You are on page 1of 1

RENCANA ANGGARAN BIAYA

RENOVASI MUSHOLLA AL MUKHLASHIN

NO. URAIAN PEKERJAAN JUMLAH HARGA Rp.

1. 2. 3.
6 Pek. Lantai granit 60x60 cm ( Lantai 2) 17.780.950
- Granit 70 175.000 12.250.000
- Pasir 4 375.000 1.500.000
- Semen 8 55.000 440.000
- Semen nat 9 10.000 90.000
- Ongkos kerja 70 50.000 3.500.950
7 Pek. Plint lantai granit 10 cm ( Lantai 2) 4.149.500
- Plint granit uk 10 cm 80 25.000 2.000.000
- Pasir 2 375.000 750.000
- Semen 4 55.000 220.000
- Semen nat 4 20.000 80.000
- Ongkos kerja 80 15.000 1.099.500
8 Pek. Lantai keramik 30x30 cm KM/WC ( Lantai 2) 1.041.755
- Keramik Lantai 8 65.000 520.000
- Pasir 0,5 375.000 187.500
- Semen 2 55.000 110.000
- Semen nat 2 20.000 40.000
- Ongkos kerja 8 35.000 184.255
9 Pek. Dinding keramik 30x60 cm KM/WC T.2,4 m ( Lantai 2) 6.672.432
- Keramik Dinding 40 70.000 2.800.000
- Pasir 4 375.000 1.500.000
- Semen 7 55.000 385.000
- Semen nat 7 20.000 140.000
- Ongkos kerja 40 40.000 1.847.432
10 Pek. Lantai keramik 20x20 cm Tangga ( Lantai 2) 1.268.960
- Keramik Lantai Tangga 13 60.000 780.000
- Pasir 0,5 375.000 187.500
- Semen 1 55.000 55.000
- Semen nat 1 20.000 20.000
- Ongkos kerja 13 22.000 226.460
11 Pek. Step noising tangga ( Lantai 2) 1.154.700
- Stepmosing granit uk 10 cm 40 20.000 800.000
- Semen 1 55.000 55.000
- Semen nat 1 20.000 20.000
- Ongkos kerja 40 5.000 279.700