Professional Documents
Culture Documents
Copyright
Contact
sustainability@hydropower.org
Acknowledgements
The Hydropower Sustainability Guidelines define how good international industry practice should be
assessed, and build on the global knowledge and experience gathered through the multi-stakeholder
process of the Hydropower Sustainability Assessment Forum (2008-2010), plus insights gained through
international application of the Hydropower Sustainability Assessment Protocol (IHA, 2011).
The guidelines content was largely authored by Dr Helen Locher, who was coordinator for the Hydropower
Sustainability Assessment Forum and is an Accredited Lead Assessor for the Hydropower Sustainability
Assessment Protocol. The lead author for the Climate Change Mitigation and Resilience topic was João Costa,
Senior Sustainability Specialist, International Hydropower Association (IHA).
This compendium has benefitted from the collaboration of numerous experts who provided valuable written
comments during the expert review process. This collaboration is gratefully acknowledged.
The members of the Hydropower Sustainability Assessment Council, coordinated through its governance
committee, reviewed and approved this document.
This work would not have been possible without the financial support and guidance from the Swiss State
Secretariat for Economic Affairs.
Drafting:
Helen Locher, Lead Author
João Costa, Author (Climate Change Mitigation and Resilience)
Reviewed by:
Aida Khalil, Asian Development Bank
Andrew Scanlon, Independent Consultant
Belinda Lip, World Wide Fund for Nature
Donal O’Leary, Transparency International
Douglas Smith, Independent Consultant
Eduard Wojczynski, Independent Consultant
Eleni Taylor-Wood, Entura
Elisa Xiao, New Development Bank
Gabriel Todt de Azevedo, Inter-American Investment Corporation – IDB Invest
Jeff Opperman, World Wide Fund for Nature
Jeremy Bird, Independent Consultant
Jian-Hua Meng, World Wide Fund for Nature
Joerg Hartmann, Independent Consultant
Margaret Trias, TULLOCH Engineering
María Ubierna, International Hydropower Association
Mathis Rogner, International Hydropower Association
Richard Taylor, International Hydropower Association
Sara Mercier-Blais, Université du Québec à Montréal – UQAM
Communications:
Will Henley, International Hydropower Association
Louis Scorza, International Hydropower Association
Communications
Communications
and Consultation and Consultation————————————————————————————— 06
Governance—————————————————————————————————————— 12
Governance
Demonstrated
Demonstrated
Need and Need and Strategic Fit———————————————————————————— 18
Strategic Fit
Siting
Siting
and Designand Design———————————————————————————————————— 22
Environmental
Environmental
and Social Issues and Social Issues Management———————————————————————— 28
Management
Integrated
Integrated Project Management—————————————————————————————— 36
Project
Management
Hydrological
Hydrological Resource—————————————————————————————————— 40
Resource
Asset Reliability
Asset
and Reliability and Efficiency—————————————————————————————— 46
Efficiency
Infrastructure
Infrastructure Safety——————————————————————————————————— 52
Safety
Financial
Financial Viability———————————————————————————————————— 58
Viability
Project
Project Benefits————————————————————————————————————— 68
Benefits
Economic
Economic Viability———————————————————————————————————— 74
Viability
Procurement—————————————————————————————————————— 78
Procurement
Resettlement—————————————————————————————————————— 94
Resettlement
Indigenous
Indigenous Peoples——————————————————————————————————
Peoples 102
Labour and
Labour and Working Conditions—————————————————————————————
Working 112
Conditions
Cultural
Cultural Heritage———————————————————————————————————
Heritage 120
Public
Public Health—————————————————————————————————————
Health 126
Biodiversity and
Biodiversity
Invasive Species and Invasive Species———————————————————————————— 134
Erosion and
Erosion and Sedimentation———————————————————————————————
Sedimentation 142
Reservoir
Reservoir Management————————————————————————————————
Management 150
Water
Water Quality—————————————————————————————————————
Quality 154
Waste, Noise
Waste,
and Noise and Air Quality——————————————————————————————
Air Quality 162
Downstream
Downstream
Flow Regimes Flow Regimes——————————————————————————————— 170
Climate Change
Climateand
Mitigation Change Mitigation and Resilience————————————————————————— 176
Resilience
This guideline expands on what is arising in the external environment and changes
expected by the criteria statements in these factors over time; an increased ability to
find management solutions that are supported
in the Hydropower Sustainability by stakeholders; and, ultimately, the avoidance
Tools (HST) for the Communications of delays and additional costs arising from poor
and Consultation topic, relating to communications.
assessment, management, stakeholder
engagement and conformance/ A stakeholder is defined as anyone who is
compliance. The good practice criteria interested in, involved in or affected by the
are expressed for different life cycle hydropower project and its associated activities.
Project stakeholders can consist of a broad
stages. range of different groups, such as affected
communities, government agencies, partners,
In the Hydropower Sustainability contractors, suppliers, financiers, catchment
Assessment Protocol (HSAP), this topic residents, the media, academics and experts,
civil society, and Non-Government Organisations
is addressed in P-1 for the preparation (NGOs). A stakeholder does not have to be
stage, I-1 for the implementation stage directly affected to meet project stakeholder
and O-1 for the operation stage. In definition and anyone with an interest should
the Hydropower Sustainability ESG be able to have access to mechanisms for
Gap Analysis Tool (HESG), this topic is communication and engagement.
addressed in Section 10. The intent is that stakeholders are identified and
engaged in the issues of interest to them, and
Hydropower projects involve a range communications and consultation processes
of stakeholders. Effective stakeholder establish a foundation for good stakeholder
communications and consultation throughout relations throughout the project life.
the life of the project is an important element
of good practice. Benefits for the developer and
owner/operator can include: a better and earlier
understanding of project risks and opportunities
This guideline addresses the contribution of the In the case of a transboundary project there may
project in meeting demonstrated needs for water also be regional (i.e. multi-national) initiatives that
and energy services as identified through broadly have relevant policies and plans. The project may
agreed local, national and regional development be within the sphere of a River Basin Organisation
objectives, and in national and regional policies (RBO) that has its own institutional structures,
and plans. The intent is that the project fits with policies, agreements, plans, and guidelines. There
development objectives and relevant policies may be bilateral or multi-lateral agreements that
and plans can be demonstrated, and that the govern the shared water resource. The developer
project is a priority option to meet identified will need to know what state or province (the tier
needs for water and energy services. The terms below national) the project sits within, whether
‘demonstrated need’ and ‘strategic fit’ are often any aspects of the project have implications that
associated with the early assessment stage of cross state or provincial boundaries, and the
energy and water planning and are closely linked policy and planning requirements that will be
with options assessment. For example, a Strategic applicable. There may also be a local government
Energy services examples include: provision of The project under consideration may not be the
electricity to meet local, national and/or regional only avenue used to address these needs, but
demand or opportunities; provision of grid it should clearly contribute towards addressing
stability; provision of peak load; and provision of the identified needs. Any conflicts (e.g. with
ancillary benefits such as spinning reserve, system food security) should be identified at an early
regulation, and improved thermal efficiency. A stage so that measures to address them can
hydropower development to meet the energy be built into the project proposal (e.g. through
requirements of an energy-intensive off-taker modifying project components or through
(e.g. an aluminium smelter) would be considered project benefits). Ways in which a project can
a demonstrated need if it is included in broadly contribute to multiple demonstrated needs could
agreed development objectives, policies and include the provision of energy, fresh water,
plans. new industries, new employment opportunities,
and new avenues for food production. Multi-
Local, national and regional objectives may purpose projects are often designed for multiple
be expressed in different forms, such as: an objectives, although every project does not
energy master plan; a water development necessarily have the right characteristics for this.
plan; a country development report; strategic
environmental assessments; options assessments;
This guideline expands on what is • deliver the project objectives – the power station
may be single purpose (hydropower generation
expected by the criteria statements in the only, which in turn may be for base load or peak
Hydropower Sustainability Tools (HST) load power, domestic use or export, or servicing
for the Siting and Design topic, relating rural or urban or industrial needs) or multi-
purpose (e.g. the reservoir may also provide
to assessment, management, stakeholder water supply for irrigation, aquaculture, or other
engagement and outcomes. The good industries, or be used for recreational, tourism
practice criteria are expressed for the and development purposes);
preparation stage. • optimise the constructed elements of the project
– namely the dam type and size, generation
capacity and efficiency, safety and access; and
In the Hydropower Sustainability
• avoid, minimise and mitigate any issues
Assessment Protocol (HSAP), this topic associated with the development – these should
is addressed in P-4. In the Hydropower not only consider technical and financial issues,
Sustainability ESG Gap Analysis Tool but should also include social and environmental
aspects.
(HESG), this topic is addressed in Section 1.
Optimal in this context means best fit once all
identified sustainability considerations have
This guideline addresses the evaluation and been factored in based on the outcomes of
determination of project siting and design a consultative process. Project designers are
options, including the dam, power house, skilled in optimising for technical and financial
reservoir and associated infrastructure. The objectives, such as maximising power output for
intent is that siting and design are optimised least cost. This guideline is focussed on ensuring
as a result of an iterative and consultative that a broader set of objectives, including
process that has taken into account technical, regulatory, social, environmental, safety and
economic, financial, environmental and social stakeholder priorities, informs and influences the
considerations. optimisation process and conclusions for project
siting and design.
The siting and design of a hydropower project
aim to: Examples of sustainability considerations for siting
and design include: prioritising alternatives that
The siting of a hydropower project will initially • criteria and methods for MCA evaluation have
be a location that offers an ability to technically been defined based on an engaged process with
stakeholders;
generate hydropower due to:
• criteria reflect social and environmental
• the head – i.e. the height through which water considerations in addition to technical and
would fall to reach the turbine (the greater the financial aspects;
head, the more power can be generated);
• methods of and outcomes from the MCA
• the volume of water available – the more analyses are readily able to be understood by key
water available, the greater the number and/or stakeholders;
size of the turbines that can be spun and
the greater the power output of the generators;
• information on technical, financial, economic,
regulatory, social and environmental criteria is
and
collected using appropriate expertise, and clearly
• the geological suitability for a dam – this is informs the analyses of location and general
determined by the shape and size of the valley at layout options; and
the proposed construction site and the geology
• stakeholder inputs and views are clearly
of the valley walls and floor. reflected in the options, the analyses, and the
The location selection for hydropower outcomes.
developments is generally (but not always) based More detailed siting and design investigations are
on consideration of several location options, and typically undertaken as part of project feasibility
the general layout that would suit each location studies. This process tests the suitability of the
option. Technically feasible sites for hydropower location and the exact siting of the project
can be derived at a comparative level (i.e. to show components through on-site investigations
more or less promising sites) from contour maps, (e.g. test drilling), develops the project design,
hydrological statistics and geological maps, which and considers how to optimise a host of other
Design documents should be produced at varying Stakeholder mapping should identify directly
levels and should include preliminary designs, affected stakeholders for various aspects of
groupings of designs according to specialty the project (see the Communications and
area (e.g. civil, structural, electro-mechanical, Consultation guideline). ‘Two-way’ engagement
geotechnical, hydraulic), and detailed designs for means the stakeholders can give their views
specific project components (e.g. weirs, spillways, on siting and design considerations rather
tunnels and channels, pumping stations, surge than just being given information without any
tanks). Documentation should also include opportunity to respond. Examples of two-‐way
drawings, technical specifications, modelling processes include public meetings and hearings,
works such as fluid computational modelling, and public comments on studies and options
master designs and plans. Physical models may assessment documents, interactive participation
need to be developed to test different design in workshops, negotiation, mediation, and focus
components, for example hydraulic flumes to groups.
test sediment management approaches. Physical
models of the project layout can also help Appropriately timed means that engagement
stakeholders engage to discuss where there are starts early enough in the preparation stage so
issues to be avoided. that the project can respond to the issues raised;
stakeholders can respond before the project takes
decisions; and engagement takes place at times
Stakeholder Engagement that are suitable for people to participate (e.g.
