You are on page 1of 12

Hall, B E, 2005. Ninth Underground Operators’ Conference, Perth WA 7-9 March.

A Quantitative Assessment of the Factors


Influencing the Shaft Versus Trucks
Decision
By B E Hall 1

Abstract
As near-surface underground mines progress deeper, the inevitable question is whether to convert
from truck haulage to shaft hoisting. The desire to defer capital expenditure frequently delays
investigation of the shaft option, or deferral of a decision to start shaft sinking, unless the shaft option
is clearly significantly better than trucking. By the time increasing depth makes trucking uneconomic,
there may then be insufficient resource remaining to justify a shaft, and the mine must close.
However, had the shaft been built earlier, its lower operating costs would have permitted the mine to
continue to greater depths.

This paper presents a methodology for investigating the shaft versus trucks decision. As well as the
typical analysis of which option is preferable at the time the analysis is conducted, the process
presented illustrates how the timing of the decision to sink a shaft is critical. The paper shows how to
identify the latest date at which the decision to sink a shaft can be made, after which time the shaft
option will not be economic. It also illustrates how to assess the resource that may be required to
justify the shaft. Considering this in conjunction with the latest decision date, implications for the
company’s exploration program are discussed.

Introduction deferred beyond this point, the smaller the resource available to
pay for it, and the lower the overall return of the mine. This
Near-surface underground mines, often as extensions of an paper describes a methodology for identifying how product
open pit, typically commence production with truck haulage for prices may influence the economic limit of mining with and
ore handling. Even if the resource is known to be of sufficient without a shaft, and, whether a shaft is viable or not, how the
size and quality to support a shaft, the desire to defer capital value of a shaft diminishes with deferral and when it becomes
may often lead to trucking initially. As the mine progresses uneconomic. It also indicates how the resource required to
deeper, the inevitable question is whether to convert from truck justify a shaft ahead of the current mining front will vary, in
haulage to shaft hoisting. The desire to defer capital particular increasing rapidly as the date of the shaft installation
expenditure frequently delays investigation of the shaft option, is deferred as long as possible.
or deferral of a decision to start shaft sinking, unless the shaft
option is clearly significantly better than trucking. By the time The examples are in the context of underground metalliferous
increasing depth makes trucking uneconomic, there is often mines, though similar situations no doubt exist in other sectors
then insufficient resource remaining to justify a shaft, and the of the industry. The challenge for mine technical and
mine must close. However, had the shaft been built earlier, its managerial staff is to identify where these types of things are
lower operating costs would have permitted the mine to happening in their operations, and to address the culture and
continue to greater depths. Frequently, in order to minimise attitudes that allow them to continue to occur.
exploration expenditure, the resource is insufficiently identified
at various stages of the mine’s life to allow rigorous evaluation Hypothetical Case Study Operation
and justification of a shaft, but in retrospect, with improved
knowledge of the resource from ongoing exploration, it A hypothetical mining operation has been used to illustrate this
becomes evident that a shaft could have been justified earlier, paper. The key underlying assumptions and input data are
had the knowledge been available earlier. The mine closes described below. The data does not represent any one mine, but
earlier than it could have, returning less to its owners than it is typical of a number of operations. Cost data in the tables are
could have done. generally typical of a number of operations of this type, though
some values have been set in order to demonstrate the
Simplistically, a shaft should not be sunk earlier than when principles involved. The results described should therefore be
production is at the depth where truck haulage costs become seen as indicative of the general nature of the results obtainable
more expensive than shaft operating costs, and there must then by such studies, and should not be taken to represent real
be sufficient reserves remaining for the lower operating costs to economic rules of thumb for current mining operations.
pay for the shaft development. Clearly the longer a shaft is
Figure 1 shows a schematic cross-section of the hypothetical
resource and infrastructure development.
1. Principal Mining Consultant, AMC Consultants Pty Ltd,
12/179 North Quay, Brisbane QLD 4000
E-mail: bhall@amcconsultants.com.au
A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

