Professional Documents
Culture Documents
Info About NSRP
Info About NSRP
Prepared for
Foster Wheeler Energy Ltd
by
ABS Consulting Ltd.
Page 2 of 96
o
Report N . 2514054 R01
Issue 4
Issue 1
First Draft issue for client comment.
DRAFT
Issue 1 Updated Jetty Area and incorporated client comments from DRAFT.
Page 3 of 96
o
Report N . 2514054 R01
Issue 4
EXECUTIVE SUMMARY
ABS Consulting Ltd (ABSC) preformed a quantitative risk assessment QRA for the proposed NSRP
refinery in Nghi Son, Vietnam for the FEED stage of the project for Foster Wheeler Energy Ltd
(FWEL). The results of the study [14], in addition to the site buildings risks, were used to check the
risks to the nearby villages and the adjacent road users. Based on those risks appropriate actions were
recommended.
Following on from previous work, the Client has now solicited definitive design proposals from
various bidders. This study has assessed the risks to the site buildings for the new proposed layout
from ‘Bidder 1’ by updating the previous study [14]. All the previous assumptions remain the same.
The three stage process for BRA is aimed at providing a structured risk assessment such that the
complexity of assessment is commensurate with the magnitude of the problem. Stage 1 is the
occupancy filtering step. At this stage, buildings which are not occupied or are not significant for the
safety of the operation are eliminated from the assessment. For stage II, worst credible consequences
are simulated and the buildings which are unaffected by the modelled hazards or for which simple
mitigations can be designed are eliminated. All the buildings which are occupied or functionally
significant AND are affected by the postulated hazards are then taken to Stage III risk assessment
process where not only the magnitude of the hazard but the frequency is taken into account to
calculate the risks to building occupants. Where risks are higher than the accepted criteria,
mitigations are considered to lower the risks to acceptable levels.
Of the on site buildings, 48 were assessed in the Stage 1 preliminary building screening as being “At
Risk”, due to their occupancy and functionality requirements.
The building risk assessment concluded that all occupied buildings at this site are shown to have
negligible Individual Risk (IR) due to explosion and fire.
Detailed recommendations for the mitigations for each building considered within the assessment in
Section 7.2 and are based on industry general practice. This risk assessment does not account to any
mitigation that may already be in place such as local deluge or passive fire protection on vessels. In
addition to the risk mitigations outlined, due attention should be paid to ensuring that a robust escape
and evacuation plan is in place within the overall emergency preparedness for the site.
The public risk was analysed on a societal risk perspective by the use of an F-N curve. Societal risk
is a measure of the collective risk to which a certain population is subjected as a whole. It is usually
depicted in form of a so-called FN curve, which shows the frequency (F), that a given number, N
people or more (hence N+) will be exposed to lethal consequences.
Based on the results of the study, it can be seen that there is the potential for thermal heat radiation to
impact the adjacent road. Fire risk (BLEVE) is predicted to affect the neighboring villages. By
inspecting the F-N curves presented previously, it can be seen that the risks to the villagers at the east
side are unacceptable.
Detailed recommendations for the mitigations for each building considered within the assessment in
Section 8 and are based on industry general practice. This risk assessment does not account to any
mitigation that may already be in place such as local deluge or passive fire protection on vessels. In
addition to the risk mitigations outlined, due attention should be paid to ensuring that a robust escape
and evacuation plan is in place within the overall emergency preparedness for the site.
Page 4 of 96
o
Report N . 2514054 R01
Issue 4
It is recommended that relocation of the villages should be considered as one of the mitigation
options. The risks to the adjacent road, south of the plant, should be mitigated by the use of a 500m
barrier, and if possible traffic control measures.
It should be noted that this QRA presents the hydrocarbon releases risk results only; occupational
risk, non-hydrocarbon events (e.g. dropped objects etc), external events (e.g. structural failure due to
extreme weather, fatigue etc), structural events (e.g. structural failures, etc), and Transportation
accidents are excluded from the scope of this study. It is assumed that the plant and buildings at the
site will be designed to withstand the appropriate seismic loading such that the hydrocarbon release
frequencies are unaffected. In cases where the plant design takes seismic risk into account, it is usual
practice to ignore the seismic considerations from the QRA.
