CE 415-Project Construction & Management November 20, 2021

Seatwork No. 2 Time 8:00-10:00 AM


Problem :
Data:

Time (Weeks Cost


Activity Precedes
Normal Crash Normal Crash
A - 6 4
100,000.00 240,000.00
B - 2 1
100,000.00 150,000.00
C A 3 3
- -
D B 2 2
- -
E C 4 2
100,000.00 180,000.00
F D 1 1
- -
G E,F 1 1
- -
H G 6 3
100,000.00 160,000.00
I H 3 2
100,000.00 140,000.00
J H 1 1
- -
K J,K 1 1
- -

From the given data above:


1. Find the minimum cost of the project if the project duration will be shortened to 23 weeks.
2. Find the minimum cost of the project if the project duration will be shortened to 21 weeks.

End of Seatwork No. 2