Diversion Channel Kalteng PVC
Diversion Channel Kalteng PVC
B = 4,3 m
H=2m
h = 1,7 m
After Cofferdam
H=2m
S = 0,02 %
S = 0,02 %
A = 5,35 m2
P = 6,1 m2
R = 0,877 m
V = 0,04 m/s
Q = 0,20 m3/s
Note :
B = Channel width (m)
H = Channel height (m)
h = Water height (m)
n = Manning’s Roughness Coefficient
S = Channel Slope (%)
A = Flow Area (m2)
P = Wetted perimeter (m)
R = Hydraulic Radius (m)
V = Velocity (m/s)
Q = Discharge (m3/s)
Qs = Estimated Discharge after cofferdam (m 3/s)
Q After Cofferdam
S = 0,02 %
A = 6,6 m2
P = 6,77 m2
R = 0,975 m
V = 0,05 m/s
Qs = 0,3 m3/s
Q Diversion Channel Formula For Velocity
Q = A. V
R = A/P
S = 0,04 %
n = 0,016
Diversion Channel
A = B X H
3 X H
P = 3 + 2H
V = 1/n . (R) . (S)1/2
2/3
B Htrial A P R V Q
0,40857 0,07356
1,3 1,1 1,43 3,5 1 7 0,105
f = 0,1 m
h = 1,1 m
B = 1,3 m