The hypothetical resource metres (‘vm’) ahead of the production front, but will finish 20
metres below the lowest production level for provision of a
The resource modelled starts 250 m below surface, is steeply sump. If a shaft is sunk, the decline is required to be at the level
dipping and is well known down to a depth of 700 m, 300 m of the shaft bottom 1.5 years before shaft commissioning.
below the current production front at 400 m depth. This is the
Measured and Indicated Resource (and Proved and Probable Haulage out of the mine is either by ‘trucking only’, with all
Reserve), and it consists of 25 000 tonnes per vertical metre rock hauled directly from where it is produced to surface, or by
(‘t/vm’) at 3.5 g/t Au. An Inferred Resource exists down to 900 ‘trucking plus shaft hoisting’ (also referred to as ‘trucking plus
m, 500 m below the current production front, since widely shaft’ or the ‘shaft option’). With trucking plus shaft hoisting,
spaced drill holes have intersected similar mineralisation down rock is trucked to surface until the shaft is commissioned.
to that depth. This zone is also assumed to consist of 25 000 Thereafter, rock generated from the depth of the production
t/vm at 3.5 g/t Au. The resource is open at depth and front down to the level of the truck tip is assumed to be tipped
exploration potential extends below 900 m to an unknown into passes on the production level and gravitate via the passes
depth. This is also assumed to be 25 000 t/vm at 3.5 g/t Au. In a to the shaft skip-loading facilities with no trucking occurring,
real study, more detailed information for tonnage and grade for while rock generated below the depth of the truck tip is trucked
smaller depth increments can of course be modelled. up to that elevation.
Infrastructure and operating physical parameters The shaft loading station is to be 1000 m below surface: it is
The orebody is assumed to be mined by a method that has a assumed that by the time the shaft is sunk, additional reserves
single mining front advancing downwards (such as sublevel will have been proved below the current limits of knowledge at
caving or uphole retreat). The mill capacity, and hence the 900 m depth. The truck tipping point is 50 m above the loading
production target, is 1.0 Mtpa, but a vertical advance rate of 50 station, and the shaft bottom 50 m below. The shaft
vertical metres per year (‘vm/yr’) is not to be exceeded. With construction period is two years and the shaft starts hoisting
the resource data specified above, mining will progress at 40 when the production front is at a depth of 650 m.
vm/yr.
Metallurgical recovery for current operations is 95 per cent, and
The main access and trucking decline can advance at a this is assumed to continue for the life of the operation.
maximum rate of 150 m per month and has an effective overall
gradient of 1:8. The decline face is at 600 m. It is planned that
the decline should generally maintain a lead of 100 vertical

Figure 1 - Schematic cross-section of hypothetical operation.

