Professional Documents
Culture Documents
Energy Efficiency:Optimizationof
Electric Power Distribution
System Losses
July 1982
July 1982
Abstract
Given the rising costs of energy supply and the high level of loss
in LDC pover systems,the objectivesof this study were to develop pratical
methods for (1) isolatingtechnicallosses in distributonsystems;(2)
evaluatingeconomically, methods of reducingloss levels;and (3) incorporat-
ing the effects of loss analysisinto engineeringcriteriafor design and
operations.
CHAPTER1: INTRODUCTION
ANDSUMMARY 1
CHAPTER4: OPTIMIZINGDISTRIBUTIONLOSSES 38
CHAP?TER5: SUMMARY
OF CASE STUDY RESULTS 49
5.1 PrimaryConductorLoading 51
5.2 Power Factor Control 52
5.3 Distribution Transformers 55
5.4 SecondarySystems 64
5.5 Connections 67
5.6 Literature Search 67
APPENDICES
A EconomicLoss OptimizationModel 69
B ComputerizedAnalytical Models 76
C Case StudyDetails 97
D Basic Loadingand Loss Parameters 124
E Bibliography
CHAPTER 1
INTRODUCTIONAND SUMMARY
(1) (J ) T
Generation
Station use +
(2) ) EHV and HV
transmission losses
_+ nontechnical losses
and Hv
iEHv
TRANSMISSION
3 'ower and energy
(3) (4)5 demands of
%HV consumers
SLVdistribution losses
(8) and nontechnical losses LV
. ~~~DISTRIBUTION
(9) Power and energy demands
Of LV consumers
Note:
,.power and energy flows
7-losses
E) generation
a transformation
The second reason for high distribution system Loss levels also
stems from the rapid rise in energy costs, recently. In brief, additional
expenditures on system hardware can bring down system losses. Rules of thumb
for system design, still used by many LDC utilities to tradeoff increased
system investment costs versus reduced losses, implicitly embody relative
costs more appropriate to the mid 1960's than the early 1980's. As a very
rough illustration, let us take the international prices of oil and aLuminum
(or copper) as proxies for the values of energy losses and of system hardware
(e.g., conductors), respectively.
Accordingly, this study seeks to help the Bank and its borrowers
identify and reduce network losses. It shows that reducing losses is often
more cost effective than building more generation capacity, and will
therefore free scarce domestic resources and foreign exchange.
(1) identify the areas within a power system where loss optimization
would be most effective, in the context of the developing
countries;.
(3) develop and test (on the basis of a desk study) a framework for
economically evaluating alternative means of reducing losses on an
existing system and determining the optimal Loss levels;
-\;2~~0
CRUDE OIL
10~~~~~~1
. S~~~~~~~~s00
*-r4
ALUMINUM
1000
AA
-~~~~~~~~~~~~ ccc
COPPER
40cc
1.2 Summary
EconomicModel
Regulator
Primary System
* Secondary System
Loading Model
Methodology
The methodology for including losses in the decision making process relative
to engineering criteria would be similar to the above process (Steps (1)
through (6)).
Sub-transmission systems
(especially 35 kV and below)
Distribution transformers
* Secondary systems
Peak Demand
Peak Equivalent Hours
Average Loading
Load Factor
Load Duration
Loss Equivalent Hours
Loss Factor
-8-
3/ The range of US¢4 to 9 per average kWh (in 1981 prices), and the high
discount rate of 12% (based on the opportunity cost of capital) are on
the conservative side. If energy was valued more highly, or if the
discount rate was lower, the conclusions regarding loss reduction given
here would be further reinforced.
- 10 -
- 3 to 5% of annual energy 4/
- 5 to 8% of power at peak
relationship between load factor and loss factor (See Appendix D for
details).
As a first step the system load factor and energy loss (average and
peak) must be estimated. For completeness, we summarize below, the
well-known expressions that may be used:
Table 1.1 provides some typical (average) values of the demand loss
multiplier (i.e., ratio of peak period to average loss) for various load
factors. Actual values will depend on.the specific network under study.
Table 1.1
Demand Loss
Load Factor Loss Factor Multiplier
30 20.6 1.46
35 24.6 1.42
40 28.8 1.39
45 33,3 1.35
50 38.1 1.31
55 43.1 1.28
60 48.4 1.24
station-use which varies from as low as 0.5% for hydro plants to over 5% for
coal-fired steam units). A total system power (kW) loss at peak in the
neighborhood of 12.0% is good, implying that overall loss reduction measures
are not critical and will not produce dramatic gains. However, a reasonable
total loss level does not mean that loss reduction in specific parts of the
system or geographic areas should not be pursued. Power factor correction,
elimination of high impedance power transformers, and distribution
transformer load management, should be investigated for all utilities.
