Professional Documents
Culture Documents
11
11
TOTAL 1,000,000company is in financial and its stockholders and creditors have requested difficulty and
its
stockholders have requested a statement of affairs for planning purposes. The following information
is available:
1. The company estimates that 126,000 is the maximum amount of collectible for the accounts
receivable.
2. Except for 20% of the inventory items that are damaged and worth only 4,000 the cost of
5. The land and building have a combined appraisal value of 340,000 and are subject to the
REQUIRED:
2. Compute the estimated settlement per peso ofLahar Construction Corporation contracted with the
City of Pampanga to construct a dam at a
price of 16,000,000. Lahar expects to earn 1,520,000 on the contract. The percentage of completion
method is to be used and the completion stage is to be determined by estimates made by the
engineer. The summary of the data for 2018,2019, and 2020: YEAR COST
INCURRED
ESTIMATED
COST TO
COMPLETE0
ENGINEER’S
ESTIMATE OF
COMPLETION
BILLINGS ON
CONTRACTS
COLLECTIONS
ON BILLINGS
2020 5,250,000 0 100% 5,000,000 6,100,000Prepare a schedule showing the revenue, cost and gross
profit earned each year using the
completion.
3. Prepare journal entries for 2020 assuming zero profit methodConstruction began operations on
January 1, 2020. During the year, the company entered
into a contract with DHE Company to construct a manufacturing facility. At that time, the Ramos
estimated that it will take 5 years to complete the facility at a total cost of 4,800,000. The total
During the year, Ramos incurred 1,250,000 in construction costs related to the project. Due to price
adjustments on materials, estimated total costand paid 30% of the contract price.
REQUIRED:
Prepare the schedules to compute the gross profit recognized for December 31, 2020 and the
amount of cost of uncompleted contract in excess of billings at the year end under zero profit