AMC Reference Library – www.amcconsultants.com.au 2


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

Financial and economic parameters Are trucking only or trucking plus shaft hoisting down to the
bottom of the current Inferred Resource at 900 m depth. For
The financial and economic parameters used in the analysis are completeness, though it will almost certainly be uneconomic,
shown in Table 1. It can be seen that a number of these have trucking plus shaft hoisting down to the bottom of the current
been entered in such a way as to permit or facilitate flexing of Reserves at 700 m depth is also evaluated. Although the nature
the physical parameters. For example, varying the shaft depth of the mineralisation suggests that the Inferred Resource
will result in changes to both the capital and operating costs. continues at 25 000 t/vm, analyses will be done for both that
Also, the time specified for no capital spending at the end of the and a conservative estimate of 60 per cent of that value, being
mine’s life will take cognisance of the calculated life of the 15 000 t/vm.
mine and adjust sustaining capital expenditure accordingly.
Winder and headframe costs have, however, been entered as Table 2 shows the after tax NPV for the six cases evaluated. It
single values only. If it were desired to vary the production can be seen as expected that there is no value from sinking a
capacity of the shaft significantly, it would be necessary to have shaft to start when production is at 650 m depth if the reserve to
capex data that supported that level of analysis. be ultimately mined only continues to 700 m. Mining down to
900 m adds some $9 M of NPV with trucking only if the
Traditional Analyses of Alternatives resource continues at 25 000 t/vm, and a shaft adds a further $2
M of NPV. If the Inferred Resource only converts to Reserve at
Typically, analyses of truck versus shaft hoisting evaluate what the conservative rate of 60 per cent or 15 000 t/vm, continuing
is known at the time of the analysis. In the hypothetical case production below 700 m is not warranted, and the shaft option
developed, one option is clearly trucking only down to the has an NPV some $5 M less than that for trucking only.
bottom of the current Reserves at 700 m depth. The alternative Interpolating linearly between the values in the table indicates
strategies that the Inferred Resource needs to convert to Reserves of some
17 300 t/vm with trucking only, and 19 200 t/vm with the shaft
Table 1 - Financial and economic parameters. option, for mining below 700 m to be economic, while 22 200
t/vm is required for the shaft option to break even with trucking
Gold price $550 $A/oz only.
Gold price inflation rate 1.50% /year A typical analysis would also involve what is often referred to
Capital costs as a ‘sensitivity analysis’, whereby certain key data parameters
Decline development $3500 /metre are varied by certain percentages above and below their base
case values, and the results plotted. Figures 2 and 3 show
Shaft sink and equipment $25 000 /metre
typical sensitivity plots for the effect on after tax NPV of
Winder, headframe, etc $10.0 M changes in gold price and operating costs, for the trucking only
General sustaining capital $2.50 /tonne produced and trucking plus shaft options down to 900 m, for 25 000 and
Shaft sustaining capital $1.00 /tonne hoisted 15 000 t/vm, and in both cases compared with trucking only
down to 700 m.
No Capex in last three years
Capital cost inflation rate 2.50% /year (excluding decline
As expected, increasing gold price leads to increasing NPV,
development)
and increasing costs lead to reducing NPV. Unfavourable
Operating costs variations of the order of 15 -25 per cent for both price and cost
Mining fixed costs $10.0 M /year result in NPVs approaching zero. With trucking only,
Mining variable costs $10.00 /tonne produced continuing down to 900 m becomes better than stopping at 700
m as the gold price increases through 90 per cent of the base
$2.00 /tonne.km produced
case price with a 25 000 t/vm reserve, and at approximately 104
Shaft fixed costs $1.0 M /year per cent of base case with 15 000 t/vm. With a shaft, the
Shaft variable costs $1.00 /tonne hoisted corresponding prices are approximately 89 per cent and 113 per
$1.00 /tonne.km hoisted
cent of the base case. Similar analyses can be done for the
break-even points for changes in operating costs.
Mill fixed costs $4.0 M /year
Mill variable costs $3.00 /tonne milled
Administration fixed costs $5.0 M /year
Operating cost inflation rate 2.00% /year (also applied to decline
development)
Discount rate before tax 10.00% /year real
Discount rate after tax 8.00% /year real

Table 2 - After tax NPVs of typical options evaluated.

Mining the Reserve only (down Mining the Reserve and Mining the Reserve and Resource at 15 000 t/vm (down
to 700 m) Resource at 25 000 t/vm (down to 900 m)
Trucking only $52.8 M $61.5 M $50.2 M
Shaft hoisting below 650 $35.3 M $63.4 M $45.2 M

AMC Reference Library – www.amcconsultants.com.au 3


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

Figure 2 - Sensitivity of after tax NPVs – trucks only. FIG 3 - Sensitivity of after tax NPVs – trucks plus shaft.

Figure 3 – Sensitivity of after tax NPVs – trucks plus shaft

This type of analysis provides some insights, but is often depth as defined by maximum NPV after tax will typically be
simplistic and of limited value for strategic decision-making. In less than the operating cost break-even depth. The type of
some analyses, it is implicitly assumed that mining is economic sensitivity analysis shown above typically does not take any
down to the known Base of the Resource, which may not be account of changes in economic limits to depth with changes in
true. In other cases, simple operating break-even depths for the the parameters being varied.
limits of trucking may be calculated for both trucking only and
trucking plus shaft. These calculations are typically done for the In a case such as this, a typical decision would be that a shaft
base case data only, and the limits identified define the reserves cannot be justified with the present knowledge of the resource,
and resources used for further evaluations. They often do not and trucking will continue. Exploration may or may not
take account of other cash flow timing effects. The optimum continue, and another evaluation of the shaft alternative may