EHV TASMISSION
(500-765 kV) SUBTRANSMISSION SECONDAY
NIVTRANSMISSION (69-115 kV) (115-480 V)
GENERATION (230-345 k))
( ~~~~ \ ~~~~DISTRIBUTION/
9 ) 1 i kV)
<~~~~~~~~~~~~~~(4-35
STEP-UP : N
STATION EHV NV DISTRIBUTION DISTRIBUTION
STATION STATION STATION TRANSFORMER
DEMANDLOSSES
(Z of kW GENERATED)
TARGETLEVEL TO BE TOLERATED
MAXIMUM
Table 1.3
VI. SecondarySystem
maximum length
capacitorson primarylines
(4) Reducingprimaryconductorloading
(5) Reducingsecondaryconductorloading
(6) Reducingtransmissionconductorloading
- 15 -
(1) The older tap changing under load transformers were often
manufactured with impedances in the general neighborhood of
15%. These transformers should be removed from service and
either scrapped or held for emergency use only.
VI. 'he values in the table are averages (for 240 Volt systems) and
therefore rather rough. They must be used only as a first check or
warning, because specific figures will depend on load densities which
are highly variable. The accepted methods for correcting overloaded
secondary systems are:
CHAPTER 2
The essence of the optimization model is the trade off between increased
distribution costs and the resultant decrease in the cost of losses. While
system costs are relatively easy to measure in terms of the economic value of
physical inputs like capital, labor and fuels, the value of losses is more
diffEicultto establish. Therefore, after discussing loss optimization, we
establish below how physical losses in a power system may be valued in
economic terms.
The net benefits (NB) of electricity consumption from the social viewpoint is
given by:
NB = TB - SC
SC = BSC + DSC
Where BSC is the bulk supply cost and DSC is the distribution system cost
(investment, O&M, etc.).
Input Fran
BulkC Supply System
QI
Distxibution
ihr >Losses
Netwrk L QI Qo
Q0
output to
Custaners
- 19 -
SC = VQi + DSC
and
NB = TB - VQI - DSC
In other words:
In the engineering studies that have been done so far, emphasis has been
placed on applying accounting principles to loss evaluations, rather
than economic principles. Although concepts such as present worth of
annual revenue requirements, levelized annual costs, annual costs, and
equivalent investment costs are used, there is no application of
economic theory in the above procedure.6 /
Figure 2.2
OPTIMALECONOMIC
LOSS LEVEL.(L*?
VALUE
8/ We note that in the first case, the cost savingsaccrue to the power
supplyingcompanywhereas in the second case, the customersgain. Thus
from a social viewpointboth costs savingsare equivalent,whereas from
the power company'sviewpointthe former is more desirable.
- 23 -
CHAPTER3
CALCULATINGDISTRIBUTIONSYSTEM LOSSES
10/ (:osin
X power factor.
FIgure 3.1
SUBSTATION
KVS T
t
Rl $ ILD1 + ILD2 + ILSI+ ILS2
LOAD 2
b ~~R2 R3
ILD2
ILD2 ILD1
+ +
ILS2 ILS1 I
RSEC LOAD 1
DT1
ILDI
- 25 -
Energy Loss is the summation of the Demand Losses (I2 R) over time (Hours).
The voltage at the substation (KVST) is known but the level erodes due to
resistances as we get further away from the station.
The voltage level at each load point is required to'compute the amount of
current (I) required by each load.
However, the current (I) is dependent upon voltage level (which is not known)
and the line losses are dependent upon the square of that also unknown
current.
(4) The above is repeated for all loads and all sections
on the feeder with load flow in each section
cumulated and noted.
In the real world, most feedersare type (C) and requiremany calculations.
I = Current in amperes
I kW
kVLL x
I - Current (Amps)
R = Resistance(ohms)
X = Reactance(ohms)
the voltage drop is for one conductor(line to neutral). The three phase
line-to-linedrop is (3) 1/2 times this value, and the single phase drop is
twice the above value.
The vector diagramof Figure 3.3 (B) shows that the above equationis
approximate,but is sufficientlyaccuratefor all practicalpurposes.
