ID Task Name Duration Start Finish % Complete Tue 8/24 Fri 8/27

1 LINGKUP PEKERJAAN PERBAIKAN KEBOCORAN UNIT 2 3.75 days Tue 8/24/21 Fri 8/27/21 53%
2 PRE-SHUT DOWN / PREPARATIONS 3 days Tue 8/24/21 Thu 8/26/21 72%
3 UNIT STOP 2 hrs Tue 8/24/21 Tue 8/24/21 100%
4 COOLING DOWN 3 days Tue 8/24/21 Thu 8/26/21 70%
5 PEKERJAAN TURBIN 2.75 days Tue 8/24/21 Thu 8/26/21 50%
6 PERSIAPAN TOOLS DAN MATERIAL 2 hrs Tue 8/24/21 Tue 8/24/21 100% 100%
7 DRAIN HOTWELL KONDENSOR 4 hrs Tue 8/24/21 Tue 8/24/21 100% 100%
8 PENGISIAN HOTWELL KONDENSOR 2 hrs Tue 8/24/21 Tue 8/24/21 100% 100%
9 PENGAMBILAN SAMPLE HOTWELL KONDENSOR 6 hrs Tue 8/24/21 Wed 8/25/21 100% 100%
10 PENGECEKAN KEBOCORAN KONDENSOR 8 hrs Thu 8/26/21 Thu 8/26/21 0% 0%
11 PLUG TUBE KONDENSOR 6 hrs Thu 8/26/21 Thu 8/26/21 0% 0%
12 START-UP 1 day Thu 8/26/21 Fri 8/27/21 0%
13 FIRING & SYNCRON 8 hrs Thu 8/26/21 Fri 8/27/21 0% 0%

Page 1
120 S-CURVE FO #2 UPK OMBILIN

100

80

60
ACTUAL
PLAN

40

20

0
8/24/21 8/25/21 8/26/21 8/27/21
ACTUAL 35% 53%
PLAN 32 48 79 100