Stakeholder Engagement criterion – Preparation with respect to seasonality or time of day).
Stage: The siting and design optimisation process has
involved appropriately timed, and often two-way, Stakeholders should be supportive of the timing
engagement with directly affected stakeholders; of engagement activities. Communities need
ongoing processes are in place for stakeholders to sufficient time to receive information, be able to
raise issues and get feedback. discuss it openly with the project representatives,
then go through their own community dialogue
Location and general layout options, and siting processes before forming a consolidated
and design alternatives, should be identified community view to relay back into the evaluation
based on a dialogue with directly affected processes.
stakeholders, and this engagement process
Processes in place for stakeholders to raise issues
should continue through the evaluation and
could include, for example, a contact person and/
optimisation process. This engagement often
or a ‘contact us’ space on the company website,
happens as part of the ESIA process so the
Outcomes
Outcomes criterion - Preparation Stage: The final
project siting and design has responded to many
sustainability considerations for siting and design.
Hydropower projects can have a number of • environmental and social commitments are
environmental and social impacts if these are not fulfilled.
carefully assessed and managed. Fortunately, • ‘Avoid, minimise, mitigate and compensate’ is
there is considerable global experience available a concise expression for what is understood
to help identify potential impacts and to mitigate to be a sequential process. Measures to avoid
these impacts. Hydropower projects are quite or prevent negative or adverse impacts are
individual due to their varied technological always prioritised, and where avoidance is
specifications and environmental and socio- not practicable then minimisation of adverse
Management
impacts is sought. Where avoidance and • a scope including the hydrological resource,
minimisation are not practicable, mitigation terrestrial and aquatic biodiversity, waste,
and compensation measures are identified and noise, air quality, water quality, erosion and
undertaken commensurate with the project’s sedimentation, downstream flows, project
risks and impacts. affected communities (including a focus on
resettlement and on indigenous peoples if
Assessment relevant), climate change, cultural heritage,
public health, and labour and working
Assessment criterion - Preparation Stage: conditions (individual guidelines provide further
Assessments of project environmental and details on each of these topics);
social impacts have been undertaken for project
• distinct evaluation of the above areas for the
implementation and operation, including evaluation pre-construction, construction and operation
of associated facilities, scoping of cumulative stages of the project;
impacts, role and capacity of third parties, and
impacts associated with primary suppliers, using • proposed mitigation measures and management
plans linked to each identified impact, with
appropriate expertise and with no significant gaps;
each measure clearly stating the objective and
and a baseline has been established and well-
indicators of effectiveness;
documented for the pre-project condition against
which post-project changes can be compared. • identification of residual impacts, i.e. those
remaining after mitigation measures are
implemented;
During project preparation, assessment of
potential environmental and social impacts, • management plan implementation
and the planning of measures to address these arrangements, including responsibilities, timing,
impacts, are as fundamental as engineering resources and budget; and
feasibility studies. The Environmental and Social • a monitoring programme that addresses all
Impact Assessment (ESIA) report is a critical step potential impacts and will demonstrate if
taken alongside project feasibility studies and mitigation measures are effective or not.
informing detailed design. An ESIA identifies, Defining the project affected area is a critical
predicts, evaluates and proposes mitigation for step in the impact assessment process. This
the biophysical, social, and other relevant effects should be done at the scoping stage so that more
and consequences of development proposals detailed impact assessment and consultation is
prior to major decisions being taken and comprehensive. The project affected area is the
commitments made. project’s area of influence in terms of direct and
indirect effects. The assessment should not be
To meet good practice, an ESIA report should
limited by jurisdictional boundaries; i.e. an impact
contain at a minimum:
assessment should not stop at a national or state
border unless a credible assessment determines
• a description of the proposed hydropower
project; that there will be no impacts outside of this area.
Surrounding communities, activities along roads,
• the hydropower project rationale and quarries, disposal areas, and downstream areas
alternatives; subject to project influence must be included.
• a description of the existing environment
sufficient to establish the pre-project baseline; Spatially, the scope of impact assessment and
management must cover direct and indirect
• relevant legal and policy requirements;
impacts. Direct impacts are those under the
• a summary of stakeholder consultation control of or caused by the project, such as:
undertaken during the impact assessment (see changes in land ownership and/or land use;
the Stakeholder Engagement criterion for this changes in environmental quality; and changes
topic); in quality of life for directly affected people.
• identification and assessment of potential Indirect impacts are those outside the control
positive and negative project impacts, including of the project, such as: induced changes in
ratings of their likelihood, and the magnitude regional demographics, employment, business
and severity of consequences; and tax revenues, property values, and supply
chain effects. The establishment of a project
Management
Impacts, mitigation measures, management, Throughout the impact assessment process
and monitoring plans should be considered and identification of ongoing and emerging
separately for the project construction and issues, appropriate expertise should be used.
operation stages. Predicted impacts should be This is especially the case for specialist issues.
described using recognised descriptive terms Appropriate expertise refers to specialists with
to characterise the impacts, such as: type of experience in the key identifiable topical areas of
impact (positive, negative); nature of impact the assessment and management plans, giving
(direct, indirect, cumulative, potential if trigger particular attention to the differences between
conditions are met); magnitude or severity of environmental areas and social impact areas.
impact (low, moderate, high); extent of impact Impact assessment reports should document the
in terms of geographic area (small, medium, expertise used.
large); timing of impact (short-term, long-term,
intermittent, continuous, seasonal); duration of
impact (temporary, permanent); reversibility of
Assessment
impact (reversible, irreversible); and significance Assessment criterion - Implementation Stage:
of impact (local, regional, global). Descriptive Environmental and social issues relevant to project
terms should be explained for the different types implementation and operation have been
of impacts as needed. identified through an assessment process, including
evaluation of associated facilities, scoping of
Every attempt should be made to quantify cumulative impacts, role and capacity of third
the impacts. Predictions of impacts are parties, and impacts associated with primary
normally based on commonly used qualitative suppliers, using appropriate expertise; and
and quantitative methods and models. The monitoring is being undertaken during the project
sophistication of the predictive models should implementation stage appropriate to the identified
be proportional to the significance of the issue to issues.
which it is being applied.
During project implementation, there is a need to
The assessment should include researching monitor:
appropriate mitigation approaches for all
identified impacts. Some hydropower impact • waste, noise, dust, air quality, water quality,
mitigation measures are well-known and often erosion, sediments, and hazardous materials
applied (e.g. speed limits for vehicle related arising from construction activities;
risks), whereas others require considerably • secondary effects of construction and
more evaluation due to questions of cost and implementation activities on receptors (e.g.
likely effectiveness (e.g. multi-level offtakes for environmental receptors such as habitats and
reservoirs at risk of developing stratification, wildlife, and social receptors such as workers,
re-regulation weirs or storages to dampen flow communities and livelihoods); and
fluctuations, downstream flow releases, fish • the quality of implementation of environmental,
passage technologies, fish hatcheries, livelihood health and safety, and social programmes
improvement options, and project benefits). within the ESMP (resettlement, cultural heritage,
There may well be other measures that would occupational and public health, etc. as relevant).
merit further analysis for the proposed project
based on conflicting views among stakeholders The purpose of monitoring is to ensure
and the benefits that closer analysis and impacts are mitigated, to verify achievement
justification would bring. The effectiveness of a of objectives, and to identify any issues arising.
mitigation approach for one hydropower project Monitoring commitments should be integrally
may not be achievable for another project, so embedded within the ESMP so that the reasons
the feasibility of alternative approaches needs for monitoring are clearly apparent. Monitoring
to be tested. The feasibility of each mitigation information within the various ESMP sections
approach should be carefully considered with should clearly identify, with reasons given:
respect to factors such as likeliness of achieving parameters, locations, timing, sample analysis
its objectives, cost effectiveness, understanding and data reporting methods, standards for results
of the relevant technology or policy approach, comparison, and responsible parties.
capacity to deliver, experience in application,
stakeholder views, and risks.
Management
protection works; wastewater treatment plants; objectives. Ideally, the ESMP would also include
fish passage; re-regulation structures; and safety adaptive management measures. This would
barriers. Non-structural measures include, for identify what issues might be identified through
example: economic incentives; legal, institutional the monitoring and surveillance and what
and policy instruments; reservoir and power the response would be (including responsible
station operating rules (e.g. ramp-up and ramp- parties and contingency budget set aside).
down rates, minimum and maximum reservoir
levels); water release rules for downstream flow The ESIA and ESMP should be made available
commitments; information signage; warning to the public. This is often achieved by making
sirens; provision of community services; and hard copies available in public venues, for
training and capacity building. Non-structural example at the regulator’s office and at local
measures are increasingly being used to reinforce municipal offices; by posting the documents on
or supplement structural measures and to a publicly accessible website; and by providing
address specific impacts. summaries on paper and verbally in local
public meetings. International good practice
The ESMP needs to be structured to distinctly requires making the ESIA and ESMP fully
cover construction and operation. Sections of available on an easily accessible public website
an ESMP for hydropower projects will reflect so that it can be accessible to a broad group
the individual project context and issues. of interested stakeholders, as well as ensuring
Examples of focal areas that may be within local availability through well-considered means
the ESMP are: catchment area treatment and (see the Communications and Consultation
protection; the Resettlement Action Plan; guideline).
principles and guidance relating to indigenous
peoples; spoil (excavated waste soil) dump
management; compensatory afforestation;
Management
downstream (or “environmental”) flows; Management criterion - Implementation Stage:
integrated water resources management; Processes are in place to ensure management
emergency management; terrestrial biodiversity of identified environmental and social issues
conservation and wildlife management; utilising appropriate expertise (internal and
green belt development; quarry restoration; external), and to meet any environmental and
aquatic biodiversity conservation and fisheries social commitments, relevant to the project
management; air quality management; implementation stage; plans are in place for the
noise management; labour management; operation stage for ongoing environmental and
worker occupational health and safety; land social issues management; and the environmental
management; land disturbance rehabilitation; and social impact assessment and key associated
water quality management; water use and water management plans are publicly disclosed.
supply management; reservoir rim treatment;
erosion and sedimentation management; Management criterion - Operation Stage: An
wastewater treatment; solid waste management; environmental and social management system
public health management; stakeholder is in place to manage measures to address
engagement; grievance management; identified environmental and social issues, and
community development; project benefits; is implemented utilising appropriate expertise
livelihood improvement; community safety; (internal and external).
road safety; energy conservation; and traffic
management. Identification and associated management
arrangements should be updated in
Each component of the ESMP must outline response to changes in the project, findings
impacts, mitigation measures, mitigation from monitoring programmes, changes in
objectives and indicators of success, community expectations, and changes in
responsibilities, budget including contingency, compliance requirements that may occur
time schedule, and monitoring. It is essential that during implementation and operation. An
all items on the above list are included or else the environmental and social management
ESMP actions risk not achieving their intended system provides a systematic approach to
Management
To show that plans avoid, minimise, mitigate demonstrate that responsibilities and budgets
and compensate negative environmental and have been allocated to implement ESMP plans
social impacts from project activities, mitigation and commitments. Monitoring reports and
measures in the plans should be directly linked data in the implementation and operation
to all identified environmental and social issues stages should clearly track performance
and risks. The assessment and planning should against commitments and objectives and
be informed by appropriate expertise. The capture environmental and social impacts.
assignment of responsibilities and resource It should be possible to provide examples to
allocation for implementation, monitoring and show how identified risks from the ESIA have
evaluation should be appropriate to the planned been avoided or minimised. It should also
actions. be possible to table evidence to show that
mitigation plans have been implemented
An evidence-based approach should demonstrate and are being monitored. Implementation
that negative environmental and social impacts of measures for environmental and social
arising from project implementation and mitigation should be evident and monitoring
operation activities are avoided, minimised, should show how they are achieving their
mitigated and compensated with no significant stated objectives.
gaps. The developer, owner and operator should
This guideline expands on what is one component does not progress at the expense
expected by the criteria statements in the of another.