- 27 -
Figure 3.2
LOADING CONFIGURATION
Line
Sour.ce
Load
Source
I Dl x ,, ,
Figure 3.3
I
R X
l| 'SOURCE KVLL
Ir- ~~~~~
R X
Calculate Dr=D
CoIRs
Cosa__________
Ix
sin a
Losses (Watts)= I2 R
The above losses are for one conductor,so the total would be 3 times the
above value for 3 phases.
Figure 3.4
IC ID
I~ ~~ I
I TOTAL
MODEL I Resistance
I v
o Single Phase
o Three Phase I
o Bank of Transfo=er Reactance
I I
KVA No Load Tbtal No Load Total No Load Tbta1 No Load Tottal No Load Tbtal
50 166 611 166 613 166 671 166 717 166 714
75 274 916 274 918 274 937 274 1024 274 981
100 319 1192 319 1146 319 1200 319 1300 319 1247
167 530 2085 530 2085 530 2085 530 2085 530 2035
250 625 2800 625 2800 625 2800 625 2800 625 2800
333 800 3400 800 3400 800 3400 800 3400 800 3400
500 1100 4850 1100 4850 1100 4850 1100 4850 1100 4850
TABLE 3.2
DISTRIBUTION TRANSFORMERLOSSES
First and very important--- primary capacitorshave been used for power
factor correctionand voltage regulationfor over 40 years. The economics,
their durabilityand benefitshave been proven time after time by thousands
of utilities. There is no reasonableor logicalreason for refusingto apply
capacitorsto reduce losses.
The lagging1000 kVAR's of the load can be suppliedby a 1000 kVAR capacitor
bank locatedright at the load center. The resultantload on the system is:
KilowattDemand = 1000 kW
KilovarDemand O kVAR
0
1000 kW
1000 kVAR
1.414 Units of Current 1414 kVA
I
s i ~~~~is s
Gbr. 0atio
Transsion Sub- Distribution
1000 kVAR
Capactor
1.00 Units of Current
Load
Net Load
1000 kW
0 kVAR
1000 kVAR
The capacitors reduced voltage drop by 30% and losses 50%. The effect on
voltage drop and losses of correcting power factor may be calculated with the
above equations or estimated from Table 3.3.
TABLE 3.3
/* ~ Various
Conductor
Peak Sizes
Demand
(kW)
Load
Peak Factors
Loss
(kW)
Various
Peak / Transformers
Demand
(kW)
(5) DecentralizingSecondarySystems
(2) Discountrates
CHAPTER4
OPTIMIZINGDISTRIBUTIONLOSSES
Isolatingtechnicallosses
Reducinglosses to an economiclevel
There are two major sourcesof error in this commonlyused method for
computinglosses:
- 39 -
Figure 4.1
DISTRIBUTION SYSTEM
SUB TRtMISMISSION
STATION TRANSFORMER
STATION BUS
kW
kV-AR
. /~~~~~~~~~~O
Q-
LEGEND
CQ Breakers o
Primary System
A Distribution Transformer
--- Secondary System
Regulator
'~" Capacitor
Consumer Meters
i
Si-Pot oad (kW demand is known
- 40 -
Feeder Demand
at Substation
kW & kVAR
Suibtract Spot
Loads from
Sitation Demand
Compute
Voltage, Losses
and Loading
Is LoadingSame
as
Allocated Dead?
YES N
, ~~~~Modify
Demand
to be Allocated
Note: It is not expectedthat the data of Figure 4.4 (A) and (B)
will be directlyapplicableto World Bank Borrowingnations
because they are based on USA residentialconsumers.
However,they do illustratethe type of data that is needed
and may be useful as a yardstickof comparison.
StationTransformers
Primary
DistributionTransformers
* Secondary
. Peak Demand
. Load Duration
. Load Factor
. Loss Factor
- 44 -
Figure 4.3
SERVICES
PRIMARY
| _ _ / \ l MAIN I
-A' I *DISTRIBUTION l
| TRANSFORMER |
I \1< ~~~~~~~~~i 1 l .
TYPICAL EUROPEANSTYLE SECONDARYSYSTEM
Voltage is 240/416 Volts (10/30)
NEUTRAL 2a
Figure 4.4
1.00
1.00,._.....,,,..
