You are on page 1of 96

Appendix 2

NSRP Refinery and Petrochemical Complex Project


Coarse QRA ‘Bidder 1’

Prepared for
Foster Wheeler Energy Ltd
by
ABS Consulting Ltd.

Report No. 2514054 R01


Issue 4
February 2011
o
Report N . 2514054 R01
Issue 4

DOCUMENT APPROVAL SHEET

Project No: 2514054


o
Report N : 2514054 R01
Report Title: NSRP Refinery and Petrochemical Complex Project Coarse QRA ‘Bidder 1’
Client: Foster Wheeler Energy Ltd
Contact: Ken Smith

© ABS Consulting Limited


This document and any information or descriptive matter set out herein is subject to copyright and/or design right
ownership.
All rights reserved. No part of this document, nor any information or descriptive matter within it, may be disclosed,
loaned, reproduced, copied, photocopied, translated or reduced to any electronic medium or machine readable form or
used for any purpose whatsoever without the written permission of the Company, except in accordance with established
contract conditions pertaining to the production of this document

ISSUE DATE PREPARED REVIEWED APPROVED

1 Matthew Hart Xin Hao Pradeep Prakash


03/02/11
DRAFT (Project Engineer) (Project Engineer) (Project Manager)

Matthew Hart Xin Hao Pradeep Prakash


1 11/02/11
(Project Engineer) (Project Engineer) (Project Manager)

Matthew Hart Xin Hao Pradeep Prakash


2 15/02/11
(Project Engineer) (Project Engineer) (Project Manager)

Matthew Hart Pradeep Prakash Pradeep Prakash


3 22/02/11
(Project Engineer) (Project Manager) (Project Manager)

Matthew Hart Pradeep Prakash Pradeep Prakash


4 24/02/11
(Project Engineer) (Project Manager) (Project Manager)

Page 2 of 96
o
Report N . 2514054 R01
Issue 4

DOCUMENT REVISION HISTORY


ISSUE DESCRIPTION

Issue 1
First Draft issue for client comment.
DRAFT

Issue 1 Updated Jetty Area and incorporated client comments from DRAFT.

Issue 2 Incorporated client comments from Issue 1

Issue 3 Incorporated client comments from Issue 2

Issue 4 Removed the future Jetty from the study.

Page 3 of 96
o
Report N . 2514054 R01
Issue 4

EXECUTIVE SUMMARY

ABS Consulting Ltd (ABSC) preformed a quantitative risk assessment QRA for the proposed NSRP
refinery in Nghi Son, Vietnam for the FEED stage of the project for Foster Wheeler Energy Ltd
(FWEL). The results of the study [14], in addition to the site buildings risks, were used to check the
risks to the nearby villages and the adjacent road users. Based on those risks appropriate actions were
recommended.

Following on from previous work, the Client has now solicited definitive design proposals from
various bidders. This study has assessed the risks to the site buildings for the new proposed layout
from ‘Bidder 1’ by updating the previous study [14]. All the previous assumptions remain the same.

The three stage process for BRA is aimed at providing a structured risk assessment such that the
complexity of assessment is commensurate with the magnitude of the problem. Stage 1 is the
occupancy filtering step. At this stage, buildings which are not occupied or are not significant for the
safety of the operation are eliminated from the assessment. For stage II, worst credible consequences
are simulated and the buildings which are unaffected by the modelled hazards or for which simple
mitigations can be designed are eliminated. All the buildings which are occupied or functionally
significant AND are affected by the postulated hazards are then taken to Stage III risk assessment
process where not only the magnitude of the hazard but the frequency is taken into account to
calculate the risks to building occupants. Where risks are higher than the accepted criteria,
mitigations are considered to lower the risks to acceptable levels.

Of the on site buildings, 48 were assessed in the Stage 1 preliminary building screening as being “At
Risk”, due to their occupancy and functionality requirements.

The building risk assessment concluded that all occupied buildings at this site are shown to have
negligible Individual Risk (IR) due to explosion and fire.

Detailed recommendations for the mitigations for each building considered within the assessment in
Section 7.2 and are based on industry general practice. This risk assessment does not account to any
mitigation that may already be in place such as local deluge or passive fire protection on vessels. In
addition to the risk mitigations outlined, due attention should be paid to ensuring that a robust escape
and evacuation plan is in place within the overall emergency preparedness for the site.

The public risk was analysed on a societal risk perspective by the use of an F-N curve. Societal risk
is a measure of the collective risk to which a certain population is subjected as a whole. It is usually
depicted in form of a so-called FN curve, which shows the frequency (F), that a given number, N
people or more (hence N+) will be exposed to lethal consequences.

Based on the results of the study, it can be seen that there is the potential for thermal heat radiation to
impact the adjacent road. Fire risk (BLEVE) is predicted to affect the neighboring villages. By
inspecting the F-N curves presented previously, it can be seen that the risks to the villagers at the east
side are unacceptable.

Detailed recommendations for the mitigations for each building considered within the assessment in
Section 8 and are based on industry general practice. This risk assessment does not account to any
mitigation that may already be in place such as local deluge or passive fire protection on vessels. In
addition to the risk mitigations outlined, due attention should be paid to ensuring that a robust escape
and evacuation plan is in place within the overall emergency preparedness for the site.

Page 4 of 96
o
Report N . 2514054 R01
Issue 4

It is recommended that relocation of the villages should be considered as one of the mitigation
options. The risks to the adjacent road, south of the plant, should be mitigated by the use of a 500m
barrier, and if possible traffic control measures.

It should be noted that this QRA presents the hydrocarbon releases risk results only; occupational
risk, non-hydrocarbon events (e.g. dropped objects etc), external events (e.g. structural failure due to
extreme weather, fatigue etc), structural events (e.g. structural failures, etc), and Transportation
accidents are excluded from the scope of this study. It is assumed that the plant and buildings at the
site will be designed to withstand the appropriate seismic loading such that the hydrocarbon release
frequencies are unaffected. In cases where the plant design takes seismic risk into account, it is usual
practice to ignore the seismic considerations from the QRA.

Page 5 of 96
o
Report N . 2514054 R01
Issue 4

LIST OF ACRONYMS
ABSC ABS Consulting Ltd
ACPH Air Changes per Hour
ALARP As Low As Reasonably Practicable
ARU Amine Regeneration Unit
BLEVE Boiling Liquid Expanding Vapour Explosion
BRA Building Risk Assessment
CAM Congested area Assessment Methodology
CDU Crude Distillation Unit
CMU Concrete Masonry Units
DOM Design, Operation, Maintenance
ERPG Emergency Response Planning Guidelines
ESD Emergency Shutdown
FEED Front End Engineering and Design
FWEL Foster Wheeler Energy Limited
GOHDS Gas Oil Hydrodesulphuriser Unit
HAZID Hazard Identification
HCDS Hydrogen Compression and Distribution System
HMU Hydrogen Manufacturing Unit
HVAC Heating, Ventilation and Air Conditioning
IR Individual Risk (or Incident Radiation)
IRPA Individual Risk Per Annum
InAlk Indirect Alkylation Units
KEC Kuwait Export Crude
KHDS Kerosene Hydrodesulphuriser Unit
LC Lethal Concentration
LFL Lower Flammable Limit
LPG Liquefied Petroleum Gas
LSIR Location Specific Individual Risk
NAC Naphtha and Aromatics Complex
NSRP Nghi Son Refinery and Petrochemical
PHA Preliminary Hazard Analysis
P&ID Piping and Instrumentation Diagram
PFD Process Flow Diagram

Page 6 of 96
o
Report N . 2514054 R01
Issue 4

PPU Polypropylene Unit


PRU Propylene Recovery Unit
QRA Quantitative Risk Assessment
RHDS Residue Hydrodesulphuriser Unit
RFCC Residue Fluid Catalytic Cracker Unit
R2P2 Reducing risks, protecting people
SHU Selective Hydrogenation
SRU Sulphur Recovery Unit
SWS Sour Water Stripper Units
TGT Tail Gas Treating
UPS Uninterrupted Power Supply
SCEs Safety Critical Elements
ppm parts per million
VCE Vapour Cloud Explosion

Page 7 of 96
o
Report N . 2514054 R01
Issue 4

CONTENTS
Page
Document Approval .............................................................................................................. 2
Revision Record ................................................................................................................... 3
Summary .............................................................................................................................. 4
List of Acronyms ................................................................................................................... 6
Contents ............................................................................................................................... 7
List of Tables ........................................................................................................................ 9
List of Figures ..................................................................................................................... 10
List of Appendices ............................................................................................................... 11

1 INTRODUCTION .........................................................................................................12

2 GENERAL METHODOLOGY .....................................................................................13

3 DESCRIPTION OF FACILITY.....................................................................................14

3.1 Plant Description ..................................................................................................................................................... 14


3.1.1 Process Units ................................................................................................................................................... 15
3.1.2 Buildings .......................................................................................................................................................... 16

4 STAGE 1 ASSESSMENT ...........................................................................................19

4.1 Screening Criterion ................................................................................................................................................. 19


4.1.1 Occupancy Screening ...................................................................................................................................... 19
4.1.2 Functionality Screening ................................................................................................................................... 19

4.2 Stage One Results .................................................................................................................................................... 19

5 STAGE 2 ASSESSMENT (CONSEQUENCE ANALYSES) .......................................26

5.1 Explosion Analyses .................................................................................................................................................. 26


5.1.1 Credible Explosion Hazards ............................................................................................................................ 26
5.1.2 CAM Assessment ............................................................................................................................................ 26
5.1.3 Review of Hazard Consequences..................................................................................................................... 26

5.2 Fire Analysis ............................................................................................................................................................ 32


5.2.1 Credible Fire Hazards ...................................................................................................................................... 32
5.2.2 Boiling Liquid Expanding Vapour Explosion (BLEVE) Hazards ................................................................... 35

5.3 Toxic Analysis .......................................................................................................................................................... 39


5.3.1 Credible Toxic Hazards ................................................................................................................................... 39
5.3.2 Review of Hazard Consequences..................................................................................................................... 40

5.4 Stage II Screening ................................................................................................................................................... 43

6 STAGE 3 ASSESSMENT (RISK ANALYSIS) ............................................................43


6.1 Model Development................................................................................................................................................. 43

Page 8 of 96
o
Report N . 2514054 R01
Issue 4

6.2 SHEPHERD Parameters ........................................................................................................................................ 46


6.2.1 Equipment Count and Leak Frequencies ......................................................................................................... 46
6.2.2 Design, Operation & Maintenance Factors ...................................................................................................... 47
6.2.3 Probability of Emergency Shutdown ............................................................................................................... 47
6.2.4 Building Performance ...................................................................................................................................... 47

6.3 Fire & Toxic Hazard Modelling ............................................................................................................................. 50


6.3.1 Fatality Probabilities ........................................................................................................................................ 50
6.3.2 Ignition Probabilities ....................................................................................................................................... 50
6.3.3 Building Protection Features ........................................................................................................................... 51
6.3.4 Fire Resistance of Buildings ............................................................................................................................ 52
6.3.5 Boiling Liquid Expanding Vapour Explosion (BLEVE) Scenario .................................................................. 53

6.4 Risk Acceptance Criteria ........................................................................................................................................ 53


6.4.1 Individual Risks ............................................................................................................................................... 53

6.5 Evaluation of Building Risks .................................................................................................................................. 55