Hydropower Sustainability Tools (HST) for
the Integrated Project Management topic, Project components in this context refer
relating to assessment, management, to components of the overall hydropower
development programme that need to be
conformance/compliance and outcomes. scheduled and managed. These may include,
The good practice criteria are expressed and are not limited to, design, construction,
for the preparation and implementation environmental, social, resettlement, finance,
stages. safety, human resources, communications, and
procurement.
• the adequacy of asset management inspections, Routine monitoring may include visual
functional testing, condition assessment, inspections, testing, measurements, and data
maintenance, repair, rehabilitation and upgrade collection from instrumentation. Measurements
regimes.
can be obtained through a diverse range of
sensors selected for specific risk detection or
assurance of optimal running conditions, such
Assessment as accelerometers for vibration or strain gauges
Assessment criterion - Operation Stage: Routine for mechanical stresses. An online condition
monitoring of asset condition, availability and monitoring system for the generator, turbine and
reliability is being undertaken to identify risks and main transformers can be set up to enable live
assess the effectiveness of management measures; data to be read by system operators at a central
and ongoing or emerging asset maintenance and control room.
management issues have been identified.
Optimal asset management is based on
analysis of technical condition, residual life, risk,
Operating conditions should be continuously
profitability, and timing of maintenance and
monitored and recorded. A number of intrusive
reinvestments. Condition assessments are a key
inspection and maintenance activities are
element of optimising asset management and
required in order to achieve the expected asset
as noted under the Management criterion are
life. These activities need to be complemented
the cornerstone of a mature asset management
by a well-tailored programme of preventative
system. These assessments support the
maintenance, condition monitoring and testing.
development of long-term investment strategies,
Monitoring should inform identification of prioritisation of capital investments, coordination
ongoing and emerging asset maintenance and of operations and maintenance (O&M), and
management issues. Asset maintenance issues identification and tracking of performance goals.
may be related to, for example, budget cycles
Condition assessments should be designed to
and availability, the availability and capabilities
achieve objective and repeatable assessments
of the workforce, logistical or access difficulties to
with minimal time and expense for testing, data
undertake planned maintenance, or the ability to
analysis, reporting and data management. Risks
get parts and spares.
to avoid in undertaking assessments include:
Asset reliability issues could include, for inefficient processes; more tests or inspections
example: start failures and forced or unplanned than is necessary; improper validation or
outages (i.e. the power station stops operating), calibration of procedures and results; and a lack
maintenance-induced failures; or constrained of a convenient or consistent method to store,
operation due to, for example, temperature access and utilise data.
or vibration issues. Asset efficiency issues
Condition assessments typically result in
could relate to megawatts (MW) of electricity
development of a condition index or rating.
generation per unit of water flow (m3/s) being
A view on a particular asset unit or group and
This guideline expands on what is there are a broad range of risks to the community
expected by the criteria statements in that need to be taken into account. The
requirements and expectations for the developer
the Hydropower Sustainability Tools and owner/operator differ during the life cycle
(HST) for the Infrastructure Safety topic, stages - project preparation, implementation and
relating to assessment, management, operation. The intent at any life cycle stage is that
conformance/compliance and outcomes. life, property and the environment are protected
The good practice criteria are expressed from the consequences of dam failure and other
infrastructure safety risks.
for different life cycle stages.
This guideline is primarily focussed on community
In the Hydropower Sustainability safety but has the benefits of increased employee
Assessment Protocol (HSAP), this topic safety. More focussed guidance on employee
is addressed in P-8 for the preparation safety is provided in the Labour and Working
stage, I-5 for the implementation stage Conditions guideline.
and O-6 for the operation stage. In
the Hydropower Sustainability ESG Assessment
Gap Analysis Tool (HESG), this topic is Assessment criterion - Preparation Stage: An
addressed in Section 4. assessment has been undertaken of dam and other
infrastructure safety risks with appropriate expertise
during project preparation, construction and
operation, with no significant gaps.
The infrastructure safety guideline seeks to
ensure that populations affected by hydropower For hydropower projects at the preparation
infrastructure are not put at risk at any point stage, good practice requires that dam and
during the life of the hydropower project. other infrastructure safety risks are thoroughly
While dam safety is one of the most critical identified for each project stage using
infrastructure safety considerations, this topic appropriate expertise.
also has a strong community safety focus and
Safety
risks that can arise during preparation activities and determination of the design flood for the
could relate to, for example: temporary labour spillway are critical assessment requirements
camps, access roads, test wells, helipads, fuel for dam safety at the preparation stage. The
storage, and power supply. During preparation, methodologies used, hydrological datasets, and
structures may be built or assembled in guiding standards all need to be well-considered
previously undeveloped locations with no and justified (see the Hydrological Resource
protection against community interactions. The guideline). Regional circumstances will influence
assessment should consider risks inherent to the the degree to which other types of risks require
structures, the likelihood of community impacts, consideration (e.g. volcanism, seismicity, landslip
and options to avoid or minimise safety incidents hazard, glacial lake outburst floods). Cascading
(e.g. location, fencing or other barriers, security dam failure may be of importance in basins with
personnel, signage). multiple dam developments. Dambreak analyses
should always be undertaken to determine
During the preparation stage, the evaluations the downstream risk zones, the populations or
that ensure adequate safety measures will structures at risk, and propagation times for
be incorporated into the permanent project flood waves, and these analyses should inform
infrastructure design are critical. Dam and other emergency response planning.
infrastructure design choices are informed by
numerous and varied assessments including: All regulatory requirements for the jurisdiction,
climatic, hydrological, hydraulic, geological, and relevant design standards for the
geotechnical, seismic, glacial (where relevant), infrastructure and risks, should be identified, well-
and material properties. documented and met.
For a hydropower project, dam safety is Appropriate expertise must be used for
paramount and a highly specialised field. All infrastructure safety-related assessments. This
potential failure modes, i.e. features or events refers to specialists with proven experience
in the systems that can lead to an asset failure, designing and constructing projects of a
should be identified and addressed where similar complexity. Particular attention should
possible in the dam design. Extreme events can be given to engineering safety competencies,
trigger failures (e.g. floods, earthquakes, fire, such as hydrological, geotechnical, structural,
landslips, landslides), as well as more incremental electrical, mechanical, and for key risk areas (e.g.
processes internal to the structure (e.g. cracks, seismology, volcanology, glaciology).
settlement, instability). The design should address
all identified failure modes and consider the Important during the preparation stage is
following dam failure risks at a minimum: infrastructure safety risk assessment and planning
for the implementation and operation stages.
• overtopping, which may be caused by Any risk assessment should take a systematic
inadequate spillway design, debris blockage of approach to considering possible risks,
spillways, or settlement of the dam crest; monitoring instrumentation and procedures,
• foundation defects, which may arise due to and management responses to risks that may
settlement or slope instability; materialise during each project life cycle stage.
• seepage-induced erosion (i.e. piping), which
can occur around hydraulic structures such as Assessment
pipes and spillways; through animal burrows;
around roots of woody vegetation; and through Assessment criterion – Implementation Stage: Dam
cracks in dams, dam appurtenances, and dam and other infrastructure safety risks relevant to
foundations; project implementation and operation have been
identified through an assessment process; and safety
• structural failure of the materials used in dam monitoring is being undertaken during the project
construction; and
implementation stage appropriate to the identified
• inadequate monitoring and maintenance. issues.
Safety
responsibilities for different safety issues allocated report, or inclusion of a safety expert in a panel of
to different parts of a business. Linkages and experts.
overlaps between asset management planning
and safety management planning should be
clearly defined. Plans should outline what actions
Management
will be implemented for the important aspects Management criterion - Implementation Stage:
of infrastructure safety identified through the Processes are in place to address identified dam
assessment processes. Plans should make it clear and other infrastructure safety issues and to meet
how responsibilities are allocated, important any safety-related commitments relevant to the
timing requirements, budget allocations, and project implementation stage, including providing
reporting and review procedures. for communication of public safety measures; a
formal quality control programme is in place for
Examples of infrastructure safety management construction; safety management plans for the
measures that may be included in relevant plans operation stage have been developed in conjunction
include: signage, exclusion zones, emergency with relevant regulatory and local authorities; and
preparedness and response, monitoring, emergency response plans include awareness and
inspections, training, incident response, and training programmes and emergency response
communications. Regulatory and local authorities simulations.
should be consulted and involved in preparation
of infrastructure safety plans, especially where Management criterion - Operation Stage: Dam and
they involve public safety measures. other infrastructure safety management plans and
processes have been developed in conjunction with
Public safety measures need to be communicated relevant regulatory and local authorities with no
as appropriate to the measure and populations. significant gaps and provide for communication of
Examples of communications methods for public public safety measures; emergency response plans
safety include: public signage, documentation and processes include awareness and training
appropriately lodged with local authorities, programmes and emergency response simulations.
awareness raising through various types
of community engagements, and verbal During the implementation and operation stages,
communications by on-site patrolmen. infrastructure safety plans relevant to those
stages should be demonstrably put into action.