Page 5 of 96
o
Report N . 2514054 R01
Issue 4
LIST OF ACRONYMS
ABSC ABS Consulting Ltd
ACPH Air Changes per Hour
ALARP As Low As Reasonably Practicable
ARU Amine Regeneration Unit
BLEVE Boiling Liquid Expanding Vapour Explosion
BRA Building Risk Assessment
CAM Congested area Assessment Methodology
CDU Crude Distillation Unit
CMU Concrete Masonry Units
DOM Design, Operation, Maintenance
ERPG Emergency Response Planning Guidelines
ESD Emergency Shutdown
FEED Front End Engineering and Design
FWEL Foster Wheeler Energy Limited
GOHDS Gas Oil Hydrodesulphuriser Unit
HAZID Hazard Identification
HCDS Hydrogen Compression and Distribution System
HMU Hydrogen Manufacturing Unit
HVAC Heating, Ventilation and Air Conditioning
IR Individual Risk (or Incident Radiation)
IRPA Individual Risk Per Annum
InAlk Indirect Alkylation Units
KEC Kuwait Export Crude
KHDS Kerosene Hydrodesulphuriser Unit
LC Lethal Concentration
LFL Lower Flammable Limit
LPG Liquefied Petroleum Gas
LSIR Location Specific Individual Risk
NAC Naphtha and Aromatics Complex
NSRP Nghi Son Refinery and Petrochemical
PHA Preliminary Hazard Analysis
P&ID Piping and Instrumentation Diagram
PFD Process Flow Diagram
Page 6 of 96
o
Report N . 2514054 R01
Issue 4
Page 7 of 96
o
Report N . 2514054 R01
Issue 4
CONTENTS
Page
Document Approval .............................................................................................................. 2
Revision Record ................................................................................................................... 3
Summary .............................................................................................................................. 4
List of Acronyms ................................................................................................................... 6
Contents ............................................................................................................................... 7
List of Tables ........................................................................................................................ 9
List of Figures ..................................................................................................................... 10
List of Appendices ............................................................................................................... 11
1 INTRODUCTION .........................................................................................................12
3 DESCRIPTION OF FACILITY.....................................................................................14
Page 8 of 96
o
Report N . 2514054 R01
Issue 4
10 REFERENCES............................................................................................................96
List of Tables
Table 4 – Toxic Gas (H2S) Dispersion modelling results for the 150mm hole size ..................................................... 40
Page 9 of 96
o
Report N . 2514054 R01
Issue 4
Table 14- Summary Explosion Damage for the 10-4/yr Hazard .................................................................................... 55
List of Figures
Figure 8 – Maximum Potential Incident Radiation Flux Contours Jetty Area ........................................................... 34
Page 10 of 96
o
Report N . 2514054 R01
Issue 4
Figure 22 - Explosion Risk Plot for Building Type B2 Main Plant .............................................................................. 64
Figure 23 - Explosion Risk Plot for Building Type B2 Jetty Area ................................................................................ 65
Figure 24 - Explosion Risk Plot for Building Type B4 Main Plant .............................................................................. 66
Figure 25 - Explosion Risk Plot for Building Type B4 Jetty Area ................................................................................ 67
Figure 26 - Explosion Risk Plot for Building Type B5 Main Plant .............................................................................. 68
Figure 27 - Explosion Risk Plot for Building Type B5 Jetty Area ................................................................................ 69
Figure 30 - Frequency Contour Plot for Heat Flux above 15kW/m2 Main Plant........................................................ 73
Figure 31 - Frequency Contour Plot for Heat Flux above 15kW/m2 Jetty Area ......................................................... 74
Figure 34 – Total Fire and Explosion Risk Contour Level Main Plant ....................................................................... 87
Figure 35 – Total Fire and Explosion Risk Contour Level Jetty Area ......................................................................... 88
Page 11 of 96
o
Report N . 2514054 R01
Issue 4
1 INTRODUCTION
ABS Consulting Ltd (ABSC) preformed a coarse quantitative risk assessment (QRA) for the
proposed NSRP refinery in Vietnam for the FEED stage of the project for Foster Wheeler Energy
Ltd (FWEL). The results of the study [14], in addition to the site buildings risks, were used to check
the risks to the nearby villages and the adjacent road users. Based on those risks appropriate actions
were recommended.
Following on from the earlier work, the Client has now solicited definitive design proposals from
various bidders. This study assesses the risks to the site buildings, for the new proposed layout from
‘Bidder 1’ by updating the previous study [14], by incorporating the new information in the risk
model.
For this assessment all the previous assumptions about the process conditions, release frequencies,
ignition probabilities, etc remains the same.
The results of the revised risk assessment study are detailed within this report. Although unchanged
from the previous study [14], for the sake of completeness the general methodology adopted for this
study is described in Section 2. Section 3 provides a general description of the facility. Section 4
presents the results of the Stage 1 assessment. Section 5 deals with the Stage 2 consequence
modelling with Stage 3 risk analysis being covered in Section 6. Section 7 presents the Risk
Assessment, where the risks are compared to the risk acceptance criteria. Section 8 presents the
conclusions and suggests suitable risk mitigation measures for accomplishing them or showing that
the risks are As Low as Reasonably Practicable (ALARP). Finally, discussion on the QRA
uncertainties is presented in Section 9.
Page 12 of 96
o
Report N . 2514054 R01
Issue 4
2 GENERAL METHODOLOGY
The methodology adopted for the BRA follows the recommendations of in the American Institute of
Petroleum’s Recommended Practice API RP 752 [1]. The assessment follows a three step process.