AMC Reference Library – www.amcconsultants.com.au 4


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

not be undertaken until another exploration drilling program The model has been constructed in such as way as to enable the
has been conducted, at which stage the production front will flexing of any number of data input variables in any desired
have moved down. Exploration is often extended merely to combinations and to report the resulting values of any number
maintain a minimum tonnage of reserves and resources ahead of output variables (up to limits imposed by the maximum
of production, and the depth of the limits of knowledge of the number of rows and columns allowable in a worksheet in
resource beyond the current mining front are therefore typically Microsoft ExcelTM). For example, in the model as used for this
no greater than when the previous shaft evaluation was done. study, results were extracted for net undiscounted cash flow
The results of future shaft versus trucks studies will therefore (‘NCF’) and net present value (‘NPV’), both before and after
frequently be the same as before. This cycle will repeat, and a tax, for scenarios with trucking only, or trucking plus shaft
shaft will never be able to be justified, until the economic limits optioning. As the main purpose of this paper is to discuss the
of truck haulage are reached and the mine must close. results obtained, detailed modelling techniques are not
discussed further.
An Alternative Evaluation Methodology
All results discussed are for after tax NPV, unless otherwise
Construction of the evaluation model noted.

A simple hypothetical model has been constructed in Microsoft Use of the model
ExcelTM to evaluate a range of options. It allows substantially
more information to be provided for strategic decision-making For the results reported in this paper, the main parameter varied
than a traditional analysis. All the numerical values in the data in the analyses is the ultimate depth of the mine, in order to
described for the hypothetical operation can be altered and the identify the optimum depth both with and without a shaft, and
model will automatically take account of the changes in the to assess the impact on changes in other parameters on those
physical schedule generated. and other relationships. Other parameters varied are:

A key variable in the logic of the model is the changing depth • gold price;
of the production front, which as noted above, is currently at • the tonnes per vertical metre in the Inferred Resource
400 m. By considering the reserves, production rate and vertical and Exploration Potential regions below 700 m and
advance rate, this can easily be converted to a time-scale for the 900 m depth respectively;
various physical activities. The ultimate depth of the mine also • the depth of the production front when shaft hoisting
affects the model calculations. If specified as a depth less than starts; and
the base of the Reserve (700 m) or Inferred Resource (900 m),
the material to be mined will be truncated at that specified • the duration of any break in production between
ultimate depth, overriding the specified boundaries of these trucking only and shaft hoisting if the Economic
regions. If set deeper than the base of the Inferred Resource, Depth of trucking only is exceeded.
mining is assumed to continue down to the specified depth
using the tonnage and grade specified for Exploration Potential The following sections describe these evaluations and how they
in the input data. may be used for improved strategic decision-making.

The model has been constructed so that changes in any of the Definitions
data entry items will be correctly reflected in the physical
schedules, including in particular such key cost drivers as In the discussions below, several terms are used with specific
production tonnes and grades, decline development, truck and meanings, as follows.
shaft tonne.kilometres and the timing of shaft construction. The
input parameters for the size and final depth of the resource and Base of the Resource
reserve mined, and the mining rate targets and constraints, are The depth of the bottom of the mineralisation. Unless the
used to generate a production schedule that complies with all context otherwise implies, it refers to the as yet unknown true
these requirements. Requirements for decline development bottom of the mineralisation, which will eventually be
relative to both the production front and shaft development discovered by ongoing exploration. Until it is actually known, it
determine the development schedule. Cash flows are then is a hypothetical depth to facilitate evaluation of what might be
calculated from the appropriate physical cost drivers and the the case if the resource were in fact to extend to that depth.
fixed and variable unit costs and prices in the data. Mining,
milling and administration operating costs, both fixed and Base of Mining
variable, and capital costs for shaft development and
construction, decline development and sustaining capital, are The depth of the lowest level from which production will occur.
generated at the correct times from the physical schedule, and It obviously cannot be deeper than the Base of the Resource: it
tax calculations are performed. For simplicity in this can be shallower.
hypothetical example, depreciation for tax calculations is
assumed to be on a tonnage depletion basis for the mining Economic Depth
reserve and life of the mine as calculated by the model for the
The Base of Mining that delivers the maximum value of the
scenario specified by the current input data set. Net cash flows
parameter for which it is derived. For example, the Economic
and NPVs, before and after tax, are calculated.
Depth for after tax NPV will be the depth which, if set as the
Base of Mining, maximises the NPV of the operation. If the
The only financial parameters that have not been taken into
value parameter is specified as the more usual ‘cash break-
account fully in the demonstration model are the effects of
even’, it is the depth at which the revenues generated from the
production target changes on the capital cost of the shaft winder
ore mined equal the cash costs of mining them. Since costs will
and headframe, though as noted above, this requires only the
typically increase with depth, this definition is satisfactory if
inclusion of a suitable data table.
the grade is constant or has a consistent trend with depth. If,

