ID Task Name Duration Start Finish % Complete Sun 07/11 Sat 13/11 Fri 19/11 Thu 25/11

1 LINGKUP PEKERJAAN PERBAIKAN PLTG UNIT 3 15 days Wed 10/11/21 Wed 24/11/21 79% 79%
2 PREPARATIONS 1 day Wed 10/11/21 Wed 10/11/21 100% 100%
100%
3 Melepas PMT 52 L dan DS 1 day Wed 10/11/21 Wed 10/11/21 100% 100%
4 Manuver Pemakaian Sendiri 1 day Wed 10/11/21 Wed 10/11/21 100% 100%
5 Roll Out PMT 52 G 1 day Wed 10/11/21 Wed 10/11/21 100% 100%
6 PEKERJAAN PERBAIKAN STATOR EARTH FAULT 13 days Thu 11/11/21 Tue 23/11/21 80%
7 PENGECEKAN ELECTRICAL MELIPUTI UJI ( TAHANAN 3 days Thu 11/11/21 Sat 13/11/21 100% 100%
ISOLASI GENERATOR, UJI PT TITIK NETRAL, UJI PT OUTPUT
GENERATOR, UJI RELAY 51GN)
8 PENGECEKAN RELAY 51GN STATOR EARTH FAULT 1 day Sun 14/11/21 Sun 14/11/21 100% 100%
9 PENGETESAN FSNL, PENGAMBILAN DATA TEGANGAN 1 day Mon 15/11/21 Mon 15/11/21 100% 100%
GENERATOR
10 PENGGANTIAN RELAY 51GN (MATERIAL DIJEMPUT KE 7 days Tue 16/11/21 Mon 22/11/21 78% 78%
UNIT LAIN)
11 PENGETESAN FSNL DAN PENGAMATAN TEGANGAN 1 day Tue 23/11/21 Tue 23/11/21 0% 0%
GENERATOR
12 START-UP 1 day Wed 24/11/21 Wed 24/11/21 0%
13 SYNCRON 1 day Wed 24/11/21 Wed 24/11/21 0% 0%

Page 1
Thu 25/11 Wed 01/12 Tue 07/12 Mon 13/12 Sun 19/12 Sat 25/12 Fri 31/12 Thu 06/01 Wed 12/01 Tue 18/01 Mon 24/01 Sun 30/01