The philosophy of the stepped approach is to perform as simple an analysis as is consistent with the
hazards. For example if the building is not occupied or is not significant from the plant operation
aspect then no further assessment is needed. If the building is occupied or is functionally significant
then the next consideration is to check if the building is subject to a credible hazard and if simple
mitigation is feasible to mitigate the effects. No further assessment is needed if the occupied or
functionally significant building is not subject to a credible major hazard or the effects of the hazard
can be mitigated in a cost effective manner. Where the building is occupied or functionally
significant and is subject to a credible hazard which cannot be easily designed out or mitigated, a risk
assessment is undertaken to check if the risks to the building occupants are acceptable or the
frequency of significant damage to unoccupied but functionally significant building is reasonably
low. Based on the risk assessment, cost effective and proportional mitigation options can be devised.
The QRA has been performed based initially on the three steps of the BRA methodology that are
summarized below:
1. Stage 1: A screening assessment based on building occupancy and its functional significance.
Only buildings considered to be occupied or functionally significant are taken to the Stage II
assessment. This is generally undertaken by the plant and confirmed by the consultant.
2. Stage 2: This phase involves analysis of worst credible consequences of the potential hazards
to assess building vulnerability for explosions, fires, flammable and toxic gases. Only
buildings considered to be vulnerable to the assessed hazards need to be taken to the 3rd stage
of assessment.
3. Stage 3: The 3rd stage of assessment involves calculation of risk to the building occupants and
where risks are high considers risk reduction measures.
4. In addition to the standard building risk assessment, the risks to the offsite population were
also assessed using the societal risk criteria for which the F-N curves were generated.
The tool used for the stage 2 consequence modelling was Shell FRED V 5.1 which is a suite of Fire,
Release, Explosion and Dispersion models used to predict the consequences of the accidental or
design release of product from process, storage, transport or distribution operations [3].
For the stage III risk assessment Shell SHEPHERD V2.1 was used. The Shell SHEPHERD Risk
Tool forms a family of graphical risk integrators. The tool has been developed to carry out fit-for-
purpose Quantified Risk Assessment (QRA) for a broad range of onshore industrial sites such as
Refineries, Gas plants, Chemicals plants, LPG distribution sites, pipeline systems etc. SHEPHERD
is used to systematically build up risk contributions starting from a release and working through
ignition sources to the calculation of the effects of cloud fires, jet fires, toxic gas and explosions.
Escalation to other parts of the plant via vessel failure through explosion over-pressure and/or flame
engulfment is handled automatically. The input required includes the mass flow rate and dispersion
distances to lower flammable limit in process blocks or point sources [4].
Page 13 of 96
o
Report N . 2514054 R01
Issue 4
3 DESCRIPTION OF FACILITY
• LPG
• Gasoline – 92/ 95 RON
• Kerosene / Jet A-1
• Diesel – Premium and Regular
• Paraxylene / Benzene
• Polypropylene
• Sulphur
The refinery is situated in Nghi Son, Tinh Gia District, Thanh Hoa Province, Vietnam (approx. 200
km south of Hanoi) - See Figure 1.
The NSRP Project includes all process units and associated utility, offsite and infrastructure facilities
to support the refinery operation.
Page 14 of 96
o
Report N . 2514054 R01
Issue 4
• Complete utility facilities designed to meet the refinery’s demands for cooling water, fuels,
power, steam, water, instrument and plant air, inert gas, etc.
• Offsite facilities including tankage for feedstocks plus intermediate and final products as well
as systems for import and export of feed and products.
• Other offsite facilities including flare, effluent treatment, firewater, interconnecting piping
and pipelines, etc.
• Marine facilities include an SPM/ Crude import line and product loading jetties
Page 15 of 96
o
Report N . 2514054 R01
Issue 4
• Offsite Systems
• Crude Oil Import, Storage and Pumping System
• Inter Unit Storage and Pumping System
• Product Component Storage and Pumping System
• Product Storage and Pumping System
• Slop Storage and Pumping System
• Product Truck Loading System
• Sulphur Forming and Storage Unit
Utility Systems
3.1.2 Buildings
In all 59 buildings have been identified on the plant layout (See Figure 2 and Figure 3). On the
previous study [14] ABSC numbered these buildings consecutively from number 1 to number 66. To
allow direct comparison this system has been retained. These buildings are tabulated in Table 1.
Page 16 of 96
o
Report N . 2514054 R01
Issue 4
Page 17 of 96
o
Report N . 2514054 R01
Issue 4
Page 18 of 96
o
Report N . 2514054 R01
Issue 4
4 STAGE 1 ASSESSMENT
The scope of the Stage one assessment is to carry out a building screening exercise in order to
eliminate buildings of no safety concern (unoccupied and not functionally significant) from the risk
assessment process.
The stage I screening has been completed by FWEL using the API 752 [1] criteria described below;
• People are expected to remain or take refuge in the building during an emergency. Possible
reasons for people to remain in a building include a lack of suitable evacuation options or the
need for occupants to perform emergency shutdown procedures.
• The building is required for emergency response, such as fire stations or clinics.
• The building is necessary for continued operation of plant units that may be able to continue
to operate or may be unaffected by an incident in another area. This includes control
buildings, process interface buildings (PIBs), or substations that control or provide power to
multiple process units.