6.5.1 Explosion Risks ............................................................................................................................................... 55
6.5.2 Fire Risk .......................................................................................................................................................... 70

7 RISK ASSESSMENT ..................................................................................................79


7.1 On Site Risk ............................................................................................................................................................. 79

7.2 Off-site Risk ............................................................................................................................................................. 85


7.2.1 Villages to the East of the site ......................................................................................................................... 85
7.2.2 Road to the South of the site ............................................................................................................................ 86

8 CONCLUSIONS & RECOMMENDATIONS ................................................................89

8.1 Buildings at the site ................................................................................................................................................. 89

8.2 Off-site Population .................................................................................................................................................. 93


8.2.1 Villages to the East of the site ......................................................................................................................... 93
8.2.2 Road to the South of the plant ......................................................................................................................... 94

9 UNCERTAINTY IN QRA .............................................................................................95

10 REFERENCES............................................................................................................96

List of Tables

Table 1 – Stage 1 Assessment ........................................................................................................................................... 20

Table 2 - Maximum Credible Explosion Hazard ........................................................................................................... 27

Table 3 - Maximum Credible Fire Hazard ..................................................................................................................... 37

Table 4 – Toxic Gas (H2S) Dispersion modelling results for the 150mm hole size ..................................................... 40

Table 5 - Leak Frequencies used within the Process Blocks ......................................................................................... 46

Table 6 - Definition of Shell building types used in SHEPHERD ................................................................................. 47

Page 9 of 96
o
Report N . 2514054 R01
Issue 4

Table 7 -Vulnerability dependence on damage thresholds............................................................................................ 49

Table 8 - Definition of damage categories ....................................................................................................................... 49

Table 9- Fatality Probabilities from Exposure to Fires and Toxins ............................................................................. 50

Table 10 – Immediate Ignition Probabilities .................................................................................................................. 51

Table 11 – Delayed Ignition Probabilities ....................................................................................................................... 51

Table 12 - Levels of Building Protection against Fire & Toxic Hazards...................................................................... 52

Table 13 - Thermal Radiation Limits for Structures and Plant ................................................................................... 53

Table 14- Summary Explosion Damage for the 10-4/yr Hazard .................................................................................... 55

Table 15 – Frequency of 15kW/m2 at buildings ............................................................................................................. 76

Table 16 - Summary Occupancy Risk Values ................................................................................................................ 79

Table 17 – Overall Risk to Functionally Significant Buildings ..................................................................................... 81

Table 18 –Recommendations ........................................................................................................................................... 89

Table 19 – Recommendations Functional Significant Buildings .................................................................................. 91

Table 20 – Recommendations vulnerability ................................................................................................................... 94

List of Figures

Figure 1 - Proposed Location [Image taken from Google Earth] ................................................................................. 14

Figure 2 – NSRP Main Plant Plot Plan [6] ..................................................................................................................... 17

Figure 3 – NSRP Plant Plot Plan (Jetty area) [7] ........................................................................................................... 18

Figure 4 – 2nd Stage Buildings .......................................................................................................................................... 25

Figure 5 – Maximum Credible Overpressures Main Plant ........................................................................................... 30

Figure 6 – Maximum Credible Overpressures Jetty Area ............................................................................................ 31

Figure 7 – Maximum Potential Incident Radiation Flux Contours Main Plant.......................................................... 33

Figure 8 – Maximum Potential Incident Radiation Flux Contours Jetty Area ........................................................... 34

Figure 9 – BLEVE Fireballs Diameters .......................................................................................................................... 36

Figure 10 – ERPG Levels ................................................................................................................................................. 41

Figure 11 – ERPG Contours for the SRU ....................................................................................................................... 42

Figure 12 – SHEPHERD Model Main Plant .................................................................................................................. 44

Figure 13 – SHEPHERD model Jetty Area .................................................................................................................... 45

Figure 14 – Building vulnerability by type ..................................................................................................................... 48

Page 10 of 96
o
Report N . 2514054 R01
Issue 4

Figure 15 - Levels of Risk and ALARP ........................................................................................................................... 54

Figure 16 – Flammable Gas Frequency across the Main Plant .................................................................................... 58

Figure 17 – Flammable Gas Frequency across the Jetty Area ..................................................................................... 59

Figure 18 - Frequency of Overpressure Exceeding 100 mbar Main Plant .................................................................. 60

Figure 19 - Frequency of Overpressure Exceeding 100 mbar Jetty Area .................................................................... 61

Figure 20 - Frequency of Overpressure Exceeding 30 mbar Main Plant .................................................................... 62

Figure 21 - Frequency of Overpressure Exceeding 30 mbar Jetty Area ...................................................................... 63

Figure 22 - Explosion Risk Plot for Building Type B2 Main Plant .............................................................................. 64

Figure 23 - Explosion Risk Plot for Building Type B2 Jetty Area ................................................................................ 65

Figure 24 - Explosion Risk Plot for Building Type B4 Main Plant .............................................................................. 66

Figure 25 - Explosion Risk Plot for Building Type B4 Jetty Area ................................................................................ 67

Figure 26 - Explosion Risk Plot for Building Type B5 Main Plant .............................................................................. 68

Figure 27 - Explosion Risk Plot for Building Type B5 Jetty Area ................................................................................ 69

Figure 28 - Cloud Fire Frequency Contour Plot Main Plant ........................................................................................ 71

Figure 29 - Cloud Fire Frequency Contour Plot Jetty Area ......................................................................................... 72

Figure 30 - Frequency Contour Plot for Heat Flux above 15kW/m2 Main Plant........................................................ 73

Figure 31 - Frequency Contour Plot for Heat Flux above 15kW/m2 Jetty Area ......................................................... 74

Figure 32 – BLEVE Risk Plot .......................................................................................................................................... 75

Figure 33 – F-N Curve (Villagers only)........................................................................................................................... 85

Figure 34 – Total Fire and Explosion Risk Contour Level Main Plant ....................................................................... 87

Figure 35 – Total Fire and Explosion Risk Contour Level Jetty Area ......................................................................... 88

Figure 36 – Proposed concrete wall and traffic warning/control ................................................................................. 94

Page 11 of 96
o
Report N . 2514054 R01
Issue 4

1 INTRODUCTION

ABS Consulting Ltd (ABSC) preformed a coarse quantitative risk assessment (QRA) for the
proposed NSRP refinery in Vietnam for the FEED stage of the project for Foster Wheeler Energy
Ltd (FWEL). The results of the study [14], in addition to the site buildings risks, were used to check
the risks to the nearby villages and the adjacent road users. Based on those risks appropriate actions
were recommended.

Following on from the earlier work, the Client has now solicited definitive design proposals from
various bidders. This study assesses the risks to the site buildings, for the new proposed layout from
‘Bidder 1’ by updating the previous study [14], by incorporating the new information in the risk
model.

For this assessment all the previous assumptions about the process conditions, release frequencies,
ignition probabilities, etc remains the same.

The results of the revised risk assessment study are detailed within this report. Although unchanged
from the previous study [14], for the sake of completeness the general methodology adopted for this
study is described in Section 2. Section 3 provides a general description of the facility. Section 4
presents the results of the Stage 1 assessment. Section 5 deals with the Stage 2 consequence
modelling with Stage 3 risk analysis being covered in Section 6. Section 7 presents the Risk
Assessment, where the risks are compared to the risk acceptance criteria. Section 8 presents the
conclusions and suggests suitable risk mitigation measures for accomplishing them or showing that
the risks are As Low as Reasonably Practicable (ALARP). Finally, discussion on the QRA
uncertainties is presented in Section 9.

Page 12 of 96
o
Report N . 2514054 R01
Issue 4

2 GENERAL METHODOLOGY

The methodology adopted for the BRA follows the recommendations of in the American Institute of
Petroleum’s Recommended Practice API RP 752 [1]. The assessment follows a three step process.
The philosophy of the stepped approach is to perform as simple an analysis as is consistent with the
hazards. For example if the building is not occupied or is not significant from the plant operation
aspect then no further assessment is needed. If the building is occupied or is functionally significant
then the next consideration is to check if the building is subject to a credible hazard and if simple
mitigation is feasible to mitigate the effects. No further assessment is needed if the occupied or
functionally significant building is not subject to a credible major hazard or the effects of the hazard
can be mitigated in a cost effective manner. Where the building is occupied or functionally
significant and is subject to a credible hazard which cannot be easily designed out or mitigated, a risk
assessment is undertaken to check if the risks to the building occupants are acceptable or the
frequency of significant damage to unoccupied but functionally significant building is reasonably
low. Based on the risk assessment, cost effective and proportional mitigation options can be devised.
The QRA has been performed based initially on the three steps of the BRA methodology that are
summarized below:
1. Stage 1: A screening assessment based on building occupancy and its functional significance.
Only buildings considered to be occupied or functionally significant are taken to the Stage II
assessment. This is generally undertaken by the plant and confirmed by the consultant.
2. Stage 2: This phase involves analysis of worst credible consequences of the potential hazards
to assess building vulnerability for explosions, fires, flammable and toxic gases. Only
buildings considered to be vulnerable to the assessed hazards need to be taken to the 3rd stage
of assessment.
3. Stage 3: The 3rd stage of assessment involves calculation of risk to the building occupants and
where risks are high considers risk reduction measures.
4. In addition to the standard building risk assessment, the risks to the offsite population were
also assessed using the societal risk criteria for which the F-N curves were generated.
The tool used for the stage 2 consequence modelling was Shell FRED V 5.1 which is a suite of Fire,
Release, Explosion and Dispersion models used to predict the consequences of the accidental or
design release of product from process, storage, transport or distribution operations [3].
For the stage III risk assessment Shell SHEPHERD V2.1 was used. The Shell SHEPHERD Risk
Tool forms a family of graphical risk integrators. The tool has been developed to carry out fit-for-
purpose Quantified Risk Assessment (QRA) for a broad range of onshore industrial sites such as
Refineries, Gas plants, Chemicals plants, LPG distribution sites, pipeline systems etc. SHEPHERD
is used to systematically build up risk contributions starting from a release and working through
ignition sources to the calculation of the effects of cloud fires, jet fires, toxic gas and explosions.
Escalation to other parts of the plant via vessel failure through explosion over-pressure and/or flame
engulfment is handled automatically. The input required includes the mass flow rate and dispersion
distances to lower flammable limit in process blocks or point sources [4].

Page 13 of 96
o
Report N . 2514054 R01
Issue 4

3 DESCRIPTION OF FACILITY

3.1 Plant Description


The NSRP Refinery and Petrochemical Project will process 200,000 BPSD of imported Kuwait
Export Crude (KEC) oil. The fuels section of the refinery includes Residue Hydrodesulphurisation
and Residue Catalytic Cracking as the main upgrading units. The refinery is integrated with
petrochemical production. The Aromatics plant produces Paraxylene and Benzene. A key product
from the Residue Cracker is Propylene which is used to produce Polypropylene product [5].

The products produced include the following:

• LPG
• Gasoline – 92/ 95 RON
• Kerosene / Jet A-1
• Diesel – Premium and Regular
• Paraxylene / Benzene
• Polypropylene
• Sulphur

The refinery is situated in Nghi Son, Tinh Gia District, Thanh Hoa Province, Vietnam (approx. 200
km south of Hanoi) - See Figure 1.

Figure 1 - Proposed Location [Image taken from Google Earth]

The NSRP Project includes all process units and associated utility, offsite and infrastructure facilities
to support the refinery operation.