Given the potential consequences of any dam
The management arrangements are likely to be
safety incident to public safety, international
quite different given the large role of contractors
good practice requires independent review of
in the construction processes versus what is
all aspects of dam safety to be undertaken at
probably a more permanent and smaller staff
the preparation stage. Ideally, this should be an
during operations. Consequently, it is essential
ongoing process that commences during the
to have plans catering to each of these stages
development of concept designs and continues
and the relevant risks and mitigation measures
right through the operation stage, with the
that have been identified. Because of the long
frequency of independent reviews during the
time frame applicable to the operations stage,
operations stage being commensurate with risks.
review and updates to plans should be made at
Independent review refers to expert review by
meaningful time intervals.
someone who is not employed by the project,
has no financial interest in profits made by the During implementation, the quality control
project, is not unaligned with the project in programme to ensure that infrastructure is
any other manner, and is generally perceived built to design specifications is of very high
as being objective. An expert is a person with a importance. Quality control process examples
high degree of skill in or knowledge of dam and include procurement specifications and factory
infrastructure safety as a result of a high degree assessment tests, materials testing away from and
of experience or training in that subject. Forms of on-site, supervision procedures, and involvement
independent review may vary. Examples include of design engineers during construction
contracting an expert consultant to provide a monitoring. Quality control processes should
Safety
is based on the magnitude and consequence demonstrate that infrastructure safety risks
of that omission and will be context-specific. during project implementation and operation
For example, a failure to demonstrate delivery have been avoided, minimised and mitigated
of an infrastructure safety commitment such as with no significant gaps. The developer,
implementation of an alarm system is a significant owner and operator should demonstrate that
non-conformance, whereas a slight delay in responsibilities and budgets have been allocated
delivery of a monitoring report could be a non- to implement infrastructure safety plans and
significant non-conformance. commitments. Monitoring reports and data in
the implementation and operation stages should
clearly track performance against commitments
Outcomes and objectives, and have a systematic approach
Outcomes criterion - Preparation Stage: Plans avoid, to data collection, analysis and reporting so
minimise and mitigate safety risks with no significant that incidents and trends are fully evident. It
gaps. should be possible to provide examples to show
how identified risks from the assessment were
Outcomes criterion - Implementation and avoided or minimised. Evidence should show
Operation Stages: Safety risks have been avoided, that mitigation plans have been implemented
minimised and mitigated with no significant gaps. and are being monitored. Implementation
of measures for infrastructure safety should
be evident, such as signage, fencing, alarms,
Of utmost importance is that public safety risks security personnel, a quality control lab on the
relating to infrastructure are recognised and construction site, actions taken to reject materials
addressed to a justifiable level of residual risk. that failed testing, minutes of meetings with
local emergency services, and photo records
To show that plans avoid, minimise and mitigate of emergency response simulation exercises.
infrastructure safety risks, they should include Records should be kept of any safety incidents,
a thorough outline of relevant risks. Mitigation including near misses, and these should inform
measures in the plans should also be directly improvements of plans and processes. Ideally,
linked to all identified risks. The assessment and plans and processes should reflect a continuous
planning should be informed by appropriate improvement approach and should be adapted
expertise. The assignment of responsibilities to ensure that incidents that have occurred are
and resource allocation for implementation, unlikely to be repeated. Monitoring should show
monitoring and evaluation should be appropriate how plans are achieving their stated objectives.
to the planned actions.
Capital budgeting methods for financial There are other financial indicators that
modelling have more rigour and use of one or developers and lenders are likely to be closely
more of these methods should be demonstrated tracking. Lenders often have thresholds on
by the project. Because the amount of capital financial ratios specified in financial agreements,
for a new project will be limited at any given with measures to be employed if target ratios
time, capital budgeting techniques are used to are breached. Examples of commonly tracked
determine which investment scenario will yield financial ratios include:
the most financial return over a period of time.
Three examples of widely recognised methods • Debt to Equity Ratio. The debt to equity ratio
of financial modelling using capital budgeting is calculated as long-term debt divided by
– Net Present Value, Internal Rate of Return, and shareholders’ equity. A high debt to equity ratio
Discounted Cash Flow – are listed below. decreases the amount shareholders need to
supply but poses risks to the lenders in terms
Net Present Value (NPV) – NPV is a common of what can be recovered in case of project
financial modelling approach. The NPV formula financial difficulties.
calculates the difference between the present • Loan Life Cover Ratio (LLCR). The LLCR
value of cash inflows and the present value of represents the number of times the cash
cash outflows over a period of time. A positive flow over the life of the loan can repay the
NPV (NPV > 0) indicates that the investment will outstanding debt balance. It is calculated as the
be profitable because the projected earnings NPV of available cash for debt service up to the
(in present value) is greater than the anticipated maturity of the loan, divided by the principal
Compliance requirements may relate to, for Outcomes criterion - Implementation and Operation
example, accounting, reporting and auditing Stages: The project or the corporate entity to which it
standards to be met, debt repayment schedules, belongs can manage financial issues under a range
tax requirements, audit schedules, and financial of scenarios, can service its debt, and can pay for
reporting to be submitted to government and/or all plans and commitments including social and
made public. environmental.
This guideline expands on what is economic contribution to society after all costs
expected by the criteria statements in the and benefits have been accounted for. This
includes social, environmental and financial
Hydropower Sustainability Tools (HST) for costs and benefits to society. Economic viability
the economic viability topic, relating to is distinct from financial viability, which typically
assessment, stakeholder engagement and focuses on the ability of a project to generate
outcomes. The good practice criteria are sufficient cash flow to deliver an appropriate risk-
expressed for the preparation stage. adjusted return on the capital invested.
The development of procurements plans and Procurement plans should clarify the processes
processes for implementation and operation to be followed to receive, review and respond
may not have taken place during the project to procurement-related grievances. These might
preparation stage in cases where the project involve, for example, a debriefing process with
is sent to a bidding process at the end of the the company’s procurement staff if requested
preparation stage. In such cases the plan for by unsuccessful bidders. Independent audit
procurement could consist of a commitment to processes might also be used to handle
utilise the corporate entity’s procurement plans procurement-related grievances, and processes
and processes, which would then be required to for escalation of grievances may be included in
meet the stated criteria. the relevant legislation.
Livelihoods
Assessment clean water, sanitation, health, education, and
transport. Livelihoods are usually assessed using
Assessment criterion - Preparation Stage: An a mix of quantitative data, such as the number
assessment of issues relating to project affected of individuals pursuing a particular livelihood,
communities has been undertaken with no and qualitative methods such as interviews,
significant gaps, utilising local knowledge. focus groups, and observation to establish
information about the activities and assets
The potential impacts of a hydropower project on on which a livelihood depends. Information
communities and livelihoods should be assessed should be disaggregated by cultural, ethnic,
as part of the Environmental and Social Impact socio-economic, gender, age, education, health,
Assessment (ESIA). Some national requirements location and other characteristics.
may focus more narrowly on environmental
impact assessment, but international good Because project development can take years,
practice also requires a strong focus on social the baseline assessment needs to be carefully
aspects. timed. Populations can move in and out of
project affected areas and the assessment should
Project affected communities should be identified form the basis for support and compensation
with respect to both direct and indirect potential measures. In order to enable fair compensation
impacts. Upstream and downstream communities arrangements, the baseline information needs
must be included as far as flow changes induced to include data on affected households and
by the project can be detected. This may include businesses and their assets at an established
communities in other jurisdictions or countries. registration date or period. The timing of
Communities affected by transmission lines, roads establishment of the baseline should take into
and other associated infrastructure should be account any variations in the conditions that are
included. A concern to be avoided is that those influenced by, for example, seasonal cycles or
members of the community who will be resettled infrequent events (e.g. droughts or floods).
get all of the assessment and compensation
attention. It is essential that those community Once the baseline conditions are established,
members who are not resettled but experience project-related risks to livelihoods, living
direct impacts, secondary or indirect impacts, standards, and economic displacement are
or impacts only after some time has passed identified and the nature and degree of impacts
are identified as part of the project affected analysed. Analysis of gender and vulnerable
communities and that mitigation measures are groups should be included. Community risks
addressed for these impacts. during the construction stage may include the
following:
The studies must establish a baseline of the
households and communities that may be project • Physical displacement (e.g. relocation, loss of
residential land, or loss of shelter). Physical
affected. Social science expertise and recognised
displacement involves risks both for the
social survey techniques should be used to select displaced people and for the host communities
indicators and generate baseline information. As receiving them (see the Resettlement guideline).
far as practically possible, standardised indicators
should be used that are compatible with • Economic displacement (e.g. loss of community
existing official monitoring mechanisms, such forest access, loss of paddy or home garden,
or diminished fisheries). Many issues can be
as the periodic household surveys. Indicators
missed relating to affected livelihood resources
of livelihoods and living standards used for if, as is often the case, there is too narrow a
characterising the baseline should be applicable focus on land acquisition and compensation.
for post-project development comparisons. Living Many livelihood impacts can occur through,
standards are usually assessed using quantitative for example, changes in road accessibility, land
social science methods, such as census and public access, supply chains, or river flow regimes.
health data. Examples of indicators of living • Impacts from worksites and construction
standards include: consumption, income, savings, traffic (e.g. dust and other air emissions, solid
employment, health, education, nutrition, waste, wastewater, noise, vibrations, visual
housing, and access to services such as electricity, disturbances, hazards, access to travel routes,
Livelihoods
resettlement was a secondary impact (from hydropower facility to have mechanisms to detect
delayed bank erosion) and not a primary impact and evaluate if issues relating to the hydropower
(e.g. from reservoir inundation) of the project. facility are arising for the surrounding
The risk of long-term impoverishment for project communities as these can evolve over the many
affected communities is a major concern and decades of operations.
must be fully assessed.
Management
Assessment Management criterion - Preparation Stage:
Assessment criterion - Implementation Stage: Issues Management plans and processes for issues that
relating to project affected communities have been affect project affected communities have been
identified through an assessment process utilising developed with no significant gaps including
local knowledge; and monitoring of project impacts monitoring procedures, utilising local expertise
and effectiveness of management measures is when available; and if there are formal agreements
being undertaken during project implementation with project affected communities these are publicly
appropriate to the identified issues. disclosed.
Livelihoods
so that the approach to support for the most mitigation and compensation may be measures
vulnerable is documented and consistent. to formalise or legalise land titles and/or access
to natural resources, or to provide ways to pursue
Measures to mitigate risks of human-wildlife livelihoods that are not in conflict with national
conflict, in which wildlife is displaced by conservation objectives. These are delicate
project activities or humans displaced by the matters and would require good partnership
project encroach upon wildlife habitat, include: approaches between the project developer
avoidance and minimisation through project and the government to ensure the future and
siting, design and operations; provision of long-term wellbeing of the project affected
alternative habitats for wildlife; employment of communities.
local guards or wardens in high risk areas and
times of day; fencing and other measures to keep An agreement is a recorded understanding
animals from fields and settlements; relocation between individuals, groups or entities to
or hunting of problem animals; compensation follow a specific course of conduct or action. An
of farmers for livestock and crop losses; and agreement would be recognised as formal when
training and education for communities on how in the form of a document signed by recognised
to minimise and manage conflicts. representatives of all parties concerned with
witnesses present or expressed in government
Measures to mitigate risks of a barrier effect licence requirements or court decisions. An
created by the reservoir or any areas with agreement is considered publicly disclosed if
restricted access to land transport include: members of the public can access information
avoidance and minimisation through appropriate on what was agreed if they would like to do so.
project siting, design and operations; bridges; Public disclosure may take place through public
bypass roads; and boats or ferry services. access to the actual document that records
the agreement (either posted on a website,
With all management actions, efforts should distributed, or made available on request to
be made to ensure there is no ‘elite capture’ of interested parties), or public notification via
measures and benefits. a media release or website about the main
provisions of the agreement. If there was a
All of the issues identified in the assessment one-off notification, information may be hard
need to be addressed in the management plans. to access at a later date and an effort should be
Local expertise should be involved in the plan made by the owner/operator to ensure awareness
development. The management plans and of and ease of accessibility of information by
processes for addressing impacts should address stakeholders over time.
how responsibilities have been allocated, the
institutional and financing arrangements for
the implementation of plans, timing objectives, Stakeholder Engagement
monitoring and evaluation mechanisms, and any Stakeholder Engagement criterion - Preparation
handover arrangements with responsibilities Stage: Engagement with project affected
over time. For projects with transboundary communities has been appropriately timed and often
implications, the plans should include two-way; ongoing processes are in place for project
arrangements between jurisdictions. affected communities to raise issues and receive
feedback.