• The economic impact on operations of loss of buildings is significant.
Page 19 of 96
o
Report N . 2514054 R01
Issue 4
Page 20 of 96
o
Report N . 2514054 R01
Issue 4
Page 21 of 96
o
Report N . 2514054 R01
Issue 4
Page 22 of 96
o
Report N . 2514054 R01
Issue 4
Page 23 of 96
o
Report N . 2514054 R01
Issue 4
Page 24 of 96
o
Report N . 2514054 R01
Issue 4
Page 25 of 96
o
Report N . 2514054 R01
Issue 4
• CDU
• LPG Recovery and Treater Unit
• KHDS
• GOHDS
• RHDS
• RFCC
• PPU
• SHU and Ind Alk
• HMU
• HCDS
• NAC
• Berth Area
• Tanks pumping system
• Fuel gas system
Page 26 of 96
o
Report N . 2514054 R01
Issue 4
7 Laboratory 0.4 24
9 Warehouse 0.6 29
19 SS-O04 3.2 94
Page 27 of 96
o
Report N . 2514054 R01
Issue 4
32 SS-O03 0.6 31
33 SS-U02 2.0 47
34 SS-O01 1.2 34
36 ISB-014 2.6 87
43 ISB-02 2.0 80
50 ISB-18 1.0 44
Page 28 of 96
o
Report N . 2514054 R01
Issue 4
52 ISB-15 7.0 44
53 ISB-16 0.6 31
54 ISB-19 1.5 36
Page 29 of 96
o
Report N . 2514054 R01
Issue 4
Page 30 of 96
o
Report N . 2514054 R01
Issue 4
Page 31 of 96
o
Report N . 2514054 R01
Issue 4
• CDU
• LPG Recovery and Treater Unit
• KHDS
• GOHDS
• RHDS
• RFCC
• PPU
• SHU and Ind Alk
• HMU
• HCDS
• NAC
• Berth Area
• Storage Tanks and pumping system
• Spheres
• Propane loading
• Fuel Gas system
Figure 7 and Figure 8 show the maximum potential incident radiation flux contours.
Page 32 of 96
o
Report N . 2514054 R01
Issue 4
Page 33 of 96
o
Report N . 2514054 R01
Issue 4
Page 34 of 96
Report No. 2514054 R01
Issue 4
True BLEVEs are associated with liquid gases such as propane which are stored as liquid by keeping
them under pressure at temperatures far in excess of the boiling points of the material. For example
the boiling point of propane is -42oC. Being kept at an ambient temperature of 30oC represents a very
large temperature difference for this liquid. Therefore, an increase in the temperature for the liquid
from a relatively small fire would tend to rapidly increase the pressure as the material tries to return
to a gaseous state. The material could go into a superheated state, and, given the sudden loss of
containment when the shell of the containing vessel fails due to the applied heat load and loss of
strength, the superheated liquid would instantly vaporize causing a rapid expansion in volume (of the
order of 100s of times the liquid volume) giving rise to the fireball that is inherent in the BLEVE
event.
The maximum fireball diameter contours are show in Figure 9.
Page 35 of 96
Report No. 2514054 R01
Issue 4
Page 36 of 96
o
Report N . 2514054 R01
Issue 4
A summary of the Maximum Incident Radiation flux from the modeled fire scenarios for each
building is given in Table 3.
Max. Incident
Building
Building Name Radiation
Number 2
(kW/m )
7 Laboratory Negligible
8 Maintenance Workshop 4
9 Warehouse 4
15 Emergency Generator 11
18 SS- U04 7
19 SS-O04 Negligible
20 SS- U01 23
23 SS-P02 >50
24 SS-P06 >50
Page 37 of 96
o
Report N . 2514054 R01
Issue 4
Max. Incident
Building
Building Name Radiation
Number 2
(kW/m )
30 SS-P05 >50
31 SS-U03 23
32 SS-O03 >50
33 SS-U02 >50
34 SS-O01 5
36 ISB-014 6
37 ISB-013 >50
38 ISB-03 >50
39 ISB-011 >50
40 ISB-06 >50
41 ISB-05 >50
42 ISB-04 >50
43 ISB-02 >50
44 ISB-12 >50
45 ISB-01 >50
46 ISB-10 >50
48 ISB-08 >50
Page 38 of 96
o
Report N . 2514054 R01
Issue 4
Max. Incident
Building
Building Name Radiation
Number 2
(kW/m )
49 ISB-07 >50
50 ISB-18 >50
51 ISB-17 >50
52 ISB-15 6
53 ISB-16 20
54 ISB-19 >50
• CDU
• SWS
• ARU
• SRU
• RFCC
• GOHDS
• KHDS
• RHDS
Page 39 of 96
o
Report N . 2514054 R01
Issue 4
Table 4 – Toxic Gas (H2S) Dispersion modelling results for the 150mm hole size
Note: The dispersion modeling was performed for two Pasquill-Gifford categories:
The Emergency Response Planning Guidelines (ERPGs) are intended to be a planning tool to help
anticipate human adverse health effects to the general public caused by toxic chemical exposure.
