You are on page 1of 3

GAS-TO-POWER

THE FUTURE OF
GAS-TO-POWER PROJECTS
AS GLOBAL DEMAND FOR POWER CONTINUES TO GROW, SO TOO DOES THE NEED FOR NEW APPROACHES TO
PROVIDING SUCH POWER. THERE ARE A NUMBER OF REASONS WHY GAS-TO-POWER PROJECTS SHOULD BE AN
IMPORTANT PART OF THE SOLUTION TO MEET THIS GLOBAL DEMAND. HOWEVER, THE PACE OF SUCH PROJECTS
REACHING THE MARKET HAS BEEN MUCH SLOWER THAN MANY EXPECTED. BY MATTHEW BROWN, PARTNER,
LATHAM & WATKINS.

Recently announced projects provide hope that being particularly attractive in locations with a
the deadlock gradually is breaking. Participants high proportion of renewable energy.
are increasingly optimistic that projects will be In addition, global credit providers such
realised around the globe – adding to the list that as export credit agencies look upon these
have already been successfully financed. So, what environmental credentials favourably, and
is the future for these projects and what can we continue to encourage and support the financing
expect in 2019 and beyond? of lower carbon emitting power projects. Many
commercial banks have announced that they
Key drivers for gas-to-power are no longer able to support coal-fired projects,
Over the past 24 months, many potential gas-to- providing an additional boost to gas-to-power
power projects have been announced around the projects.
world, including in Bangladesh, Chile, Indonesia, Advancements and innovations in technology
Myanmar, Pakistan, South Africa and Vietnam. also are key, particularly floating storage and
A number of global trends and market changes regasification units (FSRUs), which provide an
have led to this new wave of announced gas-to- efficient solution for the development of gas-to-
power projects. power projects using LNG.
First, ever-increasing global demand for Many of the gas-to-power projects being
power, particularly in emerging markets – where considered incorporate an FSRU rather than
existing generation capacity continues to be more traditional onshore regasification facilities.
insufficient to meet the needs of domestic and FSRUs carry many advantages, including that
industrial users – has created a need for rapid they can be built offsite and readily transported
deployment of large capacity generating units to the location of the project with a reduced
beyond what feasibly can be met by renewable construction time and cost, and with potentially
energy sources alone. Even relatively conservative less risk than an onshore development -
forecasts suggest that global electricity demand particularly if onshore development may
will increase by more than 50% over the next 25 encounter issues such as increased security or
years. permitting risks.
A fall in liquefied natural gas (LNG) prices Finally, geographical considerations are also a
over recent years – coupled with significant new factor. Unlike pipeline gas, LNG can be redirected
supply becoming available from both existing to different parts of the world based on regional
market players and new market entrants demand, including where domestic gas reserves
including those that will come on stream over the may be depleted.
next few years in Australia, Canada and the US – A number of the gas-to-power projects that
has substantially changed gas pricing and supply have been announced are looking to deliver
metrics. LNG supply is set to more than double gas and power to regions where domestic gas
over the next 20 years, met by a corresponding reserves, or other fuel sources, are dwindling.
increase in demand – particularly in the Far East. The increasingly diverse sources of supply
At the same time, environmental and social for LNG are also very attractive to many host
factors also play into the equation. Combined-
cycle gas turbines generate far less pollution and
greenhouse gas emissions than other traditional Many of the gas-to-power projects
thermal projects, coal or diesel.
This allows countries to work towards a being considered incorporate an FSRU
cleaner energy mix by incorporating gas-to-power
projects in an overall portfolio that includes more rather than more traditional onshore
intermittent power generation sources such as
solar or wind – the ability of gas-fired projects to regasification facilities
respond quickly to changes in load on the grid