AMC Reference Library – www.amcconsultants.com.au 5


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

however, the grade is variable, it may be necessary to define the Figure 4 shows a number of features that may be of benefit for
cash break-even Economic Depth as the Base of Mining that decision-making. The Economic Depths of the mine with
delivers the maximum cumulative net operating cash flow. trucking only and trucking plus shaft are 1050 m and 1550 m
respectively. The reduced truck haulage distances and operating
Evaluation of Options and Scenarios costs with a shaft installed allow production to continue to a
greater depth than with trucking only. Though hoisting starts
when production is at 650 m, the mine needs to extend to at
The effect of the ultimate depth of the mine
least 900 m for the upfront capital costs of the shaft to be paid
The Base of Mining can be varied in the model from the current for by the cumulative discounted operating cost savings. If the
mining front to any desired depth. For the cases reported, this is resource is known with confidence down to 900 m or below,
from 400 m to 2000 m depth. The Base of the Resource is at or the shaft can be safely sunk with the knowledge that any
below the Base of Mining. Figure 3 shows after tax NPVs for increase in resource will only add further value. Also, there is
trucking only and trucking plus shaft as functions of the Base of no point in exploring below 1550 m depth, unless further
Mining. The resource and exploration potential are assumed to exploration results in higher ore grades at depth, or costs are
continue down-dip at 25 000 t/vm and 3.5 g/t Au as for the reduced, in which case further analyses could be conducted
Reserve above 700 m depth. Other parameters in the initial with new data values.
analysis are as shown in the description of the model.

Figure 4 - After tax NPVs as functions of ultimate depth.

It should be noted that the Economic Depth may be different The effect of product price
for different economic goals. Table 3 shows the Economic
Depths (to the nearest 50 m) for NPV and NCF, before and Figure 5 shows similar curves to those in Figure 4, but at three
after tax, and with and without a shaft. It can be seen that the different gold prices – $A510, $A480 and $A450 per ounce. As
after tax Economic Depths are shallower than those before tax, expected, the Economic Depths decrease as the gold price
and NPV-based Economic Depths are shallower than those reduces.
using NCF. The explanation of these differences is beyond the
scope of this paper. The before tax NCF Economic Depth Other information can be derived from these curves. It can be
represents the depth where a simple cash break-even occurs and seen that at $510 the shaft curve passes through the trucking
would typically be the Economic Depth specified by traditional only curve at the Economic Depth of 850 -900 m and continues
analyses. Table 3 illustrates that this may not deliver the rising to its own Economic Depth of 1350 -1400 m. Whatever
company’s overall strategic goals. the depth of the Base of the Resource – down to the Economic
Depth of 1400 m – a viable mine plan exists with the Base of
Table 3 - Economic Depths for various parameters. Mining at the Base of the Resource, and increasing depth
delivers increasing value (so long as the shaft is operating as
planned when production is at 650 m and the resource
Trucks only Trucks and shaft continues below 900 m).
NCF before tax 1150 m 1850 m
NCF after tax 1150 m 1800 m At $480, however, there is a range of uneconomic values for
NPV before tax 1100 m 1750 m
the Base of Mining. Although the shaft option becomes better
than trucking only with the Base of Mining at 850 - 900 m, as
NPV after tax 1050 m 1550 m

AMC Reference Library – www.amcconsultants.com.au 6


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

with the higher price, the break-even point is at an NPV less This form of analysis indicates how the gold price not only has
than that at the Economic Depth for trucking only, which is at an influence on the Economic Depth, but also can generate a
700 m with this gold price. The shaft curve only rises above the range of depths for the Base of Mining, between the Economic
maximum value of trucking at a Base of Mining of 900 - 950 m Depths with and without a shaft, that will reduce project’s
depth. Therefore, if the Base of the Resource is between 700 value. This results in a step change in the Economic Depth as
and 950 m, a shaft will not add value, and the mine should the Base of the Resource gets deeper.
truck down to a Base of Mining of 700 m and then close.
However, if the resource continues below 950 m, mining may The effect of the resource tonnage
continue down to the Base of the Resource or the Economic
Depth with a shaft of 1250 - 1300 m, whichever is shallower. From the discussion of the ‘traditional’ analysis above, it is
evident that the size of the resource and exploration potential
With the lower gold price of $450, the shaft curve, though can have a bearing on the mine’s strategy. Figure 6 shows after
again higher than the trucking only curve below 900 m, never tax NPVs for trucking only as functions of Base of Mining and
rises above the maximum value of the trucking only curve, and the tonnes per vertical metre below 700 m depth. Figure 7
the mine will close after trucking down to the Economic Depth shows these for both trucking only and the shaft option.
at this gold price of 600 m, regardless of how deep the resource
extends.
Figure 5 - After tax NPVs versus ultimate depth and gold price.