Page 14 of 96
o
Report N . 2514054 R01
Issue 4

• Complete utility facilities designed to meet the refinery’s demands for cooling water, fuels,
power, steam, water, instrument and plant air, inert gas, etc.
• Offsite facilities including tankage for feedstocks plus intermediate and final products as well
as systems for import and export of feed and products.
• Other offsite facilities including flare, effluent treatment, firewater, interconnecting piping
and pipelines, etc.
• Marine facilities include an SPM/ Crude import line and product loading jetties

3.1.1 Process Units


The complex will comprise the following licensed processing blocks:
The following unit description were based on the Refinery Design basis overall [5] supplied by
FWEL.
Refinery Process Units

• Crude Distillation Unit (CDU)


• LPG Recovery Unit
• Saturated LPG Treater Unit
• Kerosene Hydrodesulphuriser Unit (KHDS)
• Gas Oil Hydrodesulphuriser Unit (GOHDS)
• Residue Hydrodesulphuriser Unit (RHDS)
• Residue Fluid Catalytic Cracker Unit (RFCC)
• Propylene Recovery Unit (PRU)
• RFCC LPG Treater Unit
• RFCC Light Gasoline Treater Unit
• Selective Hydrogenation (SHU) and Indirect Alkylation Units (InAlk)
• Hydrogen Manufacturing Unit (HMU) and Hydrogen Compression and Distribution System
(HCDS)
• Sour Water Stripper Units (SWS)
• Amine Regeneration Unit (ARU)
• Sulphur Recovery Unit (SRU) and Tail Gas Treating (TGT)

Petrochemical Process Units

• Naphtha and Aromatics Complex (NAC)


• Polypropylene Unit (PPU)

Page 15 of 96
o
Report N . 2514054 R01
Issue 4

• Offsite Systems
• Crude Oil Import, Storage and Pumping System
• Inter Unit Storage and Pumping System
• Product Component Storage and Pumping System
• Product Storage and Pumping System
• Slop Storage and Pumping System
• Product Truck Loading System
• Sulphur Forming and Storage Unit

Utility Systems

• Demineralised water system,


• Raw water/potable systems
• Cooling water system,
• Steam Power generation system,
• Flue gas Desulphurisation,
• Plant air/Instrument Air System,
• Nitrogen System
• Fuel Oil System
• Fuel Gas System
• Flushing oil system
• Chemical Supply

Electricity and steam is generated at the Cogeneration plant.

3.1.2 Buildings
In all 59 buildings have been identified on the plant layout (See Figure 2 and Figure 3). On the
previous study [14] ABSC numbered these buildings consecutively from number 1 to number 66. To
allow direct comparison this system has been retained. These buildings are tabulated in Table 1.

Page 16 of 96
o
Report N . 2514054 R01
Issue 4

Figure 2 – NSRP Main Plant Plot Plan [6]

Page 17 of 96
o
Report N . 2514054 R01
Issue 4

Figure 3 – NSRP Plant Plot Plan (Jetty area) [7]

Page 18 of 96
o
Report N . 2514054 R01
Issue 4

4 STAGE 1 ASSESSMENT

The scope of the Stage one assessment is to carry out a building screening exercise in order to
eliminate buildings of no safety concern (unoccupied and not functionally significant) from the risk
assessment process.

The stage I screening has been completed by FWEL using the API 752 [1] criteria described below;

4.1 Screening Criterion

4.1.1 Occupancy Screening


For the purposes of occupancy screening a building is considered occupied if the building occupancy
load is 300 or more man-hours per week or if during peak occupancy, 5 people or more are routinely
expected in the building for at least one hour. If this criteria is exceeded the building is selected for
second stage (Stage 2) analysis.

4.1.2 Functionality Screening


A stage-two building evaluation is required if a building is functionally significant. A building is
defined as functionally significant if either:

• People are expected to remain or take refuge in the building during an emergency. Possible
reasons for people to remain in a building include a lack of suitable evacuation options or the
need for occupants to perform emergency shutdown procedures.
• The building is required for emergency response, such as fire stations or clinics.
• The building is necessary for continued operation of plant units that may be able to continue
to operate or may be unaffected by an incident in another area. This includes control
buildings, process interface buildings (PIBs), or substations that control or provide power to
multiple process units.
• The economic impact on operations of loss of buildings is significant.

4.2 Stage One Results


A summary of the occupancy details is provided in Table 1 along with whether the building is
functionally critical or required to provide shelter during an emergency. Previously the buildings
were numbered 1 to 66. The building numbering system has been retained within this study to
facilitate a direct comparison. However, please note that numbers 17, 29, 35, 47, 61, 63 and 64 have
not been used as they were either missing on the plot plan [6] or have been revised.
Twelve building are assessed as being occupied and thirty eight as functionally significant. Six
buildings are both occupied and functionally significant. Eleven building have been screened out as
being neither occupied nor functionally significant.
The buildings taken to the second stage of this assessment are shown in Figure 4.

Page 19 of 96
o
Report N . 2514054 R01
Issue 4

Table 1 – Stage 1 Assessment

5 people or more Carry


Project Peak Total High Occupancy
Functionally routinely expected in Forward
Building Building Name Occupancy (>300 man-hours
Significant the building for at For
Number Occupancy (hr/week) per week)
least an hour? Stage 2

1 Administration Building 172 6880 Yes Yes Yes Yes

2 Canteen No1 120 6720 Yes Yes Yes Yes

3 Medical Center 6 756 Yes Yes Yes Yes

4 Main Guard House 6 756 Yes Yes Yes Yes

5 Central Control Room 90 6260 Yes Yes Yes Yes

6 CCR Oil Movements 0 0 Yes No No No

7 Laboratory 55 2200 No Yes Yes Yes

8 Maintenance Workshop 45 3812 No Yes Yes Yes

9 Warehouse 11 440 No Yes Yes Yes

10 Central Chemical Store 1 126 No No No No

11 Central Catalyst Store 2 252 No No No No

Page 20 of 96
o
Report N . 2514054 R01
Issue 4

5 people or more Carry


Project Peak Total High Occupancy
Functionally routinely expected in Forward
Building Building Name Occupancy (>300 man-hours
Significant the building for at For
Number Occupancy (hr/week) per week)
least an hour? Stage 2

12 Canteen No2 120 6720 No Yes Yes Yes

13 Fire Station 4 504 Yes No Yes Yes

14 Main Substation SS-M01 0 0 Yes No No Yes

15 Emergency Generator 0 0 Yes No No Yes

16 Truck Loading Office 4 160 No No No No

18 SS- U04 0 0 Yes No No Yes

19 SS-O04 0 0 Yes No No Yes

20 SS- U01 0 0 Yes No No Yes

21 SS- P09 0 0 Yes No No Yes

22 SS- P07 0 0 Yes No No Yes

23 SS-P02 0 0 Yes No No Yes

24 SS-P06 0 0 Yes No No Yes

Page 21 of 96
o
Report N . 2514054 R01
Issue 4

5 people or more Carry


Project Peak Total High Occupancy
Functionally routinely expected in Forward
Building Building Name Occupancy (>300 man-hours
Significant the building for at For
Number Occupancy (hr/week) per week)
least an hour? Stage 2

25 SS- P03 0 0 Yes No No Yes

26 SS- P04 0 0 Yes No No Yes

27 SS- P01 0 0 Yes No No Yes

28 SS- P08 0 0 Yes No No Yes

30 SS-P05 0 0 Yes No No Yes

31 SS-U03 0 0 Yes No No Yes

32 SS-O03 0 0 Yes No No Yes

33 SS-U02 0 0 Yes No No Yes

34 SS-O01 0 0 Yes No No Yes

36 ISB-014 0 0 Yes No No Yes

37 ISB-013 0 0 Yes No No Yes

38 ISB-03 0 0 Yes No No Yes

Page 22 of 96
o
Report N . 2514054 R01
Issue 4

5 people or more Carry


Project Peak Total High Occupancy
Functionally routinely expected in Forward
Building Building Name Occupancy (>300 man-hours
Significant the building for at For
Number Occupancy (hr/week) per week)
least an hour? Stage 2

39 ISB-011 0 0 Yes No No Yes

40 ISB-06 0 0 Yes No No Yes

41 ISB-05 0 0 Yes No No Yes

42 ISB-04 0 0 Yes No No Yes

43 ISB-02 0 0 Yes No No Yes

44 ISB-12 0 0 Yes No No Yes

45 ISB-01 0 0 Yes No No Yes

46 ISB-10 0 0 Yes No No Yes

48 ISB-08 0 0 Yes No No Yes

49 ISB-07 0 0 Yes No No Yes

50 ISB-18 0 0 Yes No No Yes

51 ISB-17 0 0 Yes No No Yes

Page 23 of 96
o
Report N . 2514054 R01
Issue 4

5 people or more Carry


Project Peak Total High Occupancy
Functionally routinely expected in Forward
Building Building Name Occupancy (>300 man-hours
Significant the building for at For
Number Occupancy (hr/week) per week)
least an hour? Stage 2

52 ISB-15 0 0 Yes No No Yes

53 ISB-16 0 0 Yes No No Yes

54 ISB-19 0 0 Yes No No Yes

55 Local Guardhouse No1 2 252 No No No No

56 Jetty Area Guardhouse 2 336 No No Yes Yes

57 Operator Shelter No1 0 0 No No No No

58 Operator Shelter No2 0 0 No No No No

59 Solid Product Warehouse 0 0 No No No No

60 Jetty Area Admin/Control Building 21 1442 Yes Yes Yes Yes

62 Jetty Area Workshop 0 0 No No No No

65 Jetty Area Storage Building 0 0 No No No No

66 Crude Oil Terminal Spares Warehouse 0 0 No No No No

Page 24 of 96
o
Report N . 2514054 R01
Issue 4

Figure 4 – 2nd Stage Buildings

Page 25 of 96
o
Report N . 2514054 R01
Issue 4

5 STAGE 2 ASSESSMENT (CONSEQUENCE ANALYSES)

5.1 Explosion Analyses

5.1.1 Credible Explosion Hazards


The flammable gas accumulating in a congested region and subsequent delayed ignition results in an
explosion. So for an explosion to occur there should be a source of flammable release near a
congested area. Considering both the PFD and the plot plan, the following potential sources of
explosion were identified for explosion consequence modeling.

• CDU
• LPG Recovery and Treater Unit
• KHDS
• GOHDS
• RHDS
• RFCC
• PPU
• SHU and Ind Alk
• HMU
• HCDS
• NAC
• Berth Area
• Tanks pumping system
• Fuel gas system

5.1.2 CAM Assessment


For the congested areas in the Aromatics Complex, RFCC Unit and Hydrogen Manufacturing plant,
the parameters were derived using Shell’s guidelines and based upon the plot plans provided. For the
remaining units an engineering judgment was use to set this parameters as more detailed plot plants
weren’t available at the time of this assessment.

5.1.3 Review of Hazard Consequences


The maximum credible overpressure and impulse for each building is provided in Table 2.