1. 2 5 10 20 50 100
Nunber of Consuers
20 - - - - -
10 - - -
8 __
6 --
4
2 _
0 -- I I- - -----
200 400 600 800 1000 2000 3000
kV9
Peak Motnth Cosmption per Ccns=er
(B) Cansurer DemandVersus Energy Usage for Sumner Season (US)
- 46 -
FiRure 4.5
DETE1INING SYSTEMCOSTS ANDCOSTS OF LOSSES
(TRANSFORMERS,
PRIMARIESAND SECONDARIES)
Select Component
of System
Select Model
Loading the
Characteristics Component
*t Analyze
Losses, Loading,Voltage
NO
Economic Analysis
. Transformers
Replace
Shift Load
. Primaries
Capacitors
Reconductor
New Lines
Switch
Change VoltageLevels
Secondaries
Reconductor(Shift Loads)
Reduce or Eliminate
CHAPTER 5
This chapter contains a summary of the case study results, with details
provided in Appendix C. Although they are desk studies, the case studies of
this project provide affirmative answers on a preliminary basis to the
following pertinent questions:
Our most important conclusion is that within practical limitations --- loss
reductions at distribution level provides capacity and energy at far less
cost than obtaining capacity and energy through the construction of new
generation and transmission facilities. The case studies indicate that
utilities can obtain savings up to $15 for every $1 of cost associated with
reducing distribution system losses (primary system, distribution
transformers, secondary system). Therefore losses should be recognized as a
dominant factor in the engineering criteria used in system planning, design
and operation.
TABLE 5.1
Economic Maximum
Loading Based
Existing Maximum Loading On Optimized Losses
Practices (As a % of (As a % of nameplate rating of
nameplate rating or Thermal Limit) Thermal Limit)
Thermal Reliability*
Item Criteria Criteria
Distribution
Transformerl 180% N.A.** 80 to 100%
Based on U.S. design, 650 rise transformers. Conventional IEC Standard units (500 C
rise) may be able to take only up to about 125% of thermal limit without drastic
reduction in useful lifetime.
- 51 -
As the table shows, the case studies indicate the need to make some very
major departures from existing practices, namely that the value of losses
should be the single most important element in establishing engineering
criteria for the planning, design and operation of distribution systems.
It must be recognized that the results of a desk study based on data from
technical sources and from a few developing countries cannot be considered
conclusive enough to develop worldwide guidelines, However, the results of
this study strongly indicates that there is significant and immediate
potential for savings to be realized through loss reduction in LDC's.
11/ The range of values US¢4 to 9 per average kWh lost is representative of
a wide variety of all hydro, hydro-thermal, and all thermal systems
found in LDC's. Some systems may have higher values of LRMC per kWh but
hardly any would be lower.
- 52 -
The resultsof this case study is tabulatedin Table 5.2 and shown
graphicallyin Figure 5.1
Table 5.2 shows that for a systemwith maximum conductorloadingof 100% and
the higher value of losses, the presentworth of losses will be $881,600and
the presentworth of future investmentsis $4,900.
TABLE 5.2
Figure 5.1
\
$250/kW/yr. INCREMENTALBENEFIT-COSTRATIO FOR SUCCESSIVEREDUCTIONS
* $0.O37/kWJil IN CONDUCTORLOADING
25%
a, 10.0
uz
In K Practical Goal
H kWi/r\
0C 50 $0.0114/kWH\
I I II _
100% (4.6%) 75% (3.5X) 50% (2.9%) 25% 1--8%) 0%
MAXIMUMCONDUCTOR LOADING (LOSS GIVEN IN PARENTRISIS)
- 55 -
In this case study, benefits have been evaluated for reducing losses
only. This was accomplished by correcting the power factor from 80% to
95% for the Primary Conductor Loading systems. The system additions
(without capacitors) to maintain conductor loading at 100%, 75%, 50% and
25% were left unchanged. Capacitors were added to those systems over
the 20 years as required to maintain a 95% power factor. Consequently,
capacitor additions are the same for each conductor loading condition.
The benefits between systems vary because the load levels and losses vary
with conductor loading. The maximum benefits from power factor control are
related to the system with 100% maximum loading because there are more losses
to eliminate by reducing kVAR flow.
A surmary of the study is tabulated in Table 5.3 and graphed in Figure 5.2.
For the higher cost of losses and 100% conductor loading, the P.W. of annual
costs of $19,700 in capacitors results in a P.W. savings of losses of
$294.,400.
Even the lowest benefit condition (lowest loss costs and 25% conductor
loading) provides $2.9 in savings for every $1 of annual cost.