The ERPGs are three-tiered guidelines, with a common denominator: 1 hour exposure duration. The
levels are defined as follows in Figure 10:
Page 40 of 96
o
Report N . 2514054 R01
Issue 4
In this assessment the AIHA ERPG-2008 values were adopted to investigate the potential for off-site
adverse effects to humans due to toxic H2S exposure [10].
Figure 11 shows the ERPG-2 and 3 contours to the Amine Acid gas on the SRU unit considering a
150mm hole size release for D5 condition.
Page 41 of 96
o
Report N . 2514054 R01
Issue 4
Page 42 of 96
o
Report N . 2514054 R01
Issue 4
Page 43 of 96
o
Report N . 2514054 R01
Issue 4
Page 44 of 96
o
Report N . 2514054 R01
Issue 4
Page 45 of 96
o
Report N . 2514054 R01
Issue 4
Leak Frequency/
Holes year
Leak Type
Size
Process LPG
Process Blocks
-4
10mm Flange Leak 1.5x10 -
Page 46 of 96
o
Report N . 2514054 R01
Issue 4
Shell
Building Description
Type
Page 47 of 96
o
Report N . 2514054 R01
Issue 4
Shell
Building Description
Type
Each building type has its own unique resistance to blast damage. The blast damage resistance of
various building types is shown in Figure 14.
14.0
12.0
Peak Incident Overpressure (psi)
10.0
4.0
2.0
0.0
0 0.2 0.4 0.6 0.8 1 1.2
Probability of Serious Injury/Fatality
The Co-Operative has also suggested a relationship between vulnerability and building damage level.
These are given in Table 7.
Page 48 of 96
o
Report N . 2514054 R01
Issue 4
Damage level
Vulnerability
interface
0.01 1/2A
0.1 2A/2B
0.3 2B/3
0.6 3/4
1.0 4/5
The definition of blast damage levels from the Co-Operative study are given in Table 8.
Discrete
Brief
damage Full description
description
level
Page 49 of 96
o
Report N . 2514054 R01
Issue 4
Discrete
Brief
damage Full description
description
level
It is highlighted that the fatality risk from exposure to the effects of fires and toxics will be different
for people depending on the location of the person from the hazard and if they are inside or outside a
building, due to the protection afforded by the building, i.e. lower hazard frequency within the
building. For instance anyone outdoors caught within a flash fire (the LFL envelope) would be killed
(i.e. fatality probability of 1), but if adequately protected from the flames indoors may not be.
Page 50 of 96
o
Report N . 2514054 R01
Issue 4
Probability of Ignition
Leak Rate (kg/s)
Gas Liquid
1 – 50 0.07 0.03
A site background ignition probability of 1E-4/m2 of the facility was adopted for this assessment, in
order to address the potential for delayed ignition with the fire modelling. For the offsite urban
location a probability of ignition of 0.25E-4/m2 as suggested by the UKHSE has been adopted. The
additional ignition probability for the road to the south of the site is based on the traffic conditions
assuming that a vehicle represents a probability of ignition of 0.1.
For explosion modelling, the exceedance module has been used which requires a delayed ignition
probability to be specified. The delayed ignition probability used for explosion modelling is given in
Table 11.
Probability of Ignition
Leak Rate (kg/s)
Gas Liquid
1 – 50 0.008 0.0036
Page 51 of 96
o
Report N . 2514054 R01
Issue 4
Page 52 of 96
o
Report N . 2514054 R01
Issue 4
Table 13 provides details of design limits for various types of structure and plant.
Page 53 of 96
o
Report N . 2514054 R01
Issue 4
UNACCEPTABLE INTOLERABLE
REGION LEVEL
ALARP
REGION Benchmark representing
the standard to be met
by new plant
(Risk is undertaken only if a
benefit is desired)
Tolerable if cost of
reduction would exceed
the improvement gained
BROADLY
ACCEPTABLE Necessary to maintain assurance
REGION that risk remains at this level
NEGLIGIBLE RISK
Page 54 of 96
o
Report N . 2514054 R01
Issue 4
Page 55 of 96
o
Report N . 2514054 R01
Issue 4
Page 56 of 96
o
Report N . 2514054 R01
Issue 4
Page 57 of 96
o
Report N . 2514054 R01
Issue 4
Page 58 of 96
o
Report N . 2514054 R01
Issue 4
Page 59 of 96
o
Report N . 2514054 R01
Issue 4
Page 60 of 96
o
Report N . 2514054 R01
Issue 4
Page 61 of 96
o
Report N . 2514054 R01
Issue 4
Page 62 of 96
o
Report N . 2514054 R01
Issue 4
Page 63 of 96
o
Report N . 2514054 R01
Issue 4
Page 64 of 96
o
Report N . 2514054 R01
Issue 4
Page 65 of 96
o
Report N . 2514054 R01
Issue 4
Page 66 of 96
o
Report N . 2514054 R01
Issue 4
Page 67 of 96
o
Report N . 2514054 R01
Issue 4
Page 68 of 96
o
Report N . 2514054 R01
Issue 4
Page 69 of 96
o
Report N . 2514054 R01
Issue 4
Page 70 of 96
o
Report N . 2514054 R01
Issue 4
Page 71 of 96
o
Report N . 2514054 R01
Issue 4
Page 72 of 96
o
Report N . 2514054 R01
Issue 4
Figure 30 - Frequency Contour Plot for Heat Flux above 15kW/m2 Main Plant
Page 73 of 96
o
Report N . 2514054 R01
Issue 4
Figure 31 - Frequency Contour Plot for Heat Flux above 15kW/m2 Jetty Area
Page 74 of 96
o
Report N . 2514054 R01
Issue 4
Page 75 of 96
Report No. 2514054 R01
Issue 4
The Individual Risk (IR) from fire for the most exposed person within the occupied buildings was
found to be negligible. This is based on the building being type B2.
