NON-CONFORMANCE REPORT

Project / Projekat Date of report / Datum izveštaja


IKEA Retail Park Belgrade 8nd December 2021
Work package / Radni paket
General Contractor Works Report No / Izveštaj br.
Contractor / Izvođač
IT Tel E 048
Non-Conformance description / Opis
grešaka Photo of defect / Fotografija greške

Objekat SM lokal SM29:


4 korugovane rebraste cevi u podnoj
betonskoj ploči su postavljene na rastojanju
260cm od ose 08 a projektovano rastojanje
je 300cm

Building SM tenant SM29:


4 corrugated pipes for electrical installations
are placed at a distance 260 cm from the
axis 08 and by design is demanded
(300cm).
Date / Datum Supervizor (nadzor) STMG Consultancy / (full name / ime i prezime & potpis /signature)

08-December-2021

_____________________________
Predrag Cvetković

Proposed corrective action / Predložene korektivne akcije

In order to bring the corrugated pipes to the projected position, it is necessary to do the following actions:
The slit in the concrete will be cut with the tool provided for cutting the concrete.
After that, the appropriate corrugated pipes will be laid, and at the end, the slit will be repaired with the appropriate
material on the recommendation of civil engineers.

Kako bi se korugovane rebraste cevi dovele na projektovanu poziciju, potrebno je uraditi sledeće:
Izvešće se šlic u betonu alatom predviđenim za sečenje betona.
Nakon toga položiće se odgovarajuće korugovane rebraste cevi i na kraju biće izvršena sanacija šlica odgovarajucim
materijalom po preporuci gradjevinskih inženjera.

Date / Datum Contractor / Izvođač (full name / ime i prezime & potpis /signature)

10.12.2021.

________________
Ivan Đorić
Proposed actions to avoid similar nonconformance for the future works / Predložene akcije za sprečavanje sličnih
pojava u nastavku radova
Date / Datum Contractor / Izvođač (full name / ime i prezime & potpis /signature)

10.12.2021. In order to prevent similar mistakes in future activities of the similar works, the project
will be considered in more detail and the performed works will be checked before
concreting the base.

Kako bi se sprečile slične pojave u nastavku radova detaljnije će se sagledavati


projekat i vršiti provera izvedenih radova pre betoniranja podloge.
Approval to proceed with corrective action / odobrenje za primenu korekcije

Date / Datum Designer / (full name / ime i prezime & potpis /signature)

Approved

Returned to be revised

_____________________________

Date / Datum Supervizor (nadzor) STMG Consultancy / (full name / ime i prezime & potpis /signature)

Approved

Returned to be revised

_____________________________

Taken corrective action / Preduzete korektivne akcije

Photos / Fotografije

During the correction / U toku During the correction / U toku


korekcije korekcije After / Posle

Corrective actions implemented / Korekcije izvršene

Date / Datum Supervisor STMG / Nadzor (full name / ime i prezime & signature / potpis)

_________________