44 Project Finance International Yearbook 2019

13 Global LNG power @p44-46.indd 44 17/12/2018 18:27:05


GAS-TO-POWER

governments – providing an alternative to domestic consumers in the form of increased


inflexible supply via a single gas pipeline. electricity charges or higher taxes.
In most cases a political choice on how this
Applying the brakes cost is allocated will be necessary, requiring
The above factors, while far from an exhaustive governments to make hard political choices.
list, would be expected to lead to a wave of In the OCTP transaction in Ghana - a non-
projects reaching financial close across many integrated gas-to-power project - for example, the
markets. However, the number of projects that government needed to (a) procure a World Bank
have reached financial close is still very small and partial risk guarantee to support the payment
a number of announced projects have stalled or obligations of GNPC as the offtaker of gas to
moved much more slowly than expected. ensure gas supply for the power projects, and (b)
The reasons for this slow progress differ provide a back-up guarantee of the obligations of
markedly from project-to-project and region- GNPC.
to-region. A significant contributing factor has
been political considerations – many countries Realising projects
in which rapid development of gas-to-power Notwithstanding the above issues, many
had been forecast have experienced slower projects are continuing to come to market and
progress after changes in government or as a more projects are being successfully financed
result of uncertain political risk following the – including the recent project financing for
announcement, or holding, of local elections. the Jawa 1 project in Indonesia. This followed
In other locations, changes in policy - including the financing of the Penco Lirquen project in
with respect to availability of government Chile in 2016. Both projects, while differing in
guarantees or other state support - have meant some respects – including in respect of funding
a slowdown while new solutions are found and arrangements – were integrated models and
new structures considered. provide solid templates for future similar projects
Elsewhere, the lack of willingness or ability to around the world.
change laws, regulations, or policies has resulted Notably, these templates offer creative
in projects encountering difficulties. solutions and mitigants to some of the above
This has included, for example, countries mentioned issues. When regulations dictate that
where minimum local ownership requirements certain assets in the gas-to-power value chain
for aspects of the gas-to-power chain - eg floating must meet certain criteria - eg have a minimum
infrastructure - or involvement of regulated local ownership requirement or be available
monopoly government-owned entities in the on an open access basis - structures have been
required value chain - eg power sellers or buyers developed to split ownership among different
of petrochemical imports - provide limits to ownership entities, while maintaining a model
aspects of the project. that permits financing of an entire project on an
Other projects have been hit by less sector- integrated basis.
specific issues, such as permitting or other
process issues or a lack in the market of Partnering up for success
creditworthy offtakers to support a financing. At the same time, we also are seeing a strong
In many countries, gas-to-power projects push to more vertical integration of the entire
straddle separate government departments - eg gas-to-power value chain. A number of LNG
gas ministry and power ministry - meaning that suppliers, including for example Qatar, have
such projects essentially face twice the level announced and activated plans to partner
of oversight and regulation, plus the risk of with other participants in the development of
inconsistency in policy. For example, the power gas-to-power projects, eg power developers,
ministry may want the developer to take the risk other governments and government utilities,
of supply of LNG but the gas ministry may wish a contractors etc.
state-owned company to maintain its monopoly From the LNG supply side, vertical integration
over the import of gas. can be a way of creating additional routes
For gas-to-power projects proposed in to market for LNG above and beyond more
developing economies, the focus – in terms of traditional buyer options. Similarly, power
making these projects economically feasible developers are becoming involved in the
– will continue to be on those entities that regasification elements of these projects. This
represent the weakest link and the legal systems move to more vertical integration aligns interests
that support their payment obligations. Typically, along the overall value chain, and can result in
the entities that cause the biggest bankability effective partnerships that facilitate successful
concerns are domestic entities involved in the projects.
offtake of the LNG/gas or the power purchasers, The Penco Lirquen project in Chile is one
whether commercial or the end-consumer. example of this, with sponsors representing
Although there are structural solutions that the LNG supply and power development sectors
can provide or enhance credit support, these working together to structure a project in which
solutions come at a cost. These costs can include interests were aligned.
the tariff charged by the LNG/gas suppliers, the This approach can greatly support the
fees charged by lenders, or the cost borne by bankability of such projects, particularly where

Project Finance International Yearbook 2019 45

13 Global LNG power @p44-46.indd 45 17/12/2018 18:27:05


GAS-TO-POWER

it can assist in reducing project-on-project


risk. Other market participants including gas
Sponsors’ willingness to participate in
traders, ship building companies, LNG shipping
companies and construction contractors have
parts of the value chain that are not their
also expressed interest in this vertical integration core business will impact the selection of
approach – looking to partner with other
participants to offer complete package solutions the preferred model
for delivery of power all over the world.

