15What are the types of constraint available in MS project?

A. As soon as possible
B. As late as possible
C. Both A and B
D. None of these

16.How to set a deadline in MS project?


A. Double-click a task -> it will open a task information dialog box
B. Now, click on the advanced tab
C. Then click on the arrow in the deadline field to show the calendar and then choose a date
D. All of the above

17.Identify the field that must be unique in Primavera.


Project Name
Project Description
Project ID
Project Manager

18.Which of the following statements regarding critical paths is true?


a.                   The shortest of all paths through the network is the critical path.
b.                  Some activities on the critical path may have slack.
c.                   Every network has exactly one critical path.
d.                  On a specific project, there can be multiple critical paths, all with exactly the same
duration.
e.                  The duration of the critical path is the average duration of all paths in the project network.

19.Which of the following statements regarding critical paths is true?


a. The shortest of all paths through the network is the critical path.
b. Some activities on the critical path may have slack.
c. Every network has exactly one critical path.
d. On a specific project, there can be multiple critical paths, all with exactly the same
duration.
e. The duration of the critical path is the average duration of all paths in the project
network.

20.Activities falling on the critical path have


zero slack
maximum slack
minimum slack
negative slack

21.What is the main objective of Software Project Planning?


a. Estimation of resources
b. Estimation of cost
c. Estimation of schedule
d. All of the above