Page 26 of 96
o
Report N . 2514054 R01
Issue 4

Table 2 - Maximum Credible Explosion Hazard

Building Overpressure Impulse


Building Name
Number (psi) (psi-ms)

1 Administration Building 0.4 20

2 Canteen No1 0.3 18

3 Medical Center 0.3 17

4 Main Guard House 0.3 18

5 Central Control Room 0.6 29

7 Laboratory 0.4 24

8 Maintenance Workshop 0.7 31

9 Warehouse 0.6 29

12 Canteen No2 0.4 22

13 Fire Station 0.4 24

14 Main Substation 3.2 94

15 Emergency Generator 1.5 58

18 SS- U04 0.6 25

19 SS-O04 3.2 94

20 SS- U01 43.5 761

21 SS- P09 37.7 725

22 SS- P07 20.3 580

23 SS-P02 10.2 236

24 SS-P06 23.2 471

25 SS- P03 13.8 326

26 SS- P04 0.4 20

Page 27 of 96
o
Report N . 2514054 R01
Issue 4

Building Overpressure Impulse


Building Name
Number (psi) (psi-ms)

27 SS- P01 7.3 181

28 SS- P08 7.0 44

30 SS-P05 6.4 145

31 SS-U03 2.3 109

32 SS-O03 0.6 31

33 SS-U02 2.0 47

34 SS-O01 1.2 34

36 ISB-014 2.6 87

37 ISB-013 43.5 1233

38 ISB-03 16.0 290

39 ISB-011 58.0 1305

40 ISB-06 21.8 580

41 ISB-05 21.8 580

42 ISB-04 8.7 160

43 ISB-02 2.0 80

44 ISB-12 7.0 174

45 ISB-01 7.3 181

46 ISB-10 8.0 181

48 ISB-08 3.8 174

49 ISB-07 4.6 145

50 ISB-18 1.0 44

51 ISB-17 7.3 181

Page 28 of 96
o
Report N . 2514054 R01
Issue 4

Building Overpressure Impulse


Building Name
Number (psi) (psi-ms)

52 ISB-15 7.0 44

53 ISB-16 0.6 31

54 ISB-19 1.5 36

56 Jetty Area Guard House 0.1 3

60 Jetty Area Admin/Control Building 0.1 7

Figure 5 and Figure 6 shows the maximum credible overpressure values.

Page 29 of 96
o
Report N . 2514054 R01
Issue 4

Figure 5 – Maximum Credible Overpressures Main Plant

Page 30 of 96
o
Report N . 2514054 R01
Issue 4

Figure 6 – Maximum Credible Overpressures Jetty Area

Page 31 of 96
o
Report N . 2514054 R01
Issue 4

5.2 Fire Analysis

5.2.1 Credible Fire Hazards


The following list summarises the main potential fire sources for fire consequence modeling:

• CDU
• LPG Recovery and Treater Unit
• KHDS
• GOHDS
• RHDS
• RFCC
• PPU
• SHU and Ind Alk
• HMU
• HCDS
• NAC
• Berth Area
• Storage Tanks and pumping system
• Spheres
• Propane loading
• Fuel Gas system

Figure 7 and Figure 8 show the maximum potential incident radiation flux contours.

Page 32 of 96
o
Report N . 2514054 R01
Issue 4

Figure 7 – Maximum Potential Incident Radiation Flux Contours Main Plant

Page 33 of 96
o
Report N . 2514054 R01
Issue 4

Figure 8 – Maximum Potential Incident Radiation Flux Contours Jetty Area

Page 34 of 96
Report No. 2514054 R01
Issue 4

5.2.2 Boiling Liquid Expanding Vapour Explosion (BLEVE) Hazards


The potential BLEVE hazards identified are listed below. A consequence modeling has been
undertaken for these BLEVE scenarios.

• Product storage (Spheres)


• LPG Loading

True BLEVEs are associated with liquid gases such as propane which are stored as liquid by keeping
them under pressure at temperatures far in excess of the boiling points of the material. For example
the boiling point of propane is -42oC. Being kept at an ambient temperature of 30oC represents a very
large temperature difference for this liquid. Therefore, an increase in the temperature for the liquid
from a relatively small fire would tend to rapidly increase the pressure as the material tries to return
to a gaseous state. The material could go into a superheated state, and, given the sudden loss of
containment when the shell of the containing vessel fails due to the applied heat load and loss of
strength, the superheated liquid would instantly vaporize causing a rapid expansion in volume (of the
order of 100s of times the liquid volume) giving rise to the fireball that is inherent in the BLEVE
event.
The maximum fireball diameter contours are show in Figure 9.

Page 35 of 96
Report No. 2514054 R01
Issue 4

Figure 9 – BLEVE Fireballs Diameters

Page 36 of 96
o
Report N . 2514054 R01
Issue 4

A summary of the Maximum Incident Radiation flux from the modeled fire scenarios for each
building is given in Table 3.

Table 3 - Maximum Credible Fire Hazard

Max. Incident
Building
Building Name Radiation
Number 2
(kW/m )

1 Administration Building Negligible

2 Canteen No1 Negligible

3 Medical Center Negligible

4 Main Guard House Negligible

5 Central Control Room 4

7 Laboratory Negligible

8 Maintenance Workshop 4

9 Warehouse 4

12 Canteen No2 Negligible

13 Fire Station Negligible

14 Main Substation SS-M01 11

15 Emergency Generator 11

18 SS- U04 7

19 SS-O04 Negligible

20 SS- U01 23

21 SS- P09 >50

22 SS- P07 >50

23 SS-P02 >50

24 SS-P06 >50

Page 37 of 96
o
Report N . 2514054 R01
Issue 4

Max. Incident
Building
Building Name Radiation
Number 2
(kW/m )

25 SS- P03 >50

26 SS- P04 >50

27 SS- P01 >50

28 SS- P08 >50

30 SS-P05 >50

31 SS-U03 23

32 SS-O03 >50

33 SS-U02 >50

34 SS-O01 5

36 ISB-014 6

37 ISB-013 >50

38 ISB-03 >50

39 ISB-011 >50

40 ISB-06 >50

41 ISB-05 >50

42 ISB-04 >50

43 ISB-02 >50

44 ISB-12 >50

45 ISB-01 >50

46 ISB-10 >50

48 ISB-08 >50

Page 38 of 96
o
Report N . 2514054 R01
Issue 4

Max. Incident
Building
Building Name Radiation
Number 2
(kW/m )

49 ISB-07 >50

50 ISB-18 >50

51 ISB-17 >50

52 ISB-15 6

53 ISB-16 20

54 ISB-19 >50

56 Local Guardhouse Jetty Area Negligible

60 Jetty Area Admin/Control Building 4

5.3 Toxic Analysis

5.3.1 Credible Toxic Hazards


The following list summarises the locations of potential sources for toxic gas release and thus
included in consequence modeling:

• CDU
• SWS
• ARU
• SRU
• RFCC
• GOHDS
• KHDS
• RHDS

Page 39 of 96
o
Report N . 2514054 R01
Issue 4

5.3.2 Review of Hazard Consequences


The hazard distances for toxic H2S gas from maximum credible release scenarios were calculated for
each of the three Emergency Response Planning Guide (ERPG) values and are provided in Table 4.

Table 4 – Toxic Gas (H2S) Dispersion modelling results for the 150mm hole size

Downwind distance (m)

ERPG1 ERPG2 ERPG3

Unit (0.1 ppm) (30 ppm) (100 ppm)

D5 Weather F2 Weather D5 Weather F2 Weather D5 Weather F2 Weather

24723 106764 1702 10831 826 4252


SRU
1398 6664 1398 6664 672 2857
086/087/088
1089 7809 39 55 33 48

RFCC 020 25294 106764 902 3700 446 1710

25551 106764 1089 9182 540 3700


SWS 080
35256 106764 2378 18031 1126 6664

GOHDS014 18031 106764 720 2537 330 440

KHDS 013 25551 106764 880 4252 410 960

CDU 010 18031 106764 720 2537 330 440

ARU 084 24723 106764 1702 10831 826 4252

RHDS 020 47641 106764 2149 21449 999 7809

Note: The dispersion modeling was performed for two Pasquill-Gifford categories:

• D5: atmospheric stability class D with 5m/s wind speed.


• F2: atmospheric stability class F with 2m/s wind speed.

The Emergency Response Planning Guidelines (ERPGs) are intended to be a planning tool to help
anticipate human adverse health effects to the general public caused by toxic chemical exposure.
The ERPGs are three-tiered guidelines, with a common denominator: 1 hour exposure duration. The
levels are defined as follows in Figure 10:

Page 40 of 96
o
Report N . 2514054 R01
Issue 4

Figure 10 – ERPG Levels

In this assessment the AIHA ERPG-2008 values were adopted to investigate the potential for off-site
adverse effects to humans due to toxic H2S exposure [10].

• ERPG-1: 0.1 ppm


• ERPG-2: 30 ppm
• ERPG-3: 100 ppm

Figure 11 shows the ERPG-2 and 3 contours to the Amine Acid gas on the SRU unit considering a
150mm hole size release for D5 condition.

Page 41 of 96
o
Report N . 2514054 R01
Issue 4

Figure 11 – ERPG Contours for the SRU

Page 42 of 96
o
Report N . 2514054 R01
Issue 4

5.4 Stage II Screening


From the review of the credible hazards modeled, it is apparent that most of the buildings taken to
stage II screening are subject to significant fire and /or explosion hazard. Conservatively therefore
all the buildings considered in the stage II assessment have been retained for the Stage III risk
assessment.

6 STAGE 3 ASSESSMENT (RISK ANALYSIS)

6.1 Model Development


The SHEPHERD model was updated using the plot plans [6].
The mass and energy balance was used to define the process condition within each of the main plant
items so that process specific fluid could be used in the consequence assessment.
The plot plans and other documents were used to define the process areas for the QRA and also used
to define the congested areas.
A plot of the SHEPHERD model is given in Figure 12 and Figure 13. The offsite area to the west,
South and East are termed areas A, B and C respectively.

Page 43 of 96
o
Report N . 2514054 R01
Issue 4

Figure 12 – SHEPHERD Model Main Plant

Page 44 of 96
o
Report N . 2514054 R01
Issue 4

Figure 13 – SHEPHERD model Jetty Area

Page 45 of 96
o
Report N . 2514054 R01
Issue 4

6.2 SHEPHERD Parameters

6.2.1 Equipment Count and Leak Frequencies


The main plant items were identified and grouped depending on the fluid composition, with process
pressure and process temperature in the same order of magnitude into process blocks, which were
entered into the Shell SHEPHERD model. The model uses the Multiple Object as a single place
holder for defining more than one process block in the model to reduce the number of physical
objects drawn in the model. Using the generic parts count (e.g. vessels or compressors), a
distribution of flanges and connections etc are applied internally within the SHEPHERD model
based on a distribution defined by Shell. Each of the flanges, connections and fittings etc associated
with a generic piece of equipment thus provides the leak source and associated frequency.
The leak frequencies are generally based on the generic data from the Hydrocarbon Leak and
Ignition Database, EP Forum Risk Assessment Data Directory, EP Forum Report No. 11.8/250, E&P
Forum, (1996) [8].
The leak frequencies for the LPG filling station used are generally accepted on the onshore industry.
A summary of the leak frequencies used is presented in Table 5 below.