In some cases the pre-project use of natural
resources (e.g. water extraction or hunting) may
Stakeholder Engagement criterion - Implementation
not be recognised formally through land tenure,
and Operation Stages: Ongoing processes are in
water rights or resource use agreements, and
place for project affected communities to raise
may in fact be in conflict with existing national
issues and get feedback.
laws (e.g. protection of threatened species).
Any existing informal arrangements should be
The risks of poor outcomes for project affected
taken into consideration in the assessment using
communities are more acute if communications
local knowledge and captured in the baseline
and cooperation between the affected
data, with the impacts of the project on these
communities, the developer, and government
activities clearly identified. Part of the package of
Livelihoods
Conformance/Compliance Outcomes
Conformance/Compliance criterion - Implementation Outcomes criterion - Preparation Stage: Plans provide
Stage: Processes and objectives relating to project for livelihoods and living standards impacted by the
affected communities issues have been and are on project to be improved, and economic displacement
track to be met with no major non-compliances or fairly
non-conformances, and commitments have been or compensated, preferably through provision of
are on track to be met. comparable goods, property or services.
Livelihoods
This guideline expands on what is Resettlement has been a highly contentious issue
expected by the criteria statements in the associated with hydropower development. It is
Hydropower Sustainability Tools (HST) good practice to avoid involuntary resettlement
for the Resettlement topic, relating to and, when unavoidable, to minimise it through
different project siting and design alternatives
assessment, management, conformance/ during the preparation stage. The intent is that
compliance, stakeholder engagement, the dignity and human rights of those physically
stakeholder support and outcomes. The displaced are respected; that these matters are
good practice criteria are expressed for dealt with in a fair and equitable manner; that
different life cycle stages. livelihoods and standards of living for resettlees
and host communities are improved; and that
commitments made to resettlees and host
In the Hydropower Sustainability communities are fulfilled.
Assessment Protocol (HSAP), this topic
Resettlement is the process of moving people
is addressed in P-14 for the preparation
to a different place to live because due to the
stage, I-10 for the implementation project they are no longer allowed to stay in the
stage and O-10 for the operation stage. area in which they were residing. Resettlees are
In the Hydropower Sustainability ESG those people who are required to be resettled,
Gap Analysis Tool (HESG), this topic is including those who have formal legal rights,
customary or traditional rights, as well as those
addressed in Section 5.
who have no recognisable rights to the land.
Host communities are the existing communities
This guideline is intended to be used as to which resettlees are relocated. Livelihood
additional guidance to that provided on Project refers to the capabilities, assets (stores, resources,
Affected Communities and Livelihoods in the claims and access) and activities required for a
case that resettlement is required by the project. means of living. Living standards refer to the
The resettlement guideline applies to projects level of material comfort as measured by the
that require permanent or temporary physical goods, services, and luxuries available to an
displacement of households, resulting in individual, group, or nation.
relocation due to loss of residential land or loss of
shelter.
The duration of support by a hydropower facility Resettlees and host communities should be
for resettlement can be an issue even when involved in the definition of key elements of
the resettlement baseline and RAP are well- the resettlement plan. For example, resettlees
documented. For example, pressure on land can be involved in proposing resettlement sites
availability can arise as families expand and and can indicate their expectations on layout
the next generation wants to stay in the new arrangements and alternative livelihood activities,
village, and assets in the resettlement village as well as influencing decision-making around
can deteriorate over time. The owner/operator housing options during the negotiation process.
should demonstrate that it is not ignoring the
long-term needs of resettled communities, and Appropriate timing, culturally appropriate, and
it is seeking to understand them and provide two-way processes are important components
support in a measured and reasonable manner. of good practice. ‘Appropriately timed’ means
If all mitigation commitments for resettlement that engagement should take place early enough
have clearly been fully delivered, then further so that the project can respond to issues raised,
support should be provided through new those affected by resettlement have inputs before
initiatives unrelated to mitigation requirements. the project takes decisions, and engagement
Mechanisms for support by the business can is at times suitable for people to participate.
include, for example, a business Corporate Social Resettlement stakeholders should be supportive
Responsibility (CSR) programme or contributions of the timing of engagement activities given the
by the hydropower facility owner/operator to a impact of the decisions involved on the rest of
community fund from which the resettlement their lives. ‘Culturally appropriate’ means that
communities or relevant local governments can methods of engagement respect the cultures of
access financial support for agreed programmes. those affected and allow adequate provisions
Cumulative impacts can also emerge due to to fit with the discussion and decision-making
This guideline expands on what is for potentially affected Indigenous Peoples are
expected by the criteria statements in the in line with those outlined in the Project Affected
Hydropower Sustainability Tools (HST) for Communities and Livelihoods guideline in terms of
establishing a socio-economic baseline, assessing
the Indigenous Peoples topic, relating to risks, analysing the degree and nature of potential
assessment, management, conformance/ impacts, identifying opportunities, and outlining
compliance, stakeholder engagement, impact avoidance, minimisation, mitigation and
stakeholder support and outcomes. compensation measures to be embedded into
The good practice criteria are expressed management plans for construction and operation.
This guideline is focused on supplementary
for different life cycle stages. measures or extra care in approaches that
constitute international good practice in matters
In the Hydropower Sustainability relating to the rights of Indigenous Peoples.
Assessment Protocol (HSAP), this topic
Indigenous peoples refers to a distinct social
is addressed in P-15 for the preparation and cultural group possessing the following
stage, I-11 for the implementation characteristics in varying degrees:
stage and O-11 for the operation stage.
In the Hydropower Sustainability ESG • self-identification as members of a distinct
indigenous cultural group and recognition of
Gap Analysis Tool (HESG), this topic is this identity by others;
addressed in Section 7.
• collective attachment to geographically distinct
habitats or ancestral territories in the project
area and to the natural resources in these
The Indigenous Peoples guideline addresses the habitats and territories;
rights at risk and opportunities of Indigenous • customary cultural, economic, social or political
Peoples with respect to the hydropower project or institutions that are separate from those of the
operating facility. This guideline accompanies and dominant society or culture; and
is additional to that provided on Project Affected
• an indigenous language, often different from
Communities and Livelihoods, to be applied the official language of the country or part of
if there are Indigenous Peoples among these the country within which they reside.
communities. The good practice requirements
This guideline expands on what is The scope of labour and working conditions
expected by the criteria statements in the assessment and management must consider
human resources policies, staff and workforce
Hydropower Sustainability Tools (HST) for planning, occupational health and safety, equal
the Labour and Working Conditions topic, opportunity, staff development and training, and
relating to assessment, management, grievance and bargaining mechanisms. These
conformance/compliance, stakeholder aspects should be considered for both staff of
engagement and outcomes. The good the developer and for staff of contractors, sub-
contractors, intermediaries, suppliers and service
practice criteria are expressed for providers.
different life cycle stages.
Intermediaries are workers engaged through
In the Hydropower Sustainability third parties who are either performing work
directly related to the functions essential for
Assessment Protocol (HSAP), this topic the project for a substantial duration or who are
is addressed in P-16 for the preparation geographically working at the project location.
stage, I-12 for the implementation They are workers involved with the project who
stage and O-12 for the operation stage. are neither employees nor contractors. They
In the Hydropower Sustainability ESG may be appointed as an in-kind contribution
from another agency, for example to provide a
Gap Analysis Tool (HESG), this topic is facilitation role with indigenous communities.
addressed in Section 2. Clarity around the role, responsibilities,
entitlements and accountabilities of these
The labour and working conditions guideline individuals would need to be defined and
seeks to ensure employee and contractor understood.
opportunity, equity, diversity, health and safety.
The intent is that workers are treated fairly and Labour and working conditions should consider
protected. all project-related offices, workshops, storage
areas, worksites, locations of ancillary services
or activities (e.g. quarries, revegetation areas,
Occupational health and safety (OH&S) is a critical Requirements for baseline labour and working
issue for the development and management of conditions information include the following:
hydropower projects. OH&S relates to protecting
the safety, health and welfare of people engaged • All of the aspects listed under the scope of this
in work or employment, for example through guidance are addressed.
preventing disease or injury that might arise • All available sources of secondary data are
as a direct result of workplace activities. OH&S identified and included, including previous
approaches and norms can vary widely from studies, information on labour issues from
country-to-country. In some countries standards comparable projects, national statistics, local
are not high, and while a particular project government information, and from all relevant
may proudly state that higher standards are in institutions.
place than other projects in the region, overall • Local knowledge and information is included,
standards may still be low and workers not safe. including from communities in the project
Poor, partial or inconsistent implementation of affected areas, for example on unemployment,
OH&S policies and plans may also be an area of skills levels, and interest in project-related
weakness. employment.
Preparation stage studies require a high level and
Assessment diversity of contracted and staff labour to: conduct
field investigations, carry out geotechnical drilling
Assessment criterion - Preparation Stage: An
and excavation works; provide hydrographical
assessment has been undertaken of human resource
services; establish monitoring sites; and undertake
and labour management requirements for the
social and environmental baseline studies. At
project, including project occupational health
this stage there may be unique labour issues
and safety (OH&S) issues, risks, and management
associated with the logistics, health, security and
measures, with no significant gaps.
safety of workers working in remote areas with
limited infrastructure (e.g. no roads or limited
For hydropower projects at the preparation stage, communications available).
assessments need to inform workforce planning
for all project stages. These assessments should Labour and working conditions risks at the
establish compliance requirements for the labour implementation stage may include:
force, identify any risks or challenges that have
arisen in relation to the project location, and inform • inadequate or unsafe living conditions in labour
the development of labour policies, plans and camps or individual accommodations
procedures. • hazardous working conditions, including: (i) work
underground, underwater, exposed to landslides
The assessment should address occupational health and rockfall, exposed to floods, working at
and safety issues associated with the preparation, heights, or in confined spaces; (ii) work with
implementation and operations stages, which will dangerous machinery, equipment, or tools, or
differ substantially from each other. The assessment involving handling of heavy loads; (iii) work in
should involve a systematic risk assessment by unhealthy environments exposing the worker
people with appropriate OH&S risk assessment to hazardous substances, agents, processes,
temperatures, noise, or vibration damaging to
expertise and experience with projects of similar
health; (iv) work under difficult conditions such
size and complexity. The assessment should involve as long hours, late nights, inadequate leave,
staff that will be working on the project as they or confinement by the employer; (v) work at
will have the most informed idea of local issues ancillary structures or activities; or (vi) work on
and risks. The assessment should cover all workers roads or through other means of transport
on the project, regardless of whether they are
employees, contractors or intermediaries, as well as
visitors who may or will be on-site. The assessment
• discrimination, harassment, breach of contract, • worker grievances registered and resolved; and
denial of fair treatment, and limited or no access • unemployment levels in local communities.
to effective grievance mechanisms
The exact nature of the monitoring will be
• conflicts between labour and management, or specific to the issue and management measure.
the workforce and the local population For example, there may be a risk of vehicle
Labour and working conditions risks at the accidents with workers walking around the site;
operation stage are essentially the same, but the management measures are that workers are
much easier to assess and manage because of required to wear high-visibility clothing, speed
the comparatively small number of operations limits are established, and there are random
personnel, more permanent accommodation checks by designated personnel of adherence to
facilities, and generally safer workplace activities. clothing requirements and speed limits. Associated
monitoring might include the number of vehicle
Labour and working conditions opportunities accidents with workers walking around the site and
should also be assessed. These may include, for the number of breaches of the clothing and speed
example: provision of local employment and rules each month.
training opportunities, sometimes in remote
project locations; and capacity-building for
hydropower industry professionals.