It is clear that power factor control via capacitors reduces losses with a
high benefit to cost ratio. It is highly probable that field studies will
confirm that the installation of primary capacitors should be the first step
in a loss reduction program, in most cases.
Transformer sizes
5, 10, 25, 50, 100 and 250 kVA
Table5.3
15.0
FOR
w ~~~~~$250/kW o
VARIOUS MAXIMUMCONDUCTORLOADINGS LEVELS
w 1$O.037/kWH\
0)
I-
0
u 5.0
° 5. a _ $130/kW
E0i $0.0114/kWl\
r'14
BceeLkeven I-hme
b) S250/kW/yr.and $0.037/kWh
(Approx.US49 per average kWh)
The computermodel was used to derive the no load losses (often referred
to as Iron losses)and load losses (often referredto as Copper losses)
for the above circumstances. The results of these analysisare
tabulatedin Table 5.4 and shown graphicallyin Figure 5.3.
Anual costs with and without the cost of losses were then derived for
each transformerat the various load levels. The results of these
derivationsare shown graphicallyin Figures 5.4 and 5.5 for the two
levels of loss costs.
Ambient temperatures
Growth rates
Purchasecosts
Installationcosts
Replacementcosts
Maintenance
Connectionsand voltages
Taps
TABLE 5.4
DISTRIBUTION TRANSFORMER
LOAD LOSS (WATTS) PER kW OF DEMAND
60-_DEMAND AS % OF RATING OR SIZE
50
sol
40
14 30
EA
zH 20
(I) E- 0'5 10l5%20
0
TABLE 5.5
LOADINGPRACTICES
PRESENT TRANSFORMER
VERSUS
5 5 $5 10 $ 75 $ 30 12%
10 5 1S0 10 110 40 27
1S 10 160 25 140 20 13
20 10 220 25 160 60 27
25 25 182 25 182 - -
30 25 210 25 210 - -
35 25 250 50 243 7 3
40 25 300 50 261 39 13
45 25 350 50 280 70 20
50 25 402 50 300 102 25
30 25 358 50 325 33 9
35 25 437 50 357 80 18
40 25 543 50 392 151 28
45 25 646 50 435 211 33
S0 25 769 50 497 272 35
$400
E-o
cn
0
$3-00
$200
$1 0_005kV
I A~~-
1
5 kVA^_jr 10 kVA
0
I I~~~~~~~~~~
0 10 20 30 40
- COSTS NO LOSSES
ANNUAL
$300
$200
$100 _
/- - 25== kVA
j
5 kVA J 10 kVA
0_I
0 10 20 30 40
kVA DEMAND(50% LOAD FACTOR)
Figure 5.5 - TRANSFORMERCOSTS VERI'US kVA DEMAND
- 64 -
Purchasing
Economicreplacementlevels
5.4 SecondarySystems
The major differences between the two concepts may be summarized as follows:
The centralized systems transport power to the consumer over low voltage
(240/416 volts) secondary lines.
Losses
Reduction - 79.2%
Reduction - 77.2%
Annual Costs
Saings
Dollars - $ 75,971
% - 35.3%
TABLE 5.6
60 CENTRALIZEDSECONDARY
SYSTEMS
VERSUS
SYSTEMS
SECONDARY
60 DECENTRALIZED
Difference
(Decentralize
Minus
Item . Centralized Decentralized Centralized)
Transformer Statistics
Primary Lines
Secondary System
Annual Costs
The 6.1% additional cost for the decentralized system provides savings at a
benefit to cost ratio of 11.3 to 1 or $11.3 saved for every $1 of cost.
5.5 Connections
* Reliability(capacityfor emergencies)
APPENDIX A
The main focus of this Appendix is to analyze the economic outcome of reducing
losses in the distribution system, by applying the principles of cost benefit
analysis. First, before separating out the distribution network from the
system, the net benefit of consumption supplied by the entire eletric power
systeIais considered.
The electric power system is planned with a time horizon of T periods, each of
duratiLon1 year.
The various terms that enter into an expression for net benefit is next con-
sidered.
The total benefit (TB) of consumption of electricity in any time period 't' is
a function of the total quantity of electricity consumed or demanded Qt in the
absence of outages i.e. it is assumed that the quality of supply is perfect.