Table 5 - Leak Frequencies used within the Process Blocks

Leak Frequency/
Holes year
Leak Type
Size
Process LPG

Process Blocks
-4
10mm Flange Leak 1.5x10 -

10mm Seal Leak -3 -4


7x10 5.2x10
(pump)
-4
25mm Fitting Leak 2.35x10 -
-5
50mm Connection 3.8x10
Leak -
-6
100mm Pipe Leak 3.5x10
(*1/D) -

LPG Filling Station

10mm General - 5.22E-01

25mm General - 3.86E-04

50mm General - 4.41E-04

100mm General - 5.17E-02

Page 46 of 96
o
Report N . 2514054 R01
Issue 4

6.2.2 Design, Operation & Maintenance Factors


The failure rate data applied in the study represents industry average values, although in order to take
plant condition into account within the risk calculation, SHEPHERD allows for the effectiveness of
prevention and shutdown measures to be taken into account. Factors including design, operation and
maintenance (DOM) are considered. A DOM factor is used by SHEPHERD and is applied to
account for the effectiveness of the prevention measures, categorised as high, average or low. In
order to obtain a site-specific failure frequency, the “average” value is modified using the input
DOM factor. In selecting a “low” effectiveness, the failure frequency is multiplied by the DOM
factor and divided by the DOM factor for “high” effectiveness. Hence selecting the “average” does
not change the failure frequency value.
For the base case quantitative risk assessment, the effectiveness of the design, operation and
maintenance was assumed to be average. Therefore, the industry average failure rate data was used.

6.2.3 Probability of Emergency Shutdown


Inventory isolation time (response time) is assumed to be 20 minutes after start of a release except
for the RFCC for which inventory isolation within 5 minutes with a 50% probability and isolation
following fire detection with a probability of 80% is assumed. This assumption affects the only the
escalation potential, all the releases are modelled.

6.2.4 Building Performance


A number of studies have sought to generate guidance on building damage and collapse, and
consequent fatality rates, for different categories of buildings. Some studies have considered both
the overpressure and impulse resulting from the explosion, while others have only correlated the
effects against the overpressure. Analytical tools have also been developed to assist with this
analysis. The work reported here is based on the results of the 1995 Petroleum and Chemical
Processing Industry Technology Co-operative report on Conventional Building Blast Performance
Capabilities.
API RP-752 [1] defines a set of building classifications included within Shell SHEPHERD
Exceedance, given in Table 6 [4].

Table 6 - Definition of Shell building types used in SHEPHERD

Shell
Building Description
Type

B1 Wood, temporary buildings, trailers

B2 Steel frame with metal siding

B3 Brick/un-reinforced masonry (load bearing wall)

B4 Steel or concrete frame with masonry fill or cladding

B5 Blast resistant (reinforced concrete)

B6 Brick/moderately reinforced masonry – load bearing

Page 47 of 96
o
Report N . 2514054 R01
Issue 4

Shell
Building Description
Type

B7 Steel frame building with pre-cast walls and concrete roof

Custom type – specify the design free-field overpressure at 100ms


B8
pulse duration

Each building type has its own unique resistance to blast damage. The blast damage resistance of
various building types is shown in Figure 14.

Overpressure Versus Vulnerability

14.0

12.0
Peak Incident Overpressure (psi)

10.0

8.0 B1,B2 & B4


B5
B6
6.0 B3

4.0

2.0

0.0
0 0.2 0.4 0.6 0.8 1 1.2
Probability of Serious Injury/Fatality

Figure 14 – Building vulnerability by type

The Co-Operative has also suggested a relationship between vulnerability and building damage level.
These are given in Table 7.

Page 48 of 96
o
Report N . 2514054 R01
Issue 4

Table 7 -Vulnerability dependence on damage thresholds

Damage level
Vulnerability
interface

0.01 1/2A

0.1 2A/2B

0.3 2B/3

0.6 3/4

1.0 4/5

The definition of blast damage levels from the Co-Operative study are given in Table 8.

Table 8 - Definition of damage categories

Discrete
Brief
damage Full description
description
level

Onset of visible damage. Repairs are only needed


Minor
1 for cosmetic reasons. Building is reusable
damage
following an explosion.

Localised building damage. Building performs


Moderate function and can be used; however, major repairs
2A
damage are required to restore integrity of structural
envelope. Total cost of repairs is moderate.

Widespread building damage. Building cannot be


Moderate used until major repairs are completed. Total cost
2B
damage of repairs is significant, approaching replacement
cost of building.

Building has lost structural integrity and may


Major collapse due to environmental conditions (i.e.
3
damage wind, snow, rain). Total cost of repairs exceeds
replacement cost of building.

4 Collapse Building fails completely. Repair not feasible.

Page 49 of 96
o
Report N . 2514054 R01
Issue 4

Discrete
Brief
damage Full description
description
level

5 Annihilation Occupant survival is not possible.

6.3 Fire & Toxic Hazard Modelling


Within the SHEPHERD fire and toxic model a number of user defined probabilities are required
which have an influence on the calculation of the individual risk contours. These are described in the
following sections. As well as these requirements, the model also requires results from the
consequence assessment e.g. mass flow rate, LFL distance and distance to 1% fatalities due to
exposure to a toxic substance.

6.3.1 Fatality Probabilities


The fatality probabilities used for a person located outside are listed in Table 9.

Table 9- Fatality Probabilities from Exposure to Fires and Toxins

Consequence Fatality Probability


2
Flame engulfment (>50kW/m ) 1
2
Thermal radiation (>10kW/m ) 0.7

Toxic Gas Based on probit functions published in the


TNO Purple Book (CPR18).
1.9
H2S Probit = -11.5+ln(C t) where t is the
exposure time in minutes set at 30 min and C
3
is the calculated concentration in mg/m .

It is highlighted that the fatality risk from exposure to the effects of fires and toxics will be different
for people depending on the location of the person from the hazard and if they are inside or outside a
building, due to the protection afforded by the building, i.e. lower hazard frequency within the
building. For instance anyone outdoors caught within a flash fire (the LFL envelope) would be killed
(i.e. fatality probability of 1), but if adequately protected from the flames indoors may not be.

6.3.2 Ignition Probabilities


The immediate ignition probabilities adopted in this assessment were derived from Cox Lees and
Ang “Classification of Hazardous Locations” [9] who have related the probability of ignition of
release of flammable material and discharge rate. These probabilities are those given in Table 10.

Page 50 of 96
o
Report N . 2514054 R01
Issue 4

Table 10 – Immediate Ignition Probabilities

Probability of Ignition
Leak Rate (kg/s)
Gas Liquid

<1 0.01 0.01

1 – 50 0.07 0.03

>50 0.30 0.08

A site background ignition probability of 1E-4/m2 of the facility was adopted for this assessment, in
order to address the potential for delayed ignition with the fire modelling. For the offsite urban
location a probability of ignition of 0.25E-4/m2 as suggested by the UKHSE has been adopted. The
additional ignition probability for the road to the south of the site is based on the traffic conditions
assuming that a vehicle represents a probability of ignition of 0.1.
For explosion modelling, the exceedance module has been used which requires a delayed ignition
probability to be specified. The delayed ignition probability used for explosion modelling is given in
Table 11.

Table 11 – Delayed Ignition Probabilities

Probability of Ignition
Leak Rate (kg/s)
Gas Liquid

<1 0.0004 0.0004

1 – 50 0.008 0.0036

>50 0.09 0.024

6.3.3 Building Protection Features


People located inside buildings will be protected to some extend from external hazards depending on
the type of building construction. These building protection levels are used to modify the probability
of fatality and are explained in Table 12.

Page 51 of 96
o
Report N . 2514054 R01
Issue 4

Table 12 - Levels of Building Protection against Fire & Toxic Hazards

Level of protection used


Protection Description
for all buildings

0% (Building Types B1)

This is the effectiveness (%) of the


Combustible Gas 50% (Building Types
protection provided against the ingress
Protection (%) B2,B3,B4,B6+)
of combustible gas.

90% (Building Type B5)

0% (Building Types B1)

This is the effectiveness (%) of the


90% (Building Types
Flame Protection protection provided against jet flame
B2,B3,B4,B6+)
impingement.

90% (Building Type B5)

0% (Building Types B1)

This is the effectiveness (%) of the


90% (Building Types
Flux Protection protection provided against thermal
B2,B3,B4,B6+)
radiation.

90% (Building Type B5)

0 ACPH (Building Types


To estimate the toxic gas concentration
B1)
within a building the number of air
changes per hour is required. This 2 ACPH (Building Types
Toxic Gas Protection
concentration is used in the probability B2,B3,B4,B6+)
equation to estimate the fatalities due to
2 ACPH (Building Type
toxic gas exposure
B5)

6.3.4 Fire Resistance of Buildings


Impairment of structural integrity is defined as loss of ability to support the buildings and facilities.
This may be due to loss of stability or structural failure due to fire or explosion.
Accordingly, loss of integrity within one hour of the following is considered:
• Structural integrity, including the supporting structure,
• Life support integrity, including prevention and mitigation of smoke and gas ingress, and
• Command support integrity.

Page 52 of 96
o
Report N . 2514054 R01
Issue 4

Table 13 provides details of design limits for various types of structure and plant.

Table 13 - Thermal Radiation Limits for Structures and Plant

Thermal Radiation Intensity


2
Thermal Limit
(kW/m )

Intensity at which damage is caused to process equipment and


37.5
tanks

25 Intensity at which non-piloted ignition of wood occurs

18-20 Intensity at which cable insulation degrades

Intensity at which operators are unlikely to be performing and


15.6
where shelter is unavailable.

14 Intensity which normal buildings should be design to withstand

12 Intensity at which plastics may begin to melt

6.3.5 Boiling Liquid Expanding Vapour Explosion (BLEVE) Scenario


The failure time for the pressurised liquid gas vessel such as product spheres from flame
impingement resulting in a BLEVE was taken as 10 minutes, which is considered to be accepted
practice within the industry.

6.4 Risk Acceptance Criteria


The purpose of risk assessment is to aid decision making and in order to do this some form of criteria
is required. In many cases risk assessment is used for comparative purposes or to identify areas or
scenarios that present the greatest risk so that risk reduction can be carried out in a sensible and cost
effective way. The use of risk assessment, however, must be performed with care, because of the
uncertainties inherent in the assessment. Furthermore there is no clear consensus with respect to the
values of tolerable or unacceptable risks, as this varies between organisations and countries.
The parameter used as a measure of risk in this study is the Individual Risk (IR).

6.4.1 Individual Risks


Individual risks involve the definition of the following elements:
• An upper risk level, beyond which risks are deemed unacceptable;
• A lower risk level, below which risks are deemed not to warrant concern; and
• An intermediate region between the upper and lower levels where risk reduction measures are
required to achieve a level deemed to be As Low As Reasonably Practicable (ALARP).

The ALARP risk review process is illustrated in Figure 15.