Assessment
Assessment criterion - Operation Stage: A periodically
updated assessment has been undertaken of human
Assessment resource and labour management requirements for
Assessment criterion - Implementation Stage: Human the operating facility, including occupational health
resources and labour management requirements and safety (OH&S) issues, risks, and management
have been identified through an assessment process, measures, with no significant gaps; monitoring is
including occupational health and safety (OH&S) being undertaken to assess if management measures
issues and risks; and processes are in place to identify are effective; and ongoing or emerging labour
any emerging or ongoing issues, and to monitor if management issues have been identified.
management measures are effective.
Many of the implementation considerations also
Further to the above guidance, at the apply at the operations stage. At the operations
implementation stage, the focus should be on stage, the labour and work conditions issues will
construction-related activities and implementation be centred on operation and maintenance of
of plans. There will be significant occupational assets, monitoring and implementation of plans
health and safety risks requiring management. and programmes, and a diversity of corporate
The construction workforce can be very large for a activities. Assessment activities need to be tailored
number of years and often needs to be brought in to fit the context and involve re-assessments over
rather than drawn from local labour pools, which time as the situation evolves. There is often a lower
can be a cause of safety and security concerns for proportion of contracted labour in the operations
both labourers and local communities.
Good practice requires that employees, contractors, Assessment processes and management measures
sub-contractors, intermediaries, suppliers and relating to labour and working conditions should
service providers are all able to raise issues and be compliant with relevant legal and administrative
concerns through a clearly established and requirements. These may be expressed in licence
functional process. This is effectively one form of a or permit conditions or captured in legislation.
grievance mechanism applicable to employees (as Implemented measures should be consistent with
described in the Communications and Consultation what is in the plans to demonstrate conformance
topic guidance). The business should establish with the plans. Labour commitments may be
indicators to ensure employee grievance processes expressed in policies of the developer or owner/
are accessible and being used, and to check operator, or in company statements made
timeliness of response and closure on issues. publicly or within management plans. Evidence
of adherence to commitments could be provided
Processes by which workers could raise issues through, for example, internal monitoring and
should be well-communicated. Examples include reports, government inspections, or independent
through nominated contact people, a designated review. Variations to commitments should be well-
platform on an internal website for workers, justified and approved by relevant authorities, with
periodic workforce briefings or question/answer appropriate stakeholder liaison.
opportunities, suggestion boxes, complaints
boxes, an employee assistance programme, and/ The significance of not meeting a commitment
or a toll free telephone number. An incident is based on the magnitude and consequence of
reporting system, whistle-blowing mechanism, and that omission and will be context-specific. For
workplace support officers or representatives can example, a failure to demonstrate delivery of a
also be evidence that this criterion is met. licence requirement to provide potable drinking
water to all workers is likely to be a significant
Regular staff and contractor team meetings, non-compliance, as would be unfair dismissal of an
surveys, information sessions, and designated employee in violation of the company’s own policy.
contact people are often used as communication A slight delay in delivery of a monitoring report
processes for raising issues and getting feedback. could be a non-significant non-conformance.
Feedback on issues raised by workers should be
documented and could be demonstrated by means The obligations of contractors, sub-contractors and
such as emails, records of telephone conversations, intermediaries with respect to corporate policies
written correspondence, meeting minutes, and/ versus the contractor’s own policies would need to
or provision of responses to frequently asked be made clear in any contract.
questions on the company website.
This guideline expands on what is and measures are in place to address those
expected by the criteria statements in the identified to be of high importance.
Hydropower Sustainability Tools (HST) Cultural heritage refers to the legacy of physical
for the Cultural Heritage topic, relating to artefacts and intangible attributes of a group or
assessment, management, conformance/ society that are inherited from past generations,
compliance, stakeholder engagement, maintained in the present and bestowed for
stakeholder support and outcomes. The the benefit of future generations. It can be
understood as the objects, places and practices
good practice criteria are expressed for that define who we are. Cultural heritage are the
different life cycle stages. values we want to retain, share and pass on to
future generations.
In the Hydropower Sustainability
Cultural heritage does not refer exclusively to the
Assessment Protocol (HSAP), this topic monumental remains of a culture and includes
is addressed in P-17 for the preparation intangible, ethnographic and social heritage. It
stage, I-13 for the implementation is an evolving concept, reflecting living cultures
stage and O-13 for the operation stage. as well as those of the past. This guideline
focusses on physical cultural resources,
In the Hydropower Sustainability ESG
which are movable or immovable objects, sites,
Gap Analysis Tool (HESG), this topic is structures, groups of structures, and natural
addressed in Section 8. features and landscapes that have archaeological,
paleontological, historical, architectural, religious,
aesthetic, or other cultural significance. Physical
This guideline addresses cultural heritage, with cultural resources may be located in urban or
specific reference to physical cultural resources rural settings and may be above or below ground,
at risk of damage or loss by the hydropower or under water. Their cultural interest may be at
project and associated infrastructure (e.g. new the local, provincial or national level, or within the
roads, transmission lines), or associated with the international community.
hydropower facility. The intent for a hydropower
development is that physical cultural resources Intangible cultural resources are oral traditions,
are identified, their importance is understood, performing arts, social practices, rituals, festive
events, knowledge and practices concerning
Good practice requires that a process of The timing of engagement must allow for
stakeholder engagement has been followed adequate data collection, analysis and reporting.
in the assessment and planning for cultural Cultural heritage stakeholders should be asked
heritage issues in relation to the hydropower to provide information on areas of concern,
project. Directly affected stakeholders for cultural and these should influence the research design.
heritage would be those who recognise and have These same stakeholders should also be asked
responsibilities for the values of the heritage to provide feedback on the significance of finds
recorded for the hydropower project affected and of potential impacts, and this should inform
area. These ‘cultural heritage stakeholders’ should any avoidance, minimisation, mitigation and
be clearly identified in any project stakeholder compensation plans. Local communities may
mapping. They might be stakeholders only for express values for heritage aspects in contrast to
this issue or stakeholders in relation to many the advice of external experts and any conflicts
issues relating to the project. Cultural heritage in views need to be managed with respect
stakeholders might include project affected and sensitivity. Cultural heritage stakeholder
communities as a whole, or a subset of these engagement needs to be undertaken before
(e.g. living in a particular area, and/or indigenous management decisions have been made and
peoples or an ethnic minority group). They should evidence should demonstrably show that these
include the relevant government department such stakeholder views have been sought and taken
as a heritage agency and could include historians, into consideration to inform cultural heritage
researchers, local interest groups, educational management plans.
institutions, and/or curators for museums or
collections. Stakeholder Support
Appropriate timing, culturally appropriate, and Stakeholder Support criterion – Preparation and
two-way processes are important components of Implementation Stages: There is general support
good practice. ‘Appropriately timed’ means that or no major ongoing opposition amongst directly
engagement should take place early enough affected stakeholder groups for the cultural heritage
so that the project can respond to issues raised, assessment, planning or implementation measures.
cultural heritage stakeholders have inputs before
the project takes decisions, and engagement takes Plans for mitigation of cultural heritage issues
place at times suitable for these stakeholders to arising from the hydropower development should
participate. Cultural heritage stakeholders should be generally supported by cultural heritage
be supportive of the timing of engagement stakeholders. Cultural heritage stakeholder support
activities. ‘Culturally appropriate’ means that may be expressed through community members or
methods of engagement respect the cultures of the their representatives, and may be evident through
cultural heritage stakeholders and allow adequate means such as surveys, signatures on plans,
provisions to fit with the discussion and decision- records of meetings, verbal advice, public hearing
making processes typical for them. Stakeholder records, public statements, government licence,
engagement processes that are culturally sensitive and court decisions. No major ongoing opposition
consider, for example, meeting styles, venues, or temporary opposition that was resolved would
facilitators, language, information provision, the satisfy this criterion.
community’s decision-making processes, time
allocation, recording, and follow-up. Engagement
processes for cultural heritage stakeholders should
This guideline expands on what is the Labour and Working Conditions guideline.
expected by the criteria statements in the Hydropower projects also have the potential to
provide improvements in public health facilities
Hydropower Sustainability Tools (HST) and health services, which is closely linked
for the Public Health topic, relating to with project benefits (see the Project Benefits
assessment, management, conformance/ guideline).
compliance, stakeholder engagement
and outcomes. The good practice criteria The intent for public health in relation to the
are expressed for different life cycle hydropower project or operating facility is that:
stages.
• the project or operating hydropower facility
does not create or exacerbate any public health
In the Hydropower Sustainability issues;
Assessment Protocol (HSAP), this topic • any ongoing or emerging public health issues
is addressed in P-18 for the preparation associated with the hydropower facility are
identified and addressed as required;
stage, I-14 for the implementation
stage and O-14 for the operation stage. • improvements in public health are achieved
through the project in project affected areas
In the Hydropower Sustainability ESG where there are significant pre-existing public
Gap Analysis Tool (HESG), this topic is health issues; and
addressed in Section 4. • commitments made by the project to implement
public health measures are fulfilled.
This guideline addresses public health issues
associated with the hydropower project. A broad
view is taken on public health to incorporate
Assessment
anything for which one would seek medical Assessment criterion – Preparation Stage: A public
attention, such as sickness, disease, mental health issues assessment has been undertaken with
health, injuries and fatalities. Guidance on no significant gaps; the assessment includes public
occupational health and safety, i.e. the health health system capacities and access to health
of the labour force, is provided separately in services, and has considered health needs, issues and
risks for different community groups.
• Mitigation measures for public health impacts • Measures to mitigate risks from air, water, and
are listed and the objectives are clearly noise pollution, vibrations, and exposure to
explained. dust and to hazardous materials: provision of
personal protective equipment for vulnerable
• Measures to be implemented have a clear community members, such as face masks, ear
timeline, budget, and responsible parties. plugs, or water filters; and temporary relief to
• Measures are culturally-sensitive, e.g. with vulnerable households if necessary, including
respect to traditional medicines and local beliefs. temporary relocation, to avoid health risks from
more intensive construction-related impacts.
This guideline expands on what is sustainable over the long-term; that biodiversity
expected by the criteria statements in impacts arising from project activities and from
the operating hydropower facility are managed
the Hydropower Sustainability Tools responsibly; and that commitments to implement
(HST) for the Biodiversity and Invasive biodiversity and invasive species measures are
Species topic, relating to assessment, fulfilled.
management, conformance/compliance
and outcomes. The good practice criteria Biodiversity is the variety of life forms (animals,
plants and micro-organisms), their genes, and the
are expressed for different life cycle ecosystems of which they are a part. Biodiversity
stages. is critical to functioning and maintenance of
the natural environment and has recognised
In the Hydropower Sustainability aesthetic, spiritual, cultural, recreational and
scientific values.