Table 15 summarises the frequency of exceeding heat flux of 15kW/m2 at various buildings.
Building Freq of 15
Building Name 2
Number kW/m
7 Laboratory Negligible
9 Warehouse Negligible
19 SS - O04 Negligible
23 SS-P02 1.45E-04
24 SS-P06 2.67E-03
Page 76 of 96
Report No. 2514054 R01
Issue 4
Building Freq of 15
Building Name 2
Number kW/m
30 SS-P05 1.52E-02
31 SS-U03 1.92E-06
32 SS-O03 5.42E-04
33 SS-U02 1.08E-03
34 SS-O01 Negligible
36 ISB-014 Negligible
37 ISB-013 1.72E-06
38 ISB-03 3.38E-03
39 ISB-011 9.62E-04
40 ISB-06 3.47E-03
41 ISB-05 1.99E-04
42 ISB-04 1.99E-04
43 ISB-02 8.23E-03
44 ISB-12 3.62E-06
45 ISB-01 1.01E-02
46 ISB-10 1.10E-03
48 ISB-08 2.98E-03
49 ISB-07 8.27E-03
Page 77 of 96
Report No. 2514054 R01
Issue 4
Building Freq of 15
Building Name 2
Number kW/m
50 ISB-18 3.26E-05
51 ISB-17 1.31E-05
52 ISB-15 Negligible
53 ISB-16 Negligible
54 ISB-19 1.45E-06
Page 78 of 96
Report No. 2514054 R01
Issue 4
7 RISK ASSESSMENT
Building
Building
Building Name classification Tolerability
Number
(B1-B7)
7 Laboratory B4 Acceptable
9 Warehouse B2 Acceptable
Page 79 of 96
Report No. 2514054 R01
Issue 4
Building
Building
Building Name classification Tolerability
Number
(B1-B7)
Page 80 of 96
o
Report N . 2514054 R01
Issue 4
Page 81 of 96
o
Report N . 2514054 R01
Issue 4
Page 82 of 96
o
Report N . 2514054 R01
Issue 4
Page 83 of 96
o
Report N . 2514054 R01
Issue 4
Page 84 of 96
Report No. 2514054 R01
Issue 4
The societal risks are presented in the form of an F-N Curve in Figure 33. The villages are
considered to have approximately 320 dwellings with 5 people each on average. The construction of
the dwellings is assumed to be basic, affording little protection from fire or toxic gas ingress. The F-
N curve shows that the societal risks to the villages from the NSRP are unacceptable.
The Location Specific Individual Risk (LSIR) is shown in Figure 34 and Figure 35. The maximum
location specific individual risk (LSIR) at the villages is 5.42x10-3/year. LSIR represents an
individual risk (IR) to an individual who remains at the location at all the time. Considering that the
individual could move to different location from high risk to low risk, an occupancy ratio of 0.5 is
appropriate thus giving an individual risk (IR) of 2.71E-3 per year. This level of risk is considered
unacceptable (>1E-4 is unacceptable for general public). Even if the occupancy ratio is taken as 0.1,
i.e. an individual is only in the high risk area for less than 2.5 hours per day, the risks are still
unacceptable.
Page 85 of 96
Report No. 2514054 R01
Issue 4
It may therefore be concluded that the risk to the villages is unacceptable both from individual risk
and societal risk perspectives.
The Location Specific Individual Risk (LSIR) for the road is shown in Figure 34. The results show
that the maximum LSIR at the road area is 1.88x10-3/year. The occupancy ratio considered for the
road is 0.006 based on the traffic moving at 60 km/hour and any one individual travelling twice a
day, six days per week across the site on this road. Therefore, the maximum individual risk at the
road is 1.13x10-5/year which corresponds to the ALARP region based on the risk tolerability criteria
in Section 6.4. This implies that mitigation measures should be considered to reduce risks as long as
the cost of such measures is not disproportionate to the benefit.