The present discounted value of net benefit to society (NB) for the planning
period can be written as
T
NB = [TBt (Qt) - SCt (Rt$Qt) o t (RtPQt)] /(l+r)t
tr o
Yt income of period t
1/
Previouswork has been done to maximizenet benefitby optimizingrelia-
bility throughthe trade-offbetween supply costs (SC ) and outage costs
(OCr). t
SC = a .MC + DSC
DSC is composed of investment costs and O&M costs. The technical losses in
the distribution network will be reflected in the a term, since more units
of electricity will enter the distribution system it losses are higher.
The next step involves giving an economic value to the distribution losses.
For this purpose it is necessary to compare the net benefits arising from two
alternative distribution systems. This approach can be extended to the com-
parison of many alternative network configurations.
Consider two distribution networks (1) and (2) in Figure A.1, each supplying
differing amounts of electricity. Let ai be the units of electricity entering
the distribution system 1, and b1 the corresponding units of electricity avail-
able to the consumers. Let 11 be the losses in the system 1.
In the distribution network, since al units are entering, with b units being
demanded and 1 units being lost
1 1 1
The net benefit from the power system can be written as:
T
NB = 2 (TBt - SC - OCt ) /(l+r)t
t=o
For eaclhsystem, the SC term is expanded into its component parts and the net
benefit can be written as:
T
For System 1: NB1 = 2 [(TBit- (alt.MCit DSClt) - OC1 i /(l+r)t
t-o
Figure A.1
DISTRIBUTION LOSS REPRESENTATION
a, a2
DSC 1 DSC 2
- losses losses
ii 12
i bl - b2
(1) (2)
APPENDIXA
-73- Page-5of
Now let us make the simplifying assumption that Systems 1 and 2 are two
alternativeways of meeting the same customerload, i.e., blt b2t.
i.e. TBI=TB
it 22t
then
T
NB1 - NB2 ' : E lt Ad ) - (at ilt +IDSClt - a2t .MC - DSC2t) -
t-o
(OCit- OCat)J / (l+r)t (3)
In additionit is assumed that the MC s are the same for the two systems.
Since the distributionnetwork is only a small part of a much larger bulk
electric supply system,the differencein marginalcosts for the two networks
at thvislevel will be negligible.
b it b 2t
As mentionedearlier,since:
alt -a2t lt 2t
_ 74 - APPENDIX A
Page 6 of 7
Thus the differencein amount of bulk power suppliedto the two systemscan
be replacedby the differencein losses in the two systems. This expression
is substitutedin equation(4):
T_
1 2 Ilt) .MC + (DSC2 t - DSClt+
-
1. 2
=
r=o(6) [(I2t -
(OC2 t - OC )]/(l+r)
T
NB 1 - NB2 T (1 2 t MC + MsC 2 t) - (llt.MC + DSCIt) +
t-o
(OC2 t - OClt)/(l+r)t (7)
where NB - NB -NB
AOC'. 0C1 - C2 i
T T
NSCi
, ' NSC1 /(l+r)t and OCt m o5
t-o t=o
75 - APPENDIX A
Page 7 of 7
Supposewe assume for the time being that the outage cost term AOC is
negligiblerelativeto .NNSC. 1/ In generalAOC would be a small correc-
tional term in the analysis.
ANB - ANSC
a NSC/a L = 0
APPENDIX B
Computerized models of the various power system components (see Figure B.1)
provide the basics for an analysis system to isolate and reduce demand and
energy losses. These models were used to carry out the following major func-
tions of this project.
Generation
&
Transmission
* Sub-transmission
Station
* Distribution Transformers
• Secondary Systems
Modeling Objectives
Generation X
Losses in this part of the system
are outside the scope of this study.
Also, losses are relatively small
Step-up because:
Trns forzer {>
(1) Original Planning and Design
High Voltage is at a Sophisticated Level
Transnission (2) Continuously Monitored After
Construction
TrTansdissicn
Substation
r Transformer
Distribution
Transfon=r
J (1)
(2)
Copper Losses ProDortional to Load
Iron Losses are Constant
FigureB.I
LOCATIONOF LOSSES
APPENDIX B
- 78 - Page 3 of 21
included all the turns, the core and the electrical/magnetic relationship
among these parameters. Such a model would have a high level of accuracy
but would be practically worthless in the real world because the necessary
data is not readily available.
The miodelsused in this project are based upon ones developed specifically for
electrical utilities over the past 15 years. These models provide a high
level of accuracy within the constraints of readily available data from
technlcal journals and manufacturers. Most of these models were used in
previous World Bank R & D Projects.
Generation Models
In general, these models are used to determine the lowest cost mix of
sources to meet forecasted needs. Losses play a very minor role in these
studies. Generation does not fall within the scope of this study.