Assessment Protocol (HSAP), this topic
is addressed in P-19 for the preparation An ecosystem is a community of living organisms
stage, I-15 for the implementation in conjunction with the non-living components of
stage and O-15 for the operation stage. their environment (e.g. air, water, soil) interacting
as a system. These biotic (living) and abiotic (non-
In the Hydropower Sustainability ESG
living) components are linked together through
Gap Analysis Tool (HESG), this topic is nutrient cycles and energy flows. Significantly
addressed in Section 6. different ecosystems are found in wet versus dry
and hot versus cold areas or regions. A habitat
is an ecological or environmental area that is
inhabited by a particular species of animal, plant,
This guideline addresses the implications of
or other type of organism. The term typically
hydropower projects and operating facilities on
refers to the zone in which an organism lives
biodiversity, ecosystems and habitats, including
and where it can find food, shelter, protection,
specific values or issues frequently associated
and mates and appropriate conditions for
with project development and operations such
reproduction. Examples of various riverine
as threatened species, fish passage, and invasive
habitats include riparian zones (i.e. the shoreline),
species. The intent is that there are healthy,
deep pools, riffles, large woody debris, sand
functional and viable aquatic and terrestrial
bars, gravel bars, backwaters, wetlands, and
ecosystems in the project affected area that are
floodplains.
• Aquatic habitats: river width, depth, gradient, • all identified potential risks and impacts for
current velocity, water quality, substrata biodiversity;
characteristics, instream and riparian vegetation • mitigation measures for all risks and impacts
extent and condition; listed, with objectives and measures of success;
• Terrestrial habitats: extent, condition and • monitoring schedules clearly linked to the risks
community composition; often done with aerial and mitigation objectives;
photo or satellite imagery analysis with ground-
truthing; • reporting schedules and formats;
This guideline expands on what is there may also be a number of social and
expected by the criteria statements in the environmental consequences if these issues are
not managed well.
Hydropower Sustainability Tools (HST)
for the Erosion and Sedimentation topic, This guideline addresses the management of
relating to assessment, management, erosion and sedimentation issues associated
conformance/compliance and outcomes. with the hydropower project or operating
The good practice criteria are expressed hydropower facility. The intent is that erosion and
sedimentation caused by the project or operating
for different life cycle stages. hydropower facility is managed responsibly
and does not present problems with respect
In the Hydropower Sustainability to other social, environmental and economic
Assessment Protocol (HSAP), this topic objectives; that external erosion or sedimentation
occurrences which may affect the project or
is addressed in P-20 for the preparation operating hydropower facility are recognised and
stage, I-16 for the implementation managed; and that commitments to implement
stage and O-16 for the operation stage. measures to address erosion and sedimentation
In the Hydropower Sustainability ESG are fulfilled.
Gap Analysis Tool (HESG), this topic is
Rivers naturally carry sediment loads. These are
addressed in Section 3. typically made up of: bed load, which moves
along the river bottom; suspended load, which is
carried within the water flow throughout the flow
Hydropower projects may fundamentally alter depth (some of which may only be in suspension
the landscape and there are likely to be changes under certain flow conditions); and wash load,
to the pre-existing erosion and sedimentation the portion of the suspended load typically of
patterns in the affected river system. Not only relatively fine material that is transported entirely
can erosion and sediment issues have strong through the system without deposition. Saltation
implications for the longevity of the hydropower refers to when particles on the bed are lifted into
installation and the maintenance costs, but suspension and fall back to the bed.
Erosion
works, drainage and settling ponds, catchment
and conditions (e.g. water depth, slope and treatment and erosion prevention works,
velocity), and the source of sediments affect the rehabilitation works in disturbed areas, desilting
river’s sediment load and how it is mobilised or chambers, sluice gates, reservoir flushing
where it is deposited. Sediments may be dropped strategies, dredging programmes; and
out by the river due to a reduction in river flow, • locations of other mitigation measure areas
an increase in-channel width, lower current and activities – e.g. reforestation activities, local
velocities, or break of slope; these dropped benefits in relation to erosion and sedimentation
sediments may form alluvial or flood plains. issues.
There are many terms for different types of fluvial
bedforms and landforms, including bars, pools, Assessment
riffles, meanders, oxbow lakes, fluvial terraces,
and islands. Fluvial channels (i.e. river or stream Assessment criterion - Preparation Stage: An
courses) have reaches or lengths of a common erosion and sedimentation issues assessment has
character that can be categorised as straight, been undertaken with no significant gaps; the
meandering, or braided. Anastomosed rivers assessment identifies impacts that may be caused
consist of multiple channels that could be either by the project, issues that may impact on the project,
straight, meandering, braided or a combination and establishes an understanding of the sediment
of these three channel planform types (an load and dynamics for the affected river system.
anastomosed river is considered a landform
feature but not a channel type in itself ). River The project Environmental and Social Impact
morphology is a dynamic process, with change Assessment (ESIA) should include evaluation
occurring over time, and is not one stable or static of the erosion and sediment related impacts of
condition. a hydropower project. A systematic approach
needs to be taken to identifying and evaluating
The geographic scope of erosion and sediments erosion and sediment status and potential
assessment and management must consider: impacts and risks from the proposed project.
Professionals working in this area might include:
• the catchment area for the reservoir in relation to hydraulic engineers, which is a specialty area
sediment yields;
of civil engineering focussed on the flow and
• the reservoir in relation to reservoir slope conveyance of fluids and sediments including
stability and reservoir sediment accumulation; the design and effects of hydraulic structures
• downstream river reaches below the dam and (e.g. bridges, canals, levees); and fluvial
power house in relation to concentrations and geomorphologists, which is a specialty area
loads for sediments in suspension, saltation and of geography focussed on the response of the
bed load as well as channel geomorphological landscape to water movement.
conditions in the river reaches that will be
affected by the project, as far downstream as the Alongside the ESIA, the feasibility studies and
flows are significantly project affected, and the detailed design report for the project will also
implications of changes for other river values address the technical risks relating to sediments.
and uses;
Liaison between the engineering and the
• the construction areas – e.g. reservoir environmental studies should be ensured so that
preparation works, dams (coffer, main, saddle), data and analyses are coordinated and consistent
adits, tunnels, power house, mitigation measures and provide information for both areas of need.
(e.g. a fish passage facility) – to determine the
potential erosion and sedimentation issues; The preparation stage assessment starts by
• locations of ancillary structures and activities establishing of the pre-project baseline. Studies
– e.g. labour camps, offices, concrete batching should establish the current sedimentation
plants, water-supply intakes, material fabrication regime and dynamics of the river to help
areas, supply storage areas, quarries, waste determine possible assessment approaches.
disposal areas, supply transport activities; Baseline studies should utilise appropriate
• locations of erosion or sediment-specific expertise for the erosion and sediment sampling
mitigation measures – e.g. slope stabilisation design, data collection, data analysis and
During the preparation stage, sampling data The assessment of erosion and sediment related
should be collected over a period of at least 12 risks during construction should include the
months. The number and timing of sampling effects caused by: erosion and sediment run-
trips should be designed to obtain the most off created by direct disturbance of land during
representative data given the factors that construction activities; landslips caused by
could influence the result. For river sampling, road works, excavations and blasting; sediment
this should cover all seasonal conditions of the run-off from excavated waste dumps (i.e. spoil)
region. Timing of sample collection should be and topsoil storage areas; erosion due to poor
sure to capture very different flow conditions drainage design or maintenance; gullying caused
Erosion
drainage areas; instream changes to channel include numerical models, physical models and
geomorphology due to changes to flows or trapping efficiency assessments. The pattern
sediment movement during construction; and distribution of sediment deposition in the
instream changes to channel geomorphology due reservoir needs to be predicted and linked to
to dumping of excavated materials into or close planning for the live storage over the long-term.
to waterbodies or direct disturbance by heavy It should not be assumed that all sediments will
machinery; and increased sediment run-off into be deposited in the deepest available volume, nor
rivers or streams at vehicle crossing points (e.g. that reservoir life corresponds to sedimentation
bridges, fords). of the dead storage, as patterns of sedimentation
tend to be more complex in practice.
Reservoir filling and project commissioning stage
erosion and sediment risks should include the Erosion and sedimentation opportunities
implications of changed flow regimes on erosion should be identified where possible. These
and sediments in the downstream river and any may include: improvements to pre-existing
potentially adverse impacts, e.g. due to reduced erosion and sedimentation issues in the project
flows or intermittent discharges of sediment- vicinity; improvements to land use planning
laden water. (e.g. retention of forest cover); use of new
technologies, such as for monitoring, slope
The assessment of erosion and sediment related treatment or rehabilitation; use of new land use
risks during operation should include the practices, such as crop rotation, crop choice, or
effects caused by: sediment accumulation in ploughing techniques; and partnerships with
the reservoir over time from catchment sources; community catchment protection or waterway
erosion of the reservoir rim due to steep slopes health monitoring groups.
and/or loss of stabilising vegetation; releases
of sediment-laden water through the low
level release valve or through flushing of the
Assessment
desilting chamber causing issues downstream; Assessment criterion - Implementation Stage:
riverbank or bed erosion due to ‘aggressive Erosion and sedimentation issues relevant to project
river’ or ‘hungry water’ effects (meaning that implementation and operation have been identified
the river’s erosive capacity below the dam is through an assessment process utilising appropriate
enhanced due to sediment being trapped within expertise; and monitoring is being undertaken during
the reservoir); riverbank or bed erosion in rivers the project implementation stage appropriate to the
subject to hydropeaking due to rapid water level identified issues.
changes; riverbank or reservoir rim erosion due
to rapid draw-down of saturated banks leading Assessment criterion - Operation Stage: Ongoing or
to bank slumping; localised riverbed sediment emerging erosion and sedimentation issues have
accumulation due to lower flows at points where been identified, and if management measures are
sediments continue to enter the river; and required then monitoring is being undertaken to
ongoing erosion issues from a lack of, or poorly assess if management measures are effective.
implemented, rehabilitation measures on land
disturbed during construction activities. Erosion and sediment related issues
determination during the implementation and
The implications of long-term temporal changes operation stages should be based on changes to
to flows and to extreme weather events, the baseline erosion and sediment condition and
potentially induced by climate change impacts, processes that may be or have been incurred, as
should be considered in the assessment of well as the implications of these for other social,
erosion and sedimentation. Significant changes environmental and/or economic objectives.
in flow arising from more intense weather events
can create additional risks relating to erosion, Consideration of what is an issue needs to
sediment movement, bank collapse, landslides take into account that there will be landscape
and mudslides. These can, in turn, have public adjustments brought about by the hydropower
safety implications. project that continue for many years until a
Erosion
implemented at the end of the disturbance rivers or streams at vehicle crossing points
activities. (e.g. bridges, fords): vehicle crossing points
• Mitigate landslips caused by road works, on streams or rivers are designed to minimise
excavations, and blasting: land stability is creation of erosion and sediment run-off,
assessed through geotechnical evaluations e.g. through location, gradients of approach,
during the feasibility studies to inform planning surface sealing, drainage.
