CE 415-Project Construction & Management November 20, 2021
Seatwork No. 2 Time 8:00-10:00 AM
Problem : Data:
Time (Weeks Cost
Activity Precedes Normal Crash Normal Crash A - 6 4 100,000.00 240,000.00 B - 2 1 100,000.00 150,000.00 C A 3 3 - - D B 2 2 - - E C 4 2 100,000.00 180,000.00 F D 1 1 - - G E,F 1 1 - - H G 6 3 100,000.00 160,000.00 I H 3 2 100,000.00 140,000.00 J H 1 1 - - K J,K 1 1 - -
From the given data above:
1. Find the minimum cost of the project if the project duration will be shortened to 23 weeks. 2. Find the minimum cost of the project if the project duration will be shortened to 21 weeks.