Note: In some cases, the high cost of losses could be an important factor in
choosing between transmission of power from the central grid versus
isolated generation, to serve rural areas. This is a specialized type
of study which is outside the scope of this project, but should be
pursued when appropriate.
Transmission Models
Sub-Transmission Models
Loading on such lines is usually not excessive and losses are low acceptable
(although not necessarily economically optimal). In addition, these lines
are often monitored by central dispatching centers. While scope for loss
APPENDIX B
-79- Page 4 of 21
The primary system model used in this project was developed over the past 15
years for planning, design and operating studies. The model is in use Oy over
75 utilities who refer to it as Distribution Primary Analysis or DPA. -
Each distribution feeder is divided into line sections and nodes (see Figure
B.2) and then DPA translates the following parameters into a digital data
base:
Physical Electrical
Analytical programs use digital maps and the data base to compute voltages,
loading, losses and fault currents for each line section of each feeder. The
programs permit the engineer to vary the following parameters and obtain the
effect on losses:
Figure B.3 provides an overview of the primary system model (Data Base), the
data base management programs, and the analytical models used in this study.
The following sample computer printouts provide details concerning the
analysis:
1/ Rural System Engineering Via Computer Models, 1976, IEEE Rural Electric
Conference, C76408-O1A by Walter Scott, Scott & Scott Consultants, Inc.,
St. Louis, Missouri.
- 80 - APPENDIX B
Page 5 of 21
Figure B.2
Substation
i~~~~~~~~~~~~ IT
b~~~~~
Legend
Substation r Capacitor
@ . Node Recloser
DATA BASE
j LOADING | APS
0,
LOSSES _ EDIT
| FAULT PRINT
OQ
0It1I'd
Figure B.3
Figure B.4 is a reduced copy of a single line diagram for the feeder used in
the above examples. The single line diagram was plotted from the DPA data
base with an electrostatic plotter.
It is hoped that the inclusion of the diagrams and printouts will help to
provide a better idea of how distribution planning may be computerized.
APPENDIXB
-83- Page a of 21
I~~~~~~~
- _
.,'~~~~~~~~~4
I
j ~1
F: ..........
~~~.
S/121
- ,<
PRINTOUT B. .1
PROGRAM BALVOL
WORL BANK LOSS STUDY
FEEDER I NORThWEST I
VOLTAaE= 12.47KY LINE TO LINE
SECY END LGTH PNASE COND ----- LOAD IN SECTION ----- LOAD THRU SECTION VOLTAGE 120 BASE -- LOSSES --
NODE K FT CONF SIZE CONN KW KVAR AMPS CUST COND KW WVAR AMPS CUST SECT ACCU LEVEL KW KVAR
KVA z DROP DROP
55 1 3.5 ABC 336 AA 0.0 0. O0 0. 0.0 68.4 5982, 4428. 328. 0. 2.4 2.4 123.6 70.7 141.8
59 5 9.0 ABC 336 AA 1325.0 1014. 701. 55. 0.0 54.7 4712. 3457. 263. 0. 4.9 7.3 118,7 116.3 233.4