Figure 6 - After tax NPV versus ultimate depth and size of resource – trucks only.

AMC Reference Library – www.amcconsultants.com.au 7


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

Figure 7 - After tax NPV versus ultimate depth and size of resource – trucks only and trucks plus shaft.

Both figures show that the effect of the size of the resource is value of the shaft option reduces, eventually falling below the
and the Base of the Resource is below 850 m to 900 m. maximum value obtainable with trucking only. The difference
relatively small for sizes above 20 000 t/vm, which is the size in value between different shaft starting times is the same for
At 15 000 t/vm, the shaft option is better than trucking only if all depths of the Base of Mining, representing the extra cost
that permits the allowable vertical advance rate to deliver the incurred by continuing to truck for a given period when cheaper
the resource extends beyond 1000 m depth, but in this case the shaft hoisting could be used, less the difference in discounted
costs of the shaft due to its deferral. (While it has not been used
1.0 Mtpa production target. Once the possible production rate in this study, this calculation logic could be used to identify the
maximum value of the operation with a shaft, at the Economic optimum timing of the shaft development and construction.)
falls below that, due to the 50 vm/yr limit, the value of material
Depth of 1250 m, is less than the value of trucking only with a For this case study it is specified that the shaft option should
below 700 m rapidly reduces and becomes uneconomic. It can have an NPV at least $5 M greater than trucking only, to reduce
Base of Mining at 700 m. Lower resource tonnages exacerbate the financial risk and deliver a positive NPV for the
also be seen in Figure 7 that the shaft option is better than this development project. If the shaft is commissioned when the
situation. The analysis provides a clear indication of the size production front is at 800 m, then it is only necessary for the
trucking only, so long as the resource is greater than 20 000 resource to extend to 1000 m for the shaft to be viable, and
t/vm and depth of the resource required to justify a shaft. additional depth of resource adds significant value. If the shaft
is delayed until production is at 1000 m, then the resource must
The effects of shaft starting date extend to 1350 m for the shaft to be viable, and there is little
extra value obtainable down to the Economic Depth of 1550 m.
Qualitatively, it can generally be stated that shaft hoisting could It can be seen that the shaft must be commissioned when the
commence economically as soon as the production front production front is no deeper than about 1030 m. In this case
progresses below the depth where the truck haulage costs the resource must extend to the Economic Depth of 1550 m for
become greater than hoisting costs. The sooner the shaft the desired $5 M margin from the shaft to be obtained. If the
becomes operational, the more tonnage can be handled at its shaft commissioning is delayed further, until the production
lower haulage costs, and the greater the benefit from the shaft. front is at 1130 m or below, the shaft option can no longer add
Delaying the shaft reduces the tonnage handled at lower any value, regardless of the depth of the Base of the Resource.
haulage costs, and if delayed too long, there may be insufficient
savings to pay for the shaft and it will no longer be justifiable. As with the effects of gold price, delaying the shaft generates a
range of depths for the Base of Mining between the Economic
Figure 8 shows after tax NPV versus the Base of Mining for Depths with and without a shaft that will reduce value, resulting
trucking only and for shafts commissioned at various times, as in a step change in the Economic Depth as the Base of the
specified by the depth of the production front when shaft Resource gets deeper. Figure 9 shows the Economic Depth,
hoisting starts. Broken and dotted lines show the maximum with or without a shaft (whichever is more valuable), as the
value obtainable with trucking only, and a $5 M margin above depth of the Base of the Resource increases, depending on
that. when the shaft is commissioned.
It can be seen that, as expected, as the start of shaft hoisting is
delayed, the break-even Base of Mining increases, and the

