/2021 9:00 K65+900-K66+200; A-1a(0),2.225,5.1 SE SOLICITA CONTROL GEOMÉTRICO (ANCHO Y COTA)DE LA CAPA BASE Y EL ENSAYO DE COMPACTACION DE LA CAPA BASE

8 06/11/2021 9:00 K66+200-K66+500; A-1a(0),2.235,5.0 SE SOLICITA CONTROL GEOMÉTRICO (ANCHO Y COTA)DE LA CAPA BASE Y EL ENSAYO DE COMPACTACION DE LA CAPA BASE

ACTUALIZAR LA
9 06/11/2021 17:00 K66+200-K66+500; CONFORMACION DE NIVELACION Y COMPACTACION DE CAPA BASE
SOLICITA
ACTUALIZAR LA
10 06/11/2021 10:00 K66+500-K66+800; NIVELACION Y COMPACTACION DE CAPA BASE
SOLICITA

ACTUALIZAR LA
11 06/11/2021 14:00 K66+800-K67+100; NIVELACION Y COMPACTACION DE CAPA BASE
SOLICITA

ACTUALIZAR LA
12 06/11/2021 15:30 K67+100-K67+300; NIVELACION Y COMPACTACION DE CAPA BASE
SOLICITA

ACTUALIZAR LA
13 06/11/2021 8:00 K67+479.55-K67+600; NIVELACION Y COMPACTACION DE SUB BASE
SOLICITA

SE SOLOICITA CARGUIO,NIVELACION Y COMPACTADO DE LA CAPA BASE,TOMA DE MUESTRA DE LA CAPA BASE POR


14 06/11/2021 16:00 K67+600-K67+900;
EL LABORATORIO

SE SOLOICITA CARGUIO,NIVELACION Y COMPACTADO DE LA CAPA BASE,TOMA DE MUESTRA DE LA CAPA BASE POR


15 06/11/2021 19:00 K67+900-K68+200;
EL LABORATORIO

ACTUALIZAR LA
16 06/11/2021 8:30 K69+100-K69+400; NIVELACION Y COMPACTACION DE SUB BASE
SOLICITA

SE SOLICITA CARGUIO,NIVELACION Y COMPACTADO DE LA SUB BASE,TOMA DE MUESTRA DE LA SUB BASE POR EL ACTUALIZAR LA
17 06/11/2021 11:00 K69+400-K69+700;
LABORATORIO SOLICITA

SE SOLICITA CARGUIO,NIVELACION Y COMPACTADO DE LA SUB BASE,TOMA DE MUESTRA DE LA SUB BASE POR EL ACTUALIZAR LA
18 06/11/2021 15:00 K69+700-K70+000;
LABORATORIO SOLICITA

SE SOLICITA CARGUIO,NIVELACION Y COMPACTADO DE LA SUB BASE,TOMA DE MUESTRA DE LA SUB BASE POR EL


19 06/11/2021 15:00 K70+000-K70+200;
LABORATORIO

20 06/11/2021 10:00 K72+142 CAPIGUAZUTI FIERROS DE BARANDAS DE ACERA(IZ,DER 10.6m)、ENCOFRADOS,HORMIGONADO(H21:1.5m³)

8:00:00-
21 06/11/2021 18:00 K76+150 CHARAGUA TENDIDO DE COLCHON DE GAVION Y GEOTEXTIL Y GAVION,INSTALACION DE GAVION

8:00:00-
22 06/11/2021
18:00
K82+747 MACHIPO TENDIDO DE COLCHON DE GAVION Y GEOTEXTIL Y GAVION,INSTALACION DE GAVION

8:00:00-
23 06/11/2021 18:00 K86+217 INSTALACION DE ENCOFRADOS,UNION DE FIERROS DE ALEROS DE LA ALCANTARILLA TIPO CAJON DTC4.0×2.0

ENSAYO DE RESISTENCIA DE 7 DIAS DE HORMIGONADO DE BASE DE ALEROS DE LA ALCANTARILLA TIPO CAJONDTC4.0×2.0 H21,
24 06/11/2021 15:00 K86+217 (2021.10.30-2021.11.06)

25 06/11/2021 15:00 K92+380.38 ENSAYO DE RESISTENCIA DE 28 DIAS DE HORMIGONADO DE MURO LATERAL DE LA ALCANTARILLA H30,(2021.10.09-2021.11.06)

26 06/11/2021 8:00:00- K93+480 PUENTE TIMBOY TENDIDO DE COLCHON DE GAVION Y GEOTEXTIL Y GAVION,INSTALACION DE GAVION
18:00

8:00:00-
27 06/11/2021 18:00 K93+500-K93+920 EXCAVACION DE CUNETAS(IZ,DE)

8:00:00-
28 06/11/2021 18:00 CAMPAMENTO DE CHARAGUA CAMPAMENTO DE CHARAGUA CORTAR HIERBA EN EL CAMPAMENTO

Ingeniero general de
ejecucion: Xie

Control de calidad:VLADIMIR ORELLANA Traducdor:JULIO


TELE:73690697 TELE:68780127

Tele: 63528346