Page 53 of 96
o
Report N . 2514054 R01
Issue 4

UNACCEPTABLE INTOLERABLE
REGION LEVEL

(Risk cannot be justified save


in extraordinary circumstances)

Tolerable only if risk reduction is


impracticable or if its cost is
grossly disproportionate to the
improvement gained

ALARP
REGION Benchmark representing
the standard to be met
by new plant
(Risk is undertaken only if a
benefit is desired)

Tolerable if cost of
reduction would exceed
the improvement gained

BROADLY
ACCEPTABLE Necessary to maintain assurance
REGION that risk remains at this level

(No need for detailed working


to demonstrate ALARP)

NEGLIGIBLE RISK

Figure 15 - Levels of Risk and ALARP

This assessment uses the following framework as agreed with FWEL:


For Industrial workers
• >10-3/year - Level at which mitigation of risk is required,

Page 54 of 96
o
Report N . 2514054 R01
Issue 4

• >10-3/year but <10-5/year - Level at which risk reduction should be considered


(i.e. ALARP region),
• <10-5/year - Level at which further risk reduction need not be considered.
For general population
• >10-4/year - Level at which mitigation of risk is required,
• >10-4/year but <10-6/year - Level at which risk reduction should be considered
(i.e. ALARP region),
<10-6/year - Level at which further risk reduction need not be considered

6.5 Evaluation of Building Risks

6.5.1 Explosion Risks


The flammable gas frequency for the site is shown in Figure 16 and Figure 17. Figure 18 to Figure
21 show the frequency of exceeding an overpressure of 100 mbar and 30 mbar respectively.
The explosion risk to the workers is dependent on the protection afforded by various building as is
thus dependent on building types. Figure 22 and Figure 23, Figure 24 and Figure 25, Figure 26 and
Figure 27 show the explosion risks to building types B2, B4 and B5 respectively.
All the occupied buildings at this site are shown to have very low explosion risk. Table 14
summarizes the over-pressure and anticipated damage from a 10-4 per year explosion scenario.

Table 14- Summary Explosion Damage for the 10-4/yr Hazard

Building 10-4 Peak


Building Explosion
Building Name classification Overpressure
Number Damage (10-4)
(B1-B7) (psi)

1 Administration Building B4 0.2 Minor, Level 1

2 Canteen No1 B4 0.2 Minor, Level 1

3 Medical Center B4 0.2 Minor, Level 1

4 Main Guard House B4 0.2 Minor, Level 1

5 Central Control Room B5 0.3 Minor, Level 1

7 Laboratory B4 0.2 Minor, Level 1

8 Maintenance Workshop B2 0.3 Minor, Level 1

9 Warehouse B2 0.2 Minor, Level 1

12 Canteen No2 B4 0.2 Minor, Level 1

Page 55 of 96
o
Report N . 2514054 R01
Issue 4

Building 10-4 Peak


Building Explosion
Building Name classification Overpressure
Number Damage (10-4)
(B1-B7) (psi)

13 Fire Station B4 0.2 Minor, Level 1

14 Main Substation B5 0.4 Minor, Level 1

15 Emergency Generator B5 0.4 Minor, Level 1

18 SS- U04 B4 0.3 Minor, Level 1

19 SS-O04 B4 0.2 Minor, Level 1

20 SS- U01 B4 0.4 Minor, Level 1

21 SS- P09 B4 1.0 Minor, Level 1

22 SS- P07 B4 1.1 Minor, Level 1

23 SS-P02 B4 1.1 Minor, Level 1

24 SS-P06 B4 0.7 Minor, Level 1

25 SS- P03 B4 0.9 Minor, Level 1

26 SS- P04 B4 3.5 Minor, Level 1

27 SS- P01 B4 0.5 Minor, Level 1

28 SS- P08 B4 0.5 Minor, Level 1

30 SS-P05 B4 0.8 Minor, Level 1

31 SS-U03 B4 0.6 Minor, Level 1

32 SS-O03 B4 0.3 Minor, Level 1

33 SS-U02 B4 0.0 Minor, Level 1

34 SS-O01 B4 0.1 Minor, Level 1

36 ISB-014 B5 0.3 Minor, Level 1

37 ISB-013 B5 0.4 Minor, Level 1

Page 56 of 96
o
Report N . 2514054 R01
Issue 4

Building 10-4 Peak


Building Explosion
Building Name classification Overpressure
Number Damage (10-4)
(B1-B7) (psi)

38 ISB-03 B5 0.9 Minor, Level 1

39 ISB-011 B5 0.9 Minor, Level 1

40 ISB-06 B5 1.5 Minor, Level 1

41 ISB-05 B5 0.8 Minor, Level 1

42 ISB-04 B5 0.8 Minor, Level 1

43 ISB-02 B5 1.7 Minor, Level 1

44 ISB-12 B5 0.5 Minor, Level 1

45 ISB-01 B5 0.5 Minor, Level 1

46 ISB-10 B5 0.5 Minor, Level 1

48 ISB-08 B5 0.6 Minor, Level 1

49 ISB-07 B5 0.8 Minor, Level 1

50 ISB-18 B5 0.6 Minor, Level 1

51 ISB-17 B5 0.2 Minor, Level 1

52 ISB-15 B5 0.1 Minor, Level 1

53 ISB-16 B5 0.3 Minor, Level 1

54 ISB-19 B5 0.0 Minor, Level 1

56 Jetty Area Guard House B4 0.0 Minor, Level 1

60 Jetty Area Admin/Control Building B5 0.0 Minor, Level 1

Page 57 of 96
o
Report N . 2514054 R01
Issue 4

Figure 16 – Flammable Gas Frequency across the Main Plant

Page 58 of 96
o
Report N . 2514054 R01
Issue 4

Figure 17 – Flammable Gas Frequency across the Jetty Area

Page 59 of 96
o
Report N . 2514054 R01
Issue 4

Figure 18 - Frequency of Overpressure Exceeding 100 mbar Main Plant

Page 60 of 96
o
Report N . 2514054 R01
Issue 4

Figure 19 - Frequency of Overpressure Exceeding 100 mbar Jetty Area

Page 61 of 96
o
Report N . 2514054 R01
Issue 4

Figure 20 - Frequency of Overpressure Exceeding 30 mbar Main Plant

Page 62 of 96
o
Report N . 2514054 R01
Issue 4

Figure 21 - Frequency of Overpressure Exceeding 30 mbar Jetty Area

Page 63 of 96
o
Report N . 2514054 R01
Issue 4

Figure 22 - Explosion Risk Plot for Building Type B2 Main Plant

Page 64 of 96
o
Report N . 2514054 R01
Issue 4

Figure 23 - Explosion Risk Plot for Building Type B2 Jetty Area

Page 65 of 96
o
Report N . 2514054 R01
Issue 4

Figure 24 - Explosion Risk Plot for Building Type B4 Main Plant

Page 66 of 96
o
Report N . 2514054 R01
Issue 4

Figure 25 - Explosion Risk Plot for Building Type B4 Jetty Area

Page 67 of 96
o
Report N . 2514054 R01
Issue 4

Figure 26 - Explosion Risk Plot for Building Type B5 Main Plant

Page 68 of 96
o
Report N . 2514054 R01
Issue 4

Figure 27 - Explosion Risk Plot for Building Type B5 Jetty Area

Page 69 of 96
o
Report N . 2514054 R01
Issue 4

6.5.2 Fire Risk


The frequency of cloud fire, frequency contour plots for heat flux exceeding 15kW/m2 and BLEVE
frequency plots are shown in Figure 28, Figure 29, Figure 30, Figure 31 and Figure 32 respectively.

Page 70 of 96
o
Report N . 2514054 R01
Issue 4

Figure 28 - Cloud Fire Frequency Contour Plot Main Plant

Page 71 of 96
o
Report N . 2514054 R01
Issue 4

Figure 29 - Cloud Fire Frequency Contour Plot Jetty Area

Page 72 of 96
o
Report N . 2514054 R01
Issue 4

Figure 30 - Frequency Contour Plot for Heat Flux above 15kW/m2 Main Plant

Page 73 of 96
o
Report N . 2514054 R01
Issue 4

Figure 31 - Frequency Contour Plot for Heat Flux above 15kW/m2 Jetty Area

Page 74 of 96
o
Report N . 2514054 R01
Issue 4

Figure 32 – BLEVE Risk Plot

Page 75 of 96
Report No. 2514054 R01
Issue 4

The Individual Risk (IR) from fire for the most exposed person within the occupied buildings was
found to be negligible. This is based on the building being type B2.
Table 15 summarises the frequency of exceeding heat flux of 15kW/m2 at various buildings.

Table 15 – Frequency of 15kW/m2 at buildings

Building Freq of 15
Building Name 2
Number kW/m

1 Administration Building Negligible

2 Canteen No1 Negligible

3 Medical Center Negligible

4 Main Guard House Negligible

5 Central Control Room Negligible

7 Laboratory Negligible

8 Maintenance Workshop Negligible

9 Warehouse Negligible

12 Canteen No2 Negligible

13 Fire Station Negligible

14 Main Substation SS-M01 Negligible

15 Emergency Generator Negligible

18 SS- U04 Negligible

19 SS - O04 Negligible

20 SS- U01 Negligible

21 SS- P09 3.27E-03

22 SS- P07 2.92E-03

23 SS-P02 1.45E-04

24 SS-P06 2.67E-03

Page 76 of 96
Report No. 2514054 R01
Issue 4

Building Freq of 15
Building Name 2
Number kW/m

25 SS- P03 2.83E-03

26 SS- P04 2.65E-02

27 SS- P01 1.01E-02

28 SS- P08 5.73E-03

30 SS-P05 1.52E-02

31 SS-U03 1.92E-06

32 SS-O03 5.42E-04

33 SS-U02 1.08E-03

34 SS-O01 Negligible

36 ISB-014 Negligible

37 ISB-013 1.72E-06

38 ISB-03 3.38E-03

39 ISB-011 9.62E-04

40 ISB-06 3.47E-03

41 ISB-05 1.99E-04

42 ISB-04 1.99E-04

43 ISB-02 8.23E-03

44 ISB-12 3.62E-06

45 ISB-01 1.01E-02

46 ISB-10 1.10E-03

48 ISB-08 2.98E-03

49 ISB-07 8.27E-03

Page 77 of 96
Report No. 2514054 R01
Issue 4

Building Freq of 15
Building Name 2
Number kW/m

50 ISB-18 3.26E-05

51 ISB-17 1.31E-05

52 ISB-15 Negligible

53 ISB-16 Negligible

54 ISB-19 1.45E-06

Local Guardhouse No2 (Jetty


56 Negligible
Area)

60 Jetty Area Admin/Control Building Negligible

Page 78 of 96
Report No. 2514054 R01
Issue 4

7 RISK ASSESSMENT

7.1 On Site Risk


This section compares the risks calculated in Section 6 with the acceptance criteria.
Table 16 summarises the occupancy risk for each building on the site and compares it against the
acceptance criteria defined in Section 6.4. It is highlighted that Table 16 includes the risk
contributions for explosion and fire scenarios in order to provide the total risk to particular building
occupants. It is noted that toxic risks for the building occupants at the site are not included in
accordance with the scope of this work.
All the occupied buildings are considered to be exposed to negligible risk from fire and explosion
events. Detailed recommendations for mitigations for each building considered within the assessment
are provided in Section 8 of this report.