Page 86 of 96
o
Report N . 2514054 R01
Issue 4
Figure 34 – Total Fire and Explosion Risk Contour Level Main Plant
Page 87 of 96
o
Report N . 2514054 R01
Issue 4
Figure 35 – Total Fire and Explosion Risk Contour Level Jetty Area
Page 88 of 96
Report No. 2514054 R01
Issue 4
The results from this coarse QRA indicate that there are a number of buildings at the site that require
risk reduction measures. This includes 18 buildings where risk mitigation must be undertaken and
10 buildings where risk mitigation should be considered, and implemented as necessary, in order to
demonstrate that the building’s risk status is ALARP. Total fire and explosion risk contour level
The focus of the Risk mitigation is to reduce the likelihood and/or consequences of explosions/Fire
on the site.
Based on this analysis, the following Table 18 provides a summary of recommendations for
refinement of the risk predicted for an area/building or for mitigation of its risk. The
recommendations are presented as General, Explosion and Fire.
Even though the explosion risk at NSRP is low, it is recommended that best industrial practice
should be used and building classification not be downgraded based on the results of this risk
assessment.
Furthermore, a detailed QRA must be undertaken once detailed plant design is in place to confirm or
update the explosion risks in particular which are sensitive to plant congestion but also other risks
which are based on the early plant information. At the detailed QRA stage, it may be possible to take
account of various mitigations in place such as the water deluge, shutdown and blowdown and risk
based inspection and maintenance and regular fugitive emission testing.
Table 18 –Recommendations
General Recommendations
Ensure that the design specifications for all plant include performance standards such that plant
L1
failure, and thus hydrocarbon release scenarios, will be minimized through design.
Reduce the hazard magnitude through the installation of gas (toxic and flammable) detectors
with emergency shutdown (ESD) systems within the critical hazard locations. Emergency
L2 shutdown valves to be located outside fire impact zone. If the valve is located inside a
fire/explosion zone then fire proofing is necessary to provide protection for a specified period of
time in line with API 2001.
Where possible, consider leak point minimization for all equipment (e.g. welded, rather than
L4
flanged pipe connections, fail safe valves, spring loaded manual valves, flange covers)
Implement a risk-based inspection (RBI) and maintenance process such that the plant items
L5
that pose the greatest risk to the plant receive the greatest levels of inspection and maintenance
Since there is a risk of an event moving onto the public highway, provisions will need to be in
L6
place to prevent traffic movement on the highway in the event of a site incident.
Page 89 of 96
Report No. 2514054 R01
Issue 4
Toxic and vapour cloud events, generally leave the site periphery it is suggested that a plan will
need to be in place to alert the populations to either end of the plant limit in the event of a site
incident. Such measures will form part of the Site Emergency Response Plan which is to be
L7 detailed during the Detailed design.
Emergency procedures should be put in place and followed if a leak is detected. Good
procedures and training for emergency response are essential.
Reduce Vulnerability
Reduce the vulnerability of the building occupants through the avoidance of windows within
V1
buildings located within the process areas.
Reduce the vulnerability of the building occupants to toxic ingress through the implementation of
V2 toxic gas detection and dampers on the HVAC inlet ducts for putting into recycle as well as
manual shutdown.
Explosion Recommendations
Reduce the vulnerability through relocation of road, provide a barrier between road and plant
V3 (not always effective for blast but prevents missiles) and reduce congestion near the site
boundary.
For buildings with cloud fire frequency >1E-4 p.a., positive pressurisation and double doors
V4 should be provided in the building. LEL detection should also be incorporated into the ventilation
inlets & automatically shutdown the ventilation system providing alarms on LEL detection
For buildings with cloud fire frequency between 1E-4 & 1E-5 p.a. self-closing doors with gas
tight seals should be provided in addition to LEL detection in the ventilation inlets providing
V5
automatic shutdown of the ventilation system and alarms on LEL detection (See Table 28 and
Table 29).
For Buildings with cloud fire frequency between 1E-5 & 1E-6 p.a., self-closing doors with gas
V6
tight seals and LEL monitors alarms and manual HVAC shutdown should be provided.
Fire Recommendations
Reduce the vulnerability of the buildings to flammable gas ingress through the implementation
of flammable gas detection and dampers on the HVAC inlet ducts, self-closing doors with gas
V8
tight seals and LEL monitors, alarms and manual HVAC shutdown should be provided. As given
for explosion
Reduce risk to building occupants from fire by ensuring building has safe refuge areas in case
V9
of fire and /or the building has adequate fire proofing.
Reduce BLEVE risk by insulating vessels, improve depressurisation and vessel deluge.
V10
Depressurized the leaking section using blowdown system.
Toxic Recommendations
Page 90 of 96
Report No. 2514054 R01
Issue 4
The ERPG contours are based on gas dispersion modeling for free field flat terrain. Simple
consequence assessment models used in QRA are not appropriate for dealing with complex
terrain especially for near field effects. It is recommended that a Computational Fluid Dynamics
T1
based H2S dispersion study should be undertaken in the detailed phase of the design to
ascertain the toxic risks and if there are any specific areas where high H2S concentrations
might develop due to the presence of the mountain to the west of the site.
