ARUSHA-MINJINGU ROAD REHABILITATION - AC 12.

5 MIX DESIGN-SERIAL N° 1 A

COMBINATED Gsb AND Gsa FOR BLENDS FROM HOT BINS

11-19 8-11 5-8 0-5 Filler 1 Cement

Gsb 2.986 2.982 2.983 2.973 2.968 3.064 Combinated Gsb

BLEND 1 % 14.5 20 13.5 45.5 6.5 0 2.978


BLEND 2 % 11 14.5 22.5 45.5 6.5 0 2.978
BLEND 3 % 16 21.5 16.5 40 6 0 2.978
BLEND 4 A % 14.5 21 13 43.5 6.5 1.5 2.979

11-19 8-11 5-8 0-5 Filler 1 Cement

Gsa 3.089 3.101 3.088 3.087 2.968 3.064 Combinated Gsa

BLEND 1 % 14.5 20 13.5 45.5 6.5 0 3.082


BLEND 2 % 11 14.5 22.5 45.5 6.5 0 3.081
BLEND 3 % 16 21.5 16.5 40 6 0 3.083
BLEND 4 A % 14.5 21 13 43.5 6.5 1.5 3.082

Combinated Gsb or Gsa = 100 / ( (%/Gsx1 + %/Gsx2 +……..))


100

100