Table 16 - Summary Occupancy Risk Values

Building
Building
Building Name classification Tolerability
Number
(B1-B7)

1 Administration Building B4 Acceptable

2 Canteen No1 B4 Acceptable

3 Medical Center B4 Acceptable

4 Main Guard House B4 Acceptable

5 Central Control Room B5 Acceptable

7 Laboratory B4 Acceptable

8 Maintenance Workshop B2 Acceptable

9 Warehouse B2 Acceptable

10 Central Chemical Store B2 Acceptable

11 Central Catalyst Store B2 Acceptable

12 Canteen No2 B4 Acceptable

13 Fire Station B4 Acceptable

55 Local Guardhouse No1 B4 Acceptable

Page 79 of 96
Report No. 2514054 R01
Issue 4

Building
Building
Building Name classification Tolerability
Number
(B1-B7)

56 Jetty Area Guard House B4 Acceptable

Jetty Area Admin/Control


B5
60 Building Acceptable

Page 80 of 96
o
Report N . 2514054 R01
Issue 4

Table 17 – Overall Risk to Functionally Significant Buildings

Frequency of flux Overall


Building Frequency For Cloud Fire
Building Name Type greater than 15 Frequency of Overall Risk
Number Damage > 2B Frequency
kW/m2 Damage

26 SS- P04 B4 Negligible 2.06E-03 2.65E-02 2.86E-02 Mitigate

30 SS-P05 B4 Negligible 2.72E-03 1.52E-02 1.79E-02 Mitigate

47 ISB-09 B5 2.90E-06 8.84E-03 8.84E-03 1.77E-02 Mitigate

45 ISB-01 B5 1.00E-06 5.38E-03 1.01E-02 1.55E-02 Mitigate

27 SS- P01 B4 Negligible 5.38E-03 1.01E-02 1.55E-02 Mitigate

49 ISB-07 B5 Negligible 2.57E-03 8.27E-03 1.08E-02 Mitigate

43 ISB-02 B5 Negligible 2.06E-03 8.23E-03 1.03E-02 Mitigate

28 SS- P08 B4 2.00E-05 1.12E-04 5.73E-03 5.86E-03 Mitigate

40 ISB-06 B5 Negligible 2.36E-03 3.47E-03 5.83E-03 Mitigate

21 SS- P09 B4 5.00E-06 1.22E-03 3.27E-03 4.50E-03 Mitigate

24 SS-P06 B4 Negligible 1.54E-03 2.67E-03 4.21E-03 Mitigate

48 ISB-08 B5 Negligible 1.03E-03 2.98E-03 4.01E-03 Mitigate

Page 81 of 96
o
Report N . 2514054 R01
Issue 4

Frequency of flux Overall


Building Frequency For Cloud Fire
Building Name Type greater than 15 Frequency of Overall Risk
Number Damage > 2B Frequency 2
kW/m Damage

38 ISB-03 B5 Negligible 5.15E-04 3.38E-03 3.90E-03 Mitigate

22 SS- P07 B4 2.50E-06 5.15E-04 2.92E-03 3.44E-03 Mitigate

25 SS- P03 B4 Negligible 8.40E-05 2.83E-03 2.91E-03 Mitigate

39 ISB-011 B5 Negligible 1.76E-03 9.62E-04 2.72E-03 Mitigate

33 SS-U02 B4 Negligible 8.22E-04 1.08E-03 1.90E-03 Mitigate

46 ISB-10 B5 1.80E-05 1.03E-04 1.10E-03 1.22E-03 Mitigate

32 SS-O03 B4 Negligible 2.84E-07 5.42E-04 5.42E-04 ALARP

41 ISB-05 B5 Negligible 1.52E-04 1.99E-04 3.51E-04 ALARP

42 ISB-04 B5 Negligible 1.52E-04 1.99E-04 3.51E-04 ALARP

23 SS-P02 B4 2.00E-05 8.66E-05 1.45E-04 2.52E-04 ALARP

44 ISB-12 B5 Negligible 1.31E-04 3.62E-06 1.35E-04 ALARP

50 ISB-18 B5 Negligible 2.68E-05 3.26E-05 5.94E-05 ALARP

51 ISB-17 B5 Negligible 2.31E-05 1.31E-05 3.62E-05 ALARP

Page 82 of 96
o
Report N . 2514054 R01
Issue 4

Frequency of flux Overall


Building Frequency For Cloud Fire
Building Name Type greater than 15 Frequency of Overall Risk
Number Damage > 2B Frequency 2
kW/m Damage

54 ISB-19 B5 Negligible 1.46E-05 1.45E-06 1.61E-05 ALARP

20 SS- U01 B4 1.30E-05 1.27E-06 3.60E-07 1.46E-05 ALARP

37 ISB-013 B5 Negligible 5.04E-06 1.72E-06 6.76E-06 Acceptable

31 SS-U03 B4 Negligible 3.49E-06 1.92E-06 5.41E-06 Acceptable

19 SS-O04 B4 2.50E-06 Negligible Negligible 2.50E-06 Acceptable

14 Main Substation SS-M01 B5 Negligible 1.27E-06 Negligible 1.27E-06 Acceptable

15 Emergency Generator B5 Negligible 1.27E-06 Negligible 1.27E-06 Acceptable

36 ISB-014 B5 1.00E-06 Negligible Negligible 1.00E-06 Acceptable

53 ISB-16 B5 Negligible 1.54E-08 1.87E-07 2.02E-07 Acceptable

1 Administration Building B4 Negligible Negligible Negligible Negligible Acceptable

2 Canteen No1 B4 Negligible Negligible Negligible Negligible Acceptable

3 Medical Center B4 Negligible Negligible Negligible Negligible Acceptable

4 Main Guard House B4 Negligible Negligible Negligible Negligible Acceptable

Page 83 of 96
o
Report N . 2514054 R01
Issue 4

Frequency of flux Overall


Building Frequency For Cloud Fire
Building Name Type greater than 15 Frequency of Overall Risk
Number Damage > 2B Frequency 2
kW/m Damage

5 Central Control Room B5 Negligible Negligible Negligible Negligible Acceptable

12 Canteen No2 B4 Negligible Negligible Negligible Negligible Acceptable

13 Fire Station B4 Negligible Negligible Negligible Negligible Acceptable

18 SS- U04 B4 Negligible Negligible Negligible Negligible Acceptable

34 SS-O01 B4 Negligible Negligible Negligible Negligible Acceptable

52 ISB-15 B5 Negligible Negligible Negligible Negligible Acceptable

56 Jetty Area Guard House B4 Negligible Negligible Negligible Negligible Acceptable

60 Jetty Area Admin/Control Building B5 Negligible Negligible Negligible Negligible Acceptable

Page 84 of 96
Report No. 2514054 R01
Issue 4

7.2 Off-site Risk

7.2.1 Villages to the East of the site

7.2.1.1 Societal Risk

The societal risks are presented in the form of an F-N Curve in Figure 33. The villages are
considered to have approximately 320 dwellings with 5 people each on average. The construction of
the dwellings is assumed to be basic, affording little protection from fire or toxic gas ingress. The F-
N curve shows that the societal risks to the villages from the NSRP are unacceptable.

Figure 33 – F-N Curve (Villagers only)


Note:
The risk levels in the F-N curve are represented as follow (See Section 6.4.2)
• Red Region: Unacceptable;
• Yellow & Green Region: Acceptable according to UK HSE document R2P2 definition [12];
• Green Region: A conservative acceptability criteria used by some companies.
R2P2 states that death of more than 50 people in any incident should be less than 1 in 5000 years.
The F-N curve is constructed by using a slope of -1 from FN pair of 2x10-4, 50 and Nmax of 1000
[12]. The line is represented by the interface between the RED and YELLOW regions of Figure 33,
implying that values within the RED region are unacceptable.

7.2.1.2 Individual Risk

The Location Specific Individual Risk (LSIR) is shown in Figure 34 and Figure 35. The maximum
location specific individual risk (LSIR) at the villages is 5.42x10-3/year. LSIR represents an
individual risk (IR) to an individual who remains at the location at all the time. Considering that the
individual could move to different location from high risk to low risk, an occupancy ratio of 0.5 is
appropriate thus giving an individual risk (IR) of 2.71E-3 per year. This level of risk is considered
unacceptable (>1E-4 is unacceptable for general public). Even if the occupancy ratio is taken as 0.1,
i.e. an individual is only in the high risk area for less than 2.5 hours per day, the risks are still
unacceptable.

Page 85 of 96
Report No. 2514054 R01
Issue 4

It may therefore be concluded that the risk to the villages is unacceptable both from individual risk
and societal risk perspectives.

7.2.2 Road to the South of the site

7.2.2.1 Individual Risk

The Location Specific Individual Risk (LSIR) for the road is shown in Figure 34. The results show
that the maximum LSIR at the road area is 1.88x10-3/year. The occupancy ratio considered for the
road is 0.006 based on the traffic moving at 60 km/hour and any one individual travelling twice a
day, six days per week across the site on this road. Therefore, the maximum individual risk at the
road is 1.13x10-5/year which corresponds to the ALARP region based on the risk tolerability criteria
in Section 6.4. This implies that mitigation measures should be considered to reduce risks as long as
the cost of such measures is not disproportionate to the benefit.

Page 86 of 96
o
Report N . 2514054 R01
Issue 4

Figure 34 – Total Fire and Explosion Risk Contour Level Main Plant

Page 87 of 96
o
Report N . 2514054 R01
Issue 4

Figure 35 – Total Fire and Explosion Risk Contour Level Jetty Area

Page 88 of 96
Report No. 2514054 R01
Issue 4

8 CONCLUSIONS & RECOMMENDATIONS

8.1 Buildings at the site

The results from this coarse QRA indicate that there are a number of buildings at the site that require
risk reduction measures. This includes 18 buildings where risk mitigation must be undertaken and
10 buildings where risk mitigation should be considered, and implemented as necessary, in order to
demonstrate that the building’s risk status is ALARP. Total fire and explosion risk contour level

The focus of the Risk mitigation is to reduce the likelihood and/or consequences of explosions/Fire
on the site.
Based on this analysis, the following Table 18 provides a summary of recommendations for
refinement of the risk predicted for an area/building or for mitigation of its risk. The
recommendations are presented as General, Explosion and Fire.
Even though the explosion risk at NSRP is low, it is recommended that best industrial practice
should be used and building classification not be downgraded based on the results of this risk
assessment.
Furthermore, a detailed QRA must be undertaken once detailed plant design is in place to confirm or
update the explosion risks in particular which are sensitive to plant congestion but also other risks
which are based on the early plant information. At the detailed QRA stage, it may be possible to take
account of various mitigations in place such as the water deluge, shutdown and blowdown and risk
based inspection and maintenance and regular fugitive emission testing.

Table 18 –Recommendations

Ref. No. Description of Recommendations Options

General Recommendations

Reduce Event Likelihood

Ensure that the design specifications for all plant include performance standards such that plant
L1
failure, and thus hydrocarbon release scenarios, will be minimized through design.

Reduce the hazard magnitude through the installation of gas (toxic and flammable) detectors
with emergency shutdown (ESD) systems within the critical hazard locations. Emergency
L2 shutdown valves to be located outside fire impact zone. If the valve is located inside a
fire/explosion zone then fire proofing is necessary to provide protection for a specified period of
time in line with API 2001.

L3 Minimize the presence of ignition sources around the process units

Where possible, consider leak point minimization for all equipment (e.g. welded, rather than
L4
flanged pipe connections, fail safe valves, spring loaded manual valves, flange covers)

Implement a risk-based inspection (RBI) and maintenance process such that the plant items
L5
that pose the greatest risk to the plant receive the greatest levels of inspection and maintenance

Since there is a risk of an event moving onto the public highway, provisions will need to be in
L6
place to prevent traffic movement on the highway in the event of a site incident.

Page 89 of 96
Report No. 2514054 R01
Issue 4

Ref. No. Description of Recommendations Options

Toxic and vapour cloud events, generally leave the site periphery it is suggested that a plan will
need to be in place to alert the populations to either end of the plant limit in the event of a site
incident. Such measures will form part of the Site Emergency Response Plan which is to be
L7 detailed during the Detailed design.