AMC Reference Library – www.amcconsultants.com.au 8


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

It can be seen that, with trucking only, as the depth of the Base However, it clearly has a cost. in the data used. This percentage
of the Resource increases, it is also the Economic Depth, down can be greater than 100 per cent. An alternative strategy could
to the Economic Depth of 1050 m. Beyond this depth, be to mothball the mine once The administration fixed cost is
increasing trucking costs reduce value. If a shaft is assumed to continue through the production reaches the
commissioned when production is at 800 m or 900 m, the trucking only Economic Depth until shaft break in production
whole resource is economic, with the Base of Mining at the to represent mothballing and care and hoisting commences,
Base of the Resource, down to the Economic Depth of 1550 m. after which production can resume and maintenance costs.
With the shaft commissioning delayed until production is at Figure 10 shows the effect on value of the continue to deeper
1000 m or 1100 m, there are ranges of depths of the Base of the levels. The model logic also permits the duration of the break in
Resource where the Economic Depth is that for trucking, at production.
1050 m, until the increasing depth of the Base of the Resource
is sufficient to justify the shaft. From those points on, the Figure 10 is similar to Figure 8, and similar inferences can be
resource is again economic for bases of mining coincident with drawn. Increasing the duration of the break in production
the Base of the Resource, down to the Economic Depth of 1550 results in the $5 M desired margin for the shaft being eroded to
m. If the shaft is commissioned when production is at 1200 m, virtually nothing, if the Base of the Resource and Base of
there is insufficient resource down to the Economic Depth to Mining continue to the Economic Depth with a shaft of 1550 m.
justify the shaft, and the Economic Depth of the mine remains If the resource does not extend this deep, the shaft cannot be
at the trucking only Economic Depth of 1050 m regardless of justified and the mine should close permanently when
the depth of the Base of the Resource below that. production with trucking only reaches 1050 m, rather than be
mothballed and a shaft constructed.
The effects of breaks in production
The impact on exploration strategy
The Economic Depth for trucking only is 1050 m, as shown in
Figure 8. The discussion of the effects of shaft timing above A number of comments in the preceding discussion have shown
includes cases with shaft hoisting starting when production is at how the size of the Inferred Resource and Exploration Potential
lower depths than this. This implies that uneconomic (in tonnes per vertical metre) that is required to justify
production by truck haulage to surface is continuing while the production below the Base of the Reserve or the construction of
shaft is being constructed. This may be a valid strategy, for a shaft can be identified by this form of analysis. The depth to
example, to modelling of this mothballing. A data entry item which the resource needs to be identified to justify a shaft can
allows retain a trained workforce on site so that the mining also be determined, together with the impact of that on the
operation specification of the time with no production as a exploration strategy. Figure 11 shows the Base of the Resource
percentage of can continue smoothly through the transition and exploration lead required to justify a shaft.
from trucking only the shaft development and construction
time, which is two years to trucking and shaft hoisting.

Figure 8 - After tax NPVs versus ultimate depth and timing of start of shaft hoisting. FIG 9 - Effect of timing of start of
shaft hoisting on Economic Depth of mining.

AMC Reference Library – www.amcconsultants.com.au 9


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

Figure 9 – Effect of timing of start of shaft hoisting on Economic Depth of mining

Figure 10 – After tax NPVs versus ultimate depth and duration of break in production before shaft hoisting

For example, as described above for Figure 8, if the shaft is 100 vm of production. The resource must therefore be
commissioned when the production front is at 800 m, it is sufficiently accurately defined at least 325 m ahead of the
necessary for the Base of Mining to be at approximately 1000 production front at the time the evaluation commences.
m – more accurately 1025 m – for the shaft option to deliver $5
M more after tax NPV than trucking only. From the input data This process is used to derive all the points on the curves in
it takes two years to develop and construct the shaft. If a six- Figure 11. The curves indicate that the minimum depth of the
month investigation and decision-making process is assumed, Base of Mining, and therefore of the Base of the Resource,
the data for the evaluation must be available 2.5 years before increases gradually as the production depth increases towards
the shaft commences operation. At a production rate of 1.0 the Economic Depth for trucking only, but the exploration lead
Mtpa and with a Reserve of 25 000 t/vm, this time represents reduces. However, as the production front approaches the