The best structuring approach


Sponsors will need to continue to look at a
range of factors for a particular project to In such projects, parties need to negotiate
decide whether to pursue an integrated - ie comprehensive usage arrangements to
incorporating all of the key upstream gas mitigate the associated risks. While the exact
extraction, midstream gas transport and arrangements will be a function of items such
downstream gas delivery/regasification and as the applicable regulatory regime, needs
power generation components - or non-integrated of potential users, physical parameters of
- incorporating only some of such components - the FSRU/terminal and whether the project
gas-to-power model or indeed a hybrid of the two is structured as a tolling or offtake model, a
approaches. number of templates have been successfully
In general, the jurisdictional opportunities and developed and financed and will provide
challenges of a project likely will be a significant guidance for future projects.
contributing factor in the chosen model and Financing considerations also will feed into
approach. While non-integrated projects may be this decision. Very few sponsors have the
appropriate in many jurisdictions - particularly ability or the risk appetite to balance sheet-
those with specific regulatory restrictions and/or finance multi-billion dollar projects, meaning
with certain parts of the gas-to-power value chain lender - including export credit agency -
already well established - in other jurisdictions a involvement is needed. Often, such lenders will
more integrated model may be more appropriate have special considerations of their own, which
and in fact may be the only option. must also be factored into the choice of project
Sponsors’ willingness to participate in parts of structure.
the value chain that are not their core business
will also impact the selection of preferred model. 2019 and beyond
In instances of such willingness, the benefits of The initial wave of new gas-to-power projects was
vertical integration may favour an integrated announced some years back and has progressed
approach. Similarly, if sponsors cannot, or are more slowly than was forecast at the time. The
not willing to, participate in sectors outside benefits of additional, reliable, and greener power
their usual business – or in certain jurisdictions, are obvious in the long term, but certain issues –
cannot do so – a more non-integrated or hybrid including political risk – provide barriers to the
structure may need to be considered. development of these projects and explain why
Lenders will typically require all, or at least the full potential of gas-to-power has not yet been
key, sponsors to retain all or a substantial realised.
portion of their ownership interest in the project A key challenge is determining how to
until completion, and to preserve a significant balance the risks and rewards to achieve
percentage for a number of years following sufficient alignment for all entities involved –
completion. including sponsors, banks, multilaterals and
Following these initial periods, international governments.
lenders generally will lift the transfer restrictions Notwithstanding the various obstacles facing
and permit sponsors to transfer their interests – gas-to-power projects, creative solutions are
though qualification requirements, such as credit being found to overcome them and projects are
ratings, may apply. Structuring decisions will being successfully financed. In 2019 and beyond,
need to take into account these requirements – there likely will be more growth in this sector
particularly if these minimum hold requirements as solutions continue to be found and templates
apply across multiple elements of the value that are demonstrably bankable become more
chain. widely used and adapted to meet remaining
The overall complexity of a project will also challenges.
drive structuring decisions. For example, if an We expect that a wide range of structuring
FSRU and associated terminal will be multi-user, outcomes will continue to be developed to
the introduction of third-party users creates address the needs of specific projects and
a number of complexities that need to be locations, including hybrids of integrated and
considered as part of the bankability assessment, non-integrated models. These factors, coupled
including allocation of storage capacity, with the continued relevancy of all of the key
scheduling, and priority and determining drivers for gas-to-power, should mean that gas-
appropriate penalties for failing to comply with to-power projects play an important role in the
these obligations. power generation mix well into the future. n

46 Project Finance International Yearbook 2019

13 Global LNG power @p44-46.indd 46 17/12/2018 18:27:05

You might also like