Emergency procedures should be put in place and followed if a leak is detected. Good
procedures and training for emergency response are essential.

Reduce Vulnerability

Reduce the vulnerability of the building occupants through the avoidance of windows within
V1
buildings located within the process areas.

Reduce the vulnerability of the building occupants to toxic ingress through the implementation of
V2 toxic gas detection and dampers on the HVAC inlet ducts for putting into recycle as well as
manual shutdown.

Explosion Recommendations

Reduce the vulnerability through relocation of road, provide a barrier between road and plant
V3 (not always effective for blast but prevents missiles) and reduce congestion near the site
boundary.

For buildings with cloud fire frequency >1E-4 p.a., positive pressurisation and double doors
V4 should be provided in the building. LEL detection should also be incorporated into the ventilation
inlets & automatically shutdown the ventilation system providing alarms on LEL detection

For buildings with cloud fire frequency between 1E-4 & 1E-5 p.a. self-closing doors with gas
tight seals should be provided in addition to LEL detection in the ventilation inlets providing
V5
automatic shutdown of the ventilation system and alarms on LEL detection (See Table 28 and
Table 29).

For Buildings with cloud fire frequency between 1E-5 & 1E-6 p.a., self-closing doors with gas
V6
tight seals and LEL monitors alarms and manual HVAC shutdown should be provided.

V7 Buildings should be designed to withstand the 10-4/yr explosion overpressure as a minimum

Fire Recommendations

Reduce the vulnerability of the buildings to flammable gas ingress through the implementation
of flammable gas detection and dampers on the HVAC inlet ducts, self-closing doors with gas
V8
tight seals and LEL monitors, alarms and manual HVAC shutdown should be provided. As given
for explosion

Reduce risk to building occupants from fire by ensuring building has safe refuge areas in case
V9
of fire and /or the building has adequate fire proofing.

Reduce BLEVE risk by insulating vessels, improve depressurisation and vessel deluge.
V10
Depressurized the leaking section using blowdown system.

Toxic Recommendations

Page 90 of 96
Report No. 2514054 R01
Issue 4

Ref. No. Description of Recommendations Options

The ERPG contours are based on gas dispersion modeling for free field flat terrain. Simple
consequence assessment models used in QRA are not appropriate for dealing with complex
terrain especially for near field effects. It is recommended that a Computational Fluid Dynamics
T1
based H2S dispersion study should be undertaken in the detailed phase of the design to
ascertain the toxic risks and if there are any specific areas where high H2S concentrations
might develop due to the presence of the mountain to the west of the site.
Based on the mitigation options detailed in Table 18, recommendations in respect of explosion risk
for each functional but considered unoccupied building were assessed are provided in Table 19.

Table 19 – Recommendations Functional Significant Buildings

Positive
Manual Automatic Self Closing
Cloud LEL Pressurisation
Building HVAC HVAC Doors with gas
Fire Risk Detection in building and
Shutdown Shutdown tight seals
double doors

ISB-09 8.84E-03 Yes No Yes Yes No

SS- P01 5.38E-03 Yes No Yes Yes No

ISB-01 5.38E-03 Yes No Yes Yes No

SS-P05 2.72E-03 Yes No Yes Yes No

ISB-07 2.57E-03 Yes No Yes Yes No

ISB-06 2.36E-03 Yes No Yes Yes No

SS- P04 2.06E-03 Yes No Yes Yes No

ISB-02 2.06E-03 Yes No Yes Yes No

ISB-011 1.76E-03 Yes No Yes Yes No

SS-P06 1.54E-03 Yes No Yes Yes No

SS- P09 1.22E-03 Yes No Yes Yes No

ISB-08 1.03E-03 Yes No Yes Yes No

SS-U02 8.22E-04 Yes No Yes Yes No

SS- P07 5.15E-04 Yes No Yes Yes No

ISB-03 5.15E-04 Yes No Yes Yes No

Page 91 of 96
Report No. 2514054 R01
Issue 4

Positive
Manual Automatic Self Closing
Cloud LEL Pressurisation
Building HVAC HVAC Doors with gas
Fire Risk Detection in building and
Shutdown Shutdown tight seals
double doors

ISB-05 1.52E-04 Yes No Yes Yes No

ISB-04 1.52E-04 Yes No Yes Yes No

ISB-12 1.31E-04 Yes No Yes Yes No

SS- P08 1.12E-04 Yes No Yes Yes No

ISB-10 1.03E-04 Yes No Yes Yes No

SS-P02 8.66E-05 Yes No Yes No Yes

SS- P03 8.40E-05 Yes No Yes No Yes

ISB-18 2.68E-05 Yes No Yes No Yes

ISB-17 2.31E-05 Yes No Yes No Yes

ISB-19 1.46E-05 Yes No Yes No Yes

ISB-013 5.04E-06 Yes No Yes No Yes

SS-U03 3.49E-06 Yes No Yes No Yes

Main Substation
SS-M01 1.27E-06 Yes No Yes No Yes

Emergency
Generator 1.27E-06 Yes No Yes No Yes

SS- U01 1.27E-06 Yes No Yes No Yes

SS-O03 2.84E-07 No Yes No No Yes

ISB-16 1.54E-08 No Yes No No Yes

Administration
Building No No No No No
Negligible

Canteen No1 No No No No No
Negligible

Page 92 of 96
Report No. 2514054 R01
Issue 4

Positive
Manual Automatic Self Closing
Cloud LEL Pressurisation
Building HVAC HVAC Doors with gas
Fire Risk Detection in building and
Shutdown Shutdown tight seals
double doors

Medical Center No No No No No
Negligible

Main Guard
House No No No No No
Negligible

Central Control
Room No No No No No
Negligible

Canteen No2 No No No No No
Negligible

Fire Station No No No No No
Negligible

SS- U04 No No No No No
Negligible

SS-O04 No No No No No
Negligible

SS-O01 No No No No No
Negligible

ISB-014 No No No No No
Negligible

ISB-15 No No No No No
Negligible

Jetty Area
Guard House No No No No No
Negligible

Jetty Area
Admin/Control
Building No No No No No
Negligible

8.2 Off-site Population

8.2.1 Villages to the East of the site


The risk to the villages, both in terms of individual and societal are unacceptable. Assuming that the
site location has been decided, the risk from the NSRP site to the villages are such that reasonable
measures of reducing risks to an acceptable level could be impractical. The Societal risks can be
reduced by reducing the population and reducing the frequency and magnitude of hazards from the
site. However, the risk assessment here does not take account of the fact that the villages are in
wooded area which is susceptible to fire escalation. In light of this, re-location of the villages to a
safer place should be given serious consideration.

Page 93 of 96
Report No. 2514054 R01
Issue 4

8.2.2 Road to the South of the plant


Although the risks to the road users for ‘Bidder 1’ option are lower than the FEED study case, the
road is nonetheless too close to the Plant boundary. It is prudent to keep the option of a barrier
between the Plant and the road as well as traffic control measures. The recommendations to reduce
risks to the road users are as follows in Table 20.

Table 20 – Recommendations vulnerability

Ref. No. Description of Recommendations Options

Reduce Vulnerability to Offsite Road to the South

Reduce the vulnerability by adding a barrier along the high risk part of the plant boundary
VR1 between the plant and the road to the south to prevent direct fire impingement and to reduce
heat flux.

VR2 Reduce risk to road users by early warning on leak and closure of access.

It is proposed that a 500m long, 6m high concrete wall designed to withstand 30 mbar side-on
overpressure as shown on Figure 36, together with the traffic control measures should provide
practical mitigation solution.

Control barriers/stop Concrete Wall ≈ 500m (6m high to Control barriers/stop


lights withstand 30 mbar overpressure) lights

Figure 36 – Proposed concrete wall and traffic warning/control

Page 94 of 96
o
Report N . 2514054 R01
Issue 4

9 UNCERTAINTY IN QRA

There will always be uncertainty as to whether certain events will occur or not, what the immediate
effects will be, and what the consequences for people, environment, or assets may be. This
uncertainty reflects the insufficient information and knowledge available for the analysis, in relation
to technical solutions, operations, and maintenance philosophies, logistic premises etc [13].

Uncertainties in the QRA will derive from the following examples:

• Since the design is at FEED stage, the level of detail in the system drawings necessitates the
use of assumptions in terms of the equipment types and volumes.

• The distribution of flanges, valves, connections, instruments and pipe sizes are assumed
based on work undertaken by Shell (default values in Shepherd) and are taken to be an
average reflection of the distribution that is to be expected. However, the actual distributions
may vary in the final design.

• The consequence modelling of the release scenarios has made some simplifications in terms
of modelling the release of mixed fluids (e.g predominantly liquid material containing gases
that may flash). The analysis of this phenomenon is very complex and as such, the
consequence results for some scenarios are a best representation of the actual scenario.

• The flow rates are taken conservatively as the instantaneous release rates. These rates could
be far in excess of the actual mass flow rates of materials through the process segments. This
is considered to be accepted methods of undertaking such studies since the results are on the
side of conservatism. However, if required, such conservatisms could be explored in detail if
considered necessary.

• The explosion overpressures are derived from assumed congestion levels based on a simple
2D plant layout drawing and at the time of this assessment only were available for the RFCC,
ARC and HMU units. It is usual to visit the actual site to undertake such assessments of site
congestion. Clearly, this is not possible with a proposed plant; therefore, as the plant design
progresses, the explosion parameters should be re-visited.

• A moderate damage to site buildings is assumed if thermal flux exceeds 15kW/m2. For
concrete or masonry infill buildings this is a conservative assumption. However this gives an
estimate as to which buildings should be considered to be at risk from fire and appropriate
insulation measures.

Page 95 of 96
o
Report N . 2514054 R01
Issue 4

10 REFERENCES

1. Management of hazards associated with location of process plant buildings, API


recommended practice 752, Second Edition, Nov. 2003.

2. HAZID-ENVID Review Report, 3550-8150-RP-0002 Rev.01, 01.05.2009, FWEL

3. FRED v 5.1 Technical manual, 2009.

4. SHEPHERD v2.1 Technical manual, 2009.

5. Refinery Design basis overall 3550-8110-PD-0005 Rev. 01, FWEL.

6. NSRP Refinery and Petrochemical Complex Plot plant, H-000-1225-501_5 REV 5,


FWEL.

7. NRSP Marine Facility Plot plant, 3550-8230-01-0002, FWEL.

8. Hydrocarbon Leak and Ignition Database, EP Forum Risk Assessment Data Directory, EP
Forum Report No. 11.8/250, E&P Forum, 1996.

9. Cox, A. W., Lees, F.W. and Ang M. Lm, “Classification of Hazardous Locations”,
IChemE, Rugby, England, 1990.

10. American Industrial Hygiene Association ERPG Table, 2008.

11. Frank P Lees, “Loss Prevention in Process Industries”, 2nd Edition, BH, 1996.

12. HSE, Reducing risks, protecting people - R2P2, 2001.

13. Nicolet-Monnier M. Gheorghe V. Andrian , Topics in Safety, Risk, Reliability and Quality
“Quantitative Risk Assessment of Hazardous Material Transport Systems”,. Kluwer
Academic Publishers, 1996.

14. NSRP Refinery and Petrochemical Complex Project Coarse QRA, Issue 4 FINAL, Report
No.2204898 R01, ABSC, Sep 2009

Page 96 of 96

You might also like