AMC Reference Library – www.amcconsultants.com.au 10


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

Figure 11 – Base of Resource and exploration lead required to justify a shaft

Economic Depth for trucking only, both the minimum depth of evaluated. Although the evaluation may then be repeated at
the Base of Mining and the exploration lead increase rapidly. various times, limited exploration in advance of the mining
The curves terminate at the Economic Depth for trucking plus front on an ongoing basis may mean that there is never
shaft. sufficient information to justify the shaft at any point in time,
even though the resources eventually proved up could have
The information derived from this type of analysis can easily justified the shaft had they been known earlier.
therefore give a clear quantitative indication of the minimum
exploration program required to provide information to justify a The alternative methodology illustrated in this paper involves
shaft. Clearly a typical exploration program that seeks only to the construction of a model that is able to handle correctly a
prove up a couple of years’ Reserves – equivalent in this case to wide range of data inputs for resources and reserves in
80 vm, or at most 100 vm at the maximum vertical advance rate particular, and also produce realistic physical schedules and
– will never, in this hypothetical example, be able to generate resulting cash flows for a range of decisions that could be
the Reserves needed to justify a shaft. Given the current level of made, including such things as production rate targets and
knowledge of the resource, the advance rates of both the constraints, and the timing of the transition from trucking only
production front and the depth of the resource required to to shaft hoisting. By evaluating the effects of variations in a
justify a shaft, and the drilling rates available for various number of factors, both external, such as product price, and
numbers and types of drills, an exploration program can be internal, such as the lowest level of production and the timing
designed to ensure that resource information is available at the of introducing a shaft, various pieces of information to assist in
right time and to at least the required depth to support a strategic decision-making can be produced. While such
definitive shaft versus trucks evaluation. ‘number crunching’ cannot in itself justify a shaft any more
than a traditional analysis if the real information is not
Conclusion available, it can clearly demonstrate what information must be
gathered in order to do so. The information generated can
The timing of the decision to sink a shaft can have a dramatic include:
impact on the value that can be extracted from a resource. If
delayed too long, for example to defer capital expenditure, or • The depth of the lowest production level to maximise
because the resource is not well enough defined to support the the value of the operation, with and without a shaft,
decision, the extra value delivered by a shaft may fall to the for any specified value measure. The Economic
point where the shaft can never be justified. Depth for after tax NPV can be significantly
shallower than that for the more typically used cash
A traditional evaluation of trucking versus shaft hoisting will break-even. There may be little point in exploring
often evaluate only the known resources, and may also for below the Economic Depth with a shaft, unless there
conservatism reduce the size and/or grade of any Inferred is some reason to believe that the tenor of the
Resource used in the analysis. Unless the shaft is clearly resource may increase in that region.
justified with sufficient certainty to support a decision to install • The loss generated by deferring the shaft by various
it, the conclusion will often be that it cannot be justified with periods. This loss depends on the period of deferral,
the present information and should be re-evaluated later, rather and is not influenced by the ultimate depth of the
than that it can never be justified and should never be re- Base of the Resource.

AMC Reference Library – www.amcconsultants.com.au 11


A Quantitative Assessment of the Factors Influencing the Shaft Versus Trucks Decision

• The latest starting time of shaft hoisting for the


maximum value generated with a shaft to be greater
than the maximum
• value generated with trucking only. If a shaft cannot
be commissioned by that time, there may be little
point in exploring below the Economic Depth with
trucking only, unless there is some reason to believe
that the tenor of the resource may increase in that
region.
• The minimum depth of the Base of the Resource that
is required to justify a shaft, hence the amount of
exploration required ahead of the producing areas,
and how these may vary over the life of the operation.
The shaft-justifying exploration lead may be
significantly greater than what may be done to
maintain a reserve equivalent to some specified
number of years of production. If the exploration
program is based on maintaining a reserve, the
analysis may show that it may never be possible to
justify a shaft, even if it would have been justifiable if
the resource information had been available earlier.
• The impact of financial parameters such as product
price and costs on the above.

The methodology illustrated is a relatively simple extension of


methodologies already used. It requires a little more data
preparation and somewhat more complex modelling to ensure
that the ranges of alternatives compared are evaluated at a level
of accuracy that supports the conclusions drawn, but can
provide significantly more useful information for decision-
makers than has been provided by more traditional analyses.

Acknowledgements
The author wishes to thank the management of AMC
Consultants Pty Ltd for permission to prepare and present this
paper, and various members of the staff for their comments and
contributions.

AMC Reference Library – www.amcconsultants.com.au 12

You might also like