Based on the mitigation options detailed in Table 18, recommendations in respect of explosion risk
for each functional but considered unoccupied building were assessed are provided in Table 19.
Positive
Manual Automatic Self Closing
Cloud LEL Pressurisation
Building HVAC HVAC Doors with gas
Fire Risk Detection in building and
Shutdown Shutdown tight seals
double doors
Page 91 of 96
Report No. 2514054 R01
Issue 4
Positive
Manual Automatic Self Closing
Cloud LEL Pressurisation
Building HVAC HVAC Doors with gas
Fire Risk Detection in building and
Shutdown Shutdown tight seals
double doors
Main Substation
SS-M01 1.27E-06 Yes No Yes No Yes
Emergency
Generator 1.27E-06 Yes No Yes No Yes
Administration
Building No No No No No
Negligible
Canteen No1 No No No No No
Negligible
Page 92 of 96
Report No. 2514054 R01
Issue 4
Positive
Manual Automatic Self Closing
Cloud LEL Pressurisation
Building HVAC HVAC Doors with gas
Fire Risk Detection in building and
Shutdown Shutdown tight seals
double doors
Medical Center No No No No No
Negligible
Main Guard
House No No No No No
Negligible
Central Control
Room No No No No No
Negligible
Canteen No2 No No No No No
Negligible
Fire Station No No No No No
Negligible
SS- U04 No No No No No
Negligible
SS-O04 No No No No No
Negligible
SS-O01 No No No No No
Negligible
ISB-014 No No No No No
Negligible
ISB-15 No No No No No
Negligible
Jetty Area
Guard House No No No No No
Negligible
Jetty Area
Admin/Control
Building No No No No No
Negligible
Page 93 of 96
Report No. 2514054 R01
Issue 4
Reduce the vulnerability by adding a barrier along the high risk part of the plant boundary
VR1 between the plant and the road to the south to prevent direct fire impingement and to reduce
heat flux.
VR2 Reduce risk to road users by early warning on leak and closure of access.
It is proposed that a 500m long, 6m high concrete wall designed to withstand 30 mbar side-on
overpressure as shown on Figure 36, together with the traffic control measures should provide
practical mitigation solution.
Page 94 of 96
o
Report N . 2514054 R01
Issue 4
9 UNCERTAINTY IN QRA
There will always be uncertainty as to whether certain events will occur or not, what the immediate
effects will be, and what the consequences for people, environment, or assets may be. This
uncertainty reflects the insufficient information and knowledge available for the analysis, in relation
to technical solutions, operations, and maintenance philosophies, logistic premises etc [13].
• Since the design is at FEED stage, the level of detail in the system drawings necessitates the
use of assumptions in terms of the equipment types and volumes.
• The distribution of flanges, valves, connections, instruments and pipe sizes are assumed
based on work undertaken by Shell (default values in Shepherd) and are taken to be an
average reflection of the distribution that is to be expected. However, the actual distributions
may vary in the final design.
• The consequence modelling of the release scenarios has made some simplifications in terms
of modelling the release of mixed fluids (e.g predominantly liquid material containing gases
that may flash). The analysis of this phenomenon is very complex and as such, the
consequence results for some scenarios are a best representation of the actual scenario.
• The flow rates are taken conservatively as the instantaneous release rates. These rates could
be far in excess of the actual mass flow rates of materials through the process segments. This
is considered to be accepted methods of undertaking such studies since the results are on the
side of conservatism. However, if required, such conservatisms could be explored in detail if
considered necessary.
• The explosion overpressures are derived from assumed congestion levels based on a simple
2D plant layout drawing and at the time of this assessment only were available for the RFCC,
ARC and HMU units. It is usual to visit the actual site to undertake such assessments of site
congestion. Clearly, this is not possible with a proposed plant; therefore, as the plant design
progresses, the explosion parameters should be re-visited.
• A moderate damage to site buildings is assumed if thermal flux exceeds 15kW/m2. For
concrete or masonry infill buildings this is a conservative assumption. However this gives an
estimate as to which buildings should be considered to be at risk from fire and appropriate
insulation measures.
Page 95 of 96
o
Report N . 2514054 R01
Issue 4
10 REFERENCES
8. Hydrocarbon Leak and Ignition Database, EP Forum Risk Assessment Data Directory, EP
Forum Report No. 11.8/250, E&P Forum, 1996.
9. Cox, A. W., Lees, F.W. and Ang M. Lm, “Classification of Hazardous Locations”,
IChemE, Rugby, England, 1990.
11. Frank P Lees, “Loss Prevention in Process Industries”, 2nd Edition, BH, 1996.
13. Nicolet-Monnier M. Gheorghe V. Andrian , Topics in Safety, Risk, Reliability and Quality
“Quantitative Risk Assessment of Hazardous Material Transport Systems”,. Kluwer
Academic Publishers, 1996.
14. NSRP Refinery and Petrochemical Complex Project Coarse QRA, Issue 4 FINAL, Report
No.2204898 R01, ABSC, Sep 2009
Page 96 of 96