of construction activities and potential risks; Measures to address erosion and sediment risks
slope stabilisation works are implemented and impacts at the operation stage could include
where needed; exclusion zones are created and some of the following:
signage employed to warn of worker and public
safety risks; work in areas prone to landslip • Mitigate sediment accumulation in the reservoir
risk is subject to appropriate safety measures; over time from catchment sources: Avoidance
landslips are treated quickly to stabilise and and minimisation: catchment protection,
repair. catchment reforestation, landslip prevention
• Mitigate sediment run-off from spoil dumps measures, sediment check dams, strict
and topsoil storage areas: sediment, spoil and rules on land disturbance in the catchment,
soil storage areas are identified through careful erosion treatment measures, sediment bypass
planning and used according to their capacities; structures. Management: density-current
compaction (where appropriate), bunding, venting (diverting flows within the reservoir
drainage and covers are used when required; carrying higher sediment loads out through
downstream settling ponds are used as needed. diversion tunnels, often combined with
desilting chambers); sediment pass-through
• Mitigate erosion due to poor drainage design or structures (e.g. sluice gates or low level outlets
maintenance: drainage is planned at the outset often left open for the first part of the rainy
for all potential erosion areas according to season to allow release of relatively higher
engineering standards; drainage is maintained sediment concentrations and accumulated
to specified standards; instances of erosion are sediments); sediment flushing (through bottom
treated promptly and incorporate measures for outlet gates used during reservoir draw-down);
avoidance of future incidents. dredging and transport downstream (e.g. by
• Mitigate gullying caused by water discharge barge or pipeline).
points or concentrated drainage areas: water • Mitigate erosion of the reservoir rim due
discharge or concentrated drainage points to steep slopes and/or loss of stabilising
are designed to prevent gullying, for example vegetation: restrictions to reservoir water level
through cement linings and slope protection change magnitude or rates; reservoir slope
works. treatment works; promotion of vegetation
• Mitigate instream changes to channel growth tolerable of water level changes on
geomorphology due to changes to flows or reservoir rim; restrictions to activities on the
sediment movement during construction: reservoir causing wave action and on the
downstream effects of flow changes or reservoir rim causing disturbance.
sediment transport changes are monitored • Mitigate releases of sediment-laden water
and residual flow releases made as needed to through the low level release valve or through
address sediment through-flow needs; channel flushing of the desilting chamber causing
stabilisation works. issues downstream: management plans and
• Mitigate instream changes to channel risk assessments for sediment-laden discharges
geomorphology due to dumping of excavated below the dam; timing of releases avoids
materials into or close to waterbodies or direct periods of high sensitivity to downstream
disturbance by heavy machinery: dumping ecosystems; releases planned when dilution
of excavated materials in watercourses is effects from tributaries can be provided.
prohibited and fines are issued if this practice • Mitigate riverbank or bed erosion due to
occurs; permits according to the approved ‘aggressive river’ effects: sediment bypass
construction plan; controls to manage erosion structures (in suitable conditions) to
and sediment into the downstream river (e.g. periodically divert sediment-laden water past
through settling ponds).
Erosion
publicly or within management plans. Evidence and compensate negative erosion and sediment
of adherence to commitments could be provided impacts from project activities, it should be
through, for example, internal monitoring and possible to directly link mitigation measures
reports, government inspections, or independent to all identified erosion and sedimentation
review. Variations to commitments should issues and risks. The assessment and planning
be well-justified and approved by relevant should be informed by appropriate expertise.
authorities, with appropriate stakeholder liaison. The assignment of responsibilities and resource
allocation for implementation, monitoring and
The significance of not meeting a commitment evaluation should be appropriate to the planned
is based on the magnitude and consequence of actions.
that omission and will be context-specific. For
example, a failure to install a sediment flushing An evidence-based approach should demonstrate
mechanism required as a licence commitment is that negative erosion and sediment impacts
a significant non-compliance, whereas a slight arising from project implementation and
delay in delivery of a monitoring report could be operation activities are avoided, minimised,
a non-significant non-conformance. mitigated and compensated with no significant
gaps. The developer and owner/operator should
demonstrate that responsibilities and budgets
Outcomes have been allocated to implement erosion and
Outcomes criterion - Preparation Stage: Plans avoid, sediment plans and commitments. Monitoring
minimise and mitigate erosion and sedimentation reports and data in the implementation and
issues arising from project activities and erosion and operation stages should clearly track performance
sedimentation issues that may impact on the project against commitments and objectives, and
with no significant gaps. capture erosion and sediment impacts. It should
be possible to provide examples to show how
identified risks from the assessment were avoided
Outcomes criterion - Implementation Stage: Erosion
or minimised. It should also be possible to table
and sedimentation issues during project
evidence to show that mitigation plans have
implementation are avoided, minimised and
been implemented and are being monitored.
mitigated with no significant gaps.
Implementation of measures for erosion and
sediment, such as bank protection works,
Outcomes criterion - Operation Stage: Erosion and sediment check dams or retention ponds, and
sedimentation issues are avoided, minimised and sediment flushing or bypass mechanisms, should
mitigated with no significant gaps. be evident, and monitoring should show how
they are achieving their stated objectives.
Noise, air quality and vibration • Relevant existing regional waste management
facilities, activities and capacities are identified
Objectives for noise, air quality and vibration and evaluated in consultation with government
assessment and management are to ensure that authorities with respect to the different waste
there are no adverse effects for surrounding streams. The evaluation should consider if
communities, biodiversity or other values created these can be used or enhanced, or if the project
should develop its own facilities. Evaluations of
by implementation stage activities of the project.
existing facilities should include understanding
The scope of noise, air quality and vibration of responsibilities, permits, tracking systems,
assessment and management must consider: and waste transport operators. If project-specific
facilities are needed, the assessment process
• All project-related activities both on and off the should evaluate the long-term options (e.g.
project sites, including road works. closure or hand-over to local authorities).
• Air emissions from point sources, fugitive sources • Primary data (i.e. sampling) and secondary data
and mobile sources. (i.e. reports) are collected for existing waste
• The activities of primary suppliers. disposal sites intended to be used by the project
to understand capacities and any existing issues,
• The proximity of sensitive receptors, including in such as the quality of run-off. The methodology
the natural and the human environment. used for primary and secondary data capture is
described.
Assessment • Areas are identified for potential disposal of
all types of waste and evaluated based on the
Assessment criterion - Implementation Stage: Waste, particular characteristics of each waste type and
noise and air quality issues relevant to project on social, environmental and financial criteria.
implementation and operation have been identified
through an assessment process utilising appropriate • Waste management and disposal risks at the
construction stage should be identified and can
expertise; and monitoring is being undertaken during
arise due to:
the project implementation stage appropriate to the
identified issues. • Underestimations of waste quantities and poor
planning for waste disposal. This can lead to
increased costs, time delays and potentially non-
The Environmental and Social Impact Assessment compliance issues while reactive management
(ESIA) should include content on waste measures are implemented.
management, and on noise, air quality and
vibration. All compliance requirements should be
• Inappropriate separation, storage, transport and
disposal of chemical, hazardous and medical
well-identified. Baseline data should be collected wastes, leading to toxic chemicals in water and
to understand the pre-project status and project- soils and occupational and public health risks.
related impacts and to inform risk assessment
and development of management plans. All • Inappropriate disposal and management of solid
wastes. This can lead to wind-blown litter, poor
implications for other social, environmental and/
water quality in the run-off, attraction of pest
or economic objectives should be identified species, visual impacts, and public health risks.
and evaluated. Monitoring activities included
• Improved regional waste transport and disposal • Primary air quality and noise data (i.e. sampling)
facilities compared to pre-project conditions, if is collected from locations which are meaningful
agreed with local authorities. in relation to the receptors of concern and where
future complaints might be made, and are in
• Use of new monitoring or treatment areas where the construction stage monitoring
technologies, such as high temperature can be compared.
incinerators for hazardous wastes or
instrumentation to monitor the stability of spoil • Air quality and noise sampling data is collected
dumps. for the different seasons and is collected at
different times of day and night according to
• Creation of new land-use areas such as standard methods. The methodologies used
sports grounds through well-planned and for primary and secondary data capture are
implemented landfill with adherence to relevant described.
soil quality standards.
This guideline expands on what is and there should be evidence that the flow
expected by the criteria statements in the regimes meet publicly disclosed objectives and
commitments.
Hydropower Sustainability Tools (HST)
for the Downstream Flow Regimes topic, A river’s flow naturally varies and has a
relating to assessment, management, characteristic pattern. The flow regime can be
conformance/compliance, stakeholder characterised according to many aspects, such
engagement and outcomes. The good as flow magnitude, duration, frequency, timing,
rates of change, and predictability. The flow
practice criteria are expressed for regime sustains the ecology of rivers and where
different life cycle stages. relevant their associated floodplains, wetlands,
groundwater dependent ecosystems, and
In the Hydropower Sustainability estuaries. The flow regime supports the ecological
processes and associated values that rivers
Assessment Protocol (HSAP), this topic provide to communities and the environment,
is addressed in P-23 for the preparation including: flood attenuation; water purification;
stage, I-20 for the implementation sediment flushing; channel and habitat
stage and O-19 for the operation stage. maintenance; nutrient dispersion; water supply;
In the Hydropower Sustainability ESG wastewater dilution; electricity generation;
and the production of fish and other foods and
Gap Analysis Tool (HESG), this topic is marketable goods.
addressed in Section 11.
Hydropower developments result in changes to
various aspects of the flow regime depending
Good practice requires that flow regimes on the project design and operational patterns.
downstream of hydropower project infrastructure These changes relative to the pre-project
should be planned and delivered with an hydrological regime can be, for example,
awareness of and measures incorporated to seasonally reduced flows, seasonally increased
address environmental, social and economic flows, rapid (i.e. hourly) increases and decreases
objectives affected by those flows. Objectives in flows due to hydropeaking, loss of or changes
should reflect important river uses, values and to flood events, and large flow events due to
services. All affected river reaches downstream of spill. For base load stations, discharges can be at
hydropower infrastructure should be considered a consistent flow for long periods; for peaking
This guideline expands on what is and that it is resilient to the effects of climate
expected by the criteria statements in change and contributes to wider adaptation to
climate change.
the Hydropower Sustainability Tools
(HST) for the Climate Mitigation and Climate change, as defined by the
Resilience topic, relating to assessment, Intergovernmental Panel on Climate Change, is
management, conformance/compliance, a change in the state of the climate that can be
stakeholder engagement and outcomes. identified by changes in the mean and/or the
variability of its properties, and that persists for
The good practice criteria are expressed an extended period, typically decades or longer.
for different life cycle stages.
Mitigation
In the Hydropower Sustainability
Climate change mitigation is defined as human
Assessment Protocol (HSAP), this topic intervention to reduce the sources or enhance
is addressed in P-24 for the preparation the sinks of GHG and other substances which may
stage, I-21 for the implementation contribute directly or indirectly to climate change.
stage and O-20 for the operation stage. For hydropower, climate change mitigation
potential rests in the ability to provide clean
In the Hydropower Sustainability ESG
energy with lifetime low GHG emissions.
Gap Analysis Tool (HESG), this topic is
addressed in Section 12. Hydropower developments can contribute to
reducing grid emissions by displacing fossil
fuel generation and improving the feasibility
of variable renewables through grid reliability
This guideline addresses the estimation and services: flexible generation, ramping capability
management of the project’s greenhouse gas and energy storage. Nonetheless, the decision
(GHG) emissions, analysis and management of to significantly alter a river catchment by
the risks of climate change for the project, and introducing a reservoir is not one to be
the project’s role in climate change adaptation. taken lightly. The flooding of terrestrial land
The intent is that the project’s GHG emissions are dramatically alters the natural state of the
consistent with low carbon power generation, catchment and with it, the natural GHG cycle.
Governed by Published by