60 6 6.0 ABC 4/0 AA 417.0 319. 221. 18. 0.0 7.0 442. 306. 25. 0. 0.4 7.7 118.3 1.1 1.5
61 7 1.8 ABC 2 AA 367.0 281. 194. 16. 0.0 4.5 140. 97 a 0. 0,1 7.8 118.2 0.1 0.0
62 8 4.4 ABC 4/0AA 237.0 181. 125. 10. 0.0 54:0 3398. 2393* 195. 0. 2.2 9.5 116.5 49.0 65.2
64 10 4.8 ABC 2 AA 862.5 660. 457. 38. 0.0 16.0 498. 344. 29. 0. 0.8 10.3 115.7 3.8 1.7
65 11 2.8 AC 2 AA 215.0 164. 114. 14. 0.0 4.0 82. 57. 7. 0. 0.1 10.4 115.6 0.1 0.0
66 12 4.6 ABC 4/0 AA 1062.5 813. 562. 47. 0.0 30.8 1908. 1332. 111. 0. 1.3 10.8 115.2 16.9 22.4 4
67 13 2.1 ABC 2 AA 37.5 29. 20. 2. 0.0 8.6 264, 182. 15. O. 0.2 11.0 115.o 05 0e2
68 14 1.9 ABC 2 AA 300.0 230. 159. 13. 0.0 3.7 115. 79, 7. 0. 0.1 11.1 114.9 0.1 0.0
69 15 1.2 B 2 AA 25,0 19. 13. 3. 0.0 0,9 10. 7. 2. 0. 0.0 11.1 114.9 0.0 0.0
70 16 2.0 ABC 4/0 AA 750.0 574. 397. 34. 0.0 15.0 920, 638. 54. 0. 0.3 11.1 114.9 1.7 2.3
71 17 5.1 DC 2 AA 187.5 143. 99. 13. 0.0 3.5 72. 50. 6. O. 0.2 11.4 114.6 0.1 0.1
72 18 5.0 ABC 4/0 AA 637.5 488. 337. 29. 0.0 4.0 244. 169. 14. 0. 0.2 11.3 114.7 0.3 0.4
63 9 5.7 B 2 AA 150.0 115. 79. 20. 0.0 5.6 58. 40. 10. 0. 0.5 10.0 116.0 0.2 0.1
56 2 7.0 BC 2 AA 475.0 363. 251. 30. 0.0 15.4 339. 233. 28. 0. 1.3 3.7 122.3 3.5 1.6
57 3 5.9 C 2 AA 200.0 153. 106. 25. 0.0 7.1 77. 53. 13. 0. 0.6 4.3 121.7 0.3 0.2
58 4 5.7 AD 2 AA 225.0 172. 119. 14. 0.0 3.9 86. 60. 7. 0. 0.3 2.7 123.3 0.2 0.1
ENDOF FEEDER
TOTALLOSSESONFEEDIER 1 264.9 471.1
FACTOR
USING 0.50Z AS CONVERGENCE
2 ITERATION(S)
to
o Vi
PRINTOUT B.2 (1 of 3)
PRORAH PHSVOL
WORLDBANKLOSSSTUDY
CEEDER 1 NORTHuEST1
VOLTAGE= 12.47'KV
LINETO LINE
SECT END LOTH PHASE CORD LOAD IN SECTION
--- LOADTHRUSECTION VOLTAGE120 BASE -- LOSSES--
NODE K FT CONF SIZE CONN KU KVAR AHPS CUST COND KU KVAR AMPS CUST SECT ACCULEVEL KW KVAR
KIJA DROP DROP
TOTALSON PHASEA
SUBSTATION 1815. 1335.
PHASEB 2271, 1683. 126.0
PHASEC 1873. 1368.
55 1 3.5 A 336 AA 0.0 O. 0. 0. 0.0 63.2 1815. 1335, 303. 0. 2.2 2.2 123.8 18.9 37.9
0 0.0 0. O. 06 0.0 79.9 2271, 1683. 383. 0. 3.1 3.1 122.9 29.5 59.2
C 0.0 0. O. 0. 0.0 64.9 1873. 1368. 311. 0. 2.0 2.0 124.0 20.0 40.1
59 5 9.0 A 336 AA 416.7 319. 221. 51. 060 55,7 1541. 1121. 267. O 5,3 7.5 118.5 33.4 67.0
0 491.7 376. 260. 61. 0.0 64.8 1766, 1295. 311. 0. 6.3 9.4 116.6 43.7 87.7
C 416.7 319. 221. 51. 0.0 49.2 1383. 1004. 236. 0. 3.7 5.6 120.4 27.1 54.3
60 6 6.0 A 4/0AA 150.0 115. 79. 18. 0.0 6.4 134. 93. 23. 0. 0.4 7.9 118.1 0.3 0.4
B 192.0 147. 102. 24. 0.0 9.7 202. 140. 35. 0. 0.6 10.0116.0 0.6 0.9
C 75.0 57. 40. 9. 0.0 4.9 105. 73. 18. O. 0.1 5.8 120.2 0.2 0,2
61 7 1,8 A 2 AA 100.0 77. 53. 12. 0.0 3.6 38. 26. 7. 0. 0.1 8.0 118.0 0.0 0.0
b 167.0 128. 88. 21. 0.0 6.2 64. 44. 11. O. 0.1 10.2115.8 0.1 0.0
C 100.0 77. 53. 12. 0.0 3.6 38. 26. 6. 0. 0.1 5.8 120.2 0.0 0.0
62 8 4.4 A 4/0 AA 174.5 133. 92. 21. 0.0 52.8 1090. 765. 190. O. 2.2 9.7 116.3 13.0 17.3
B 37.5 29. 20. 5. 0.0 61.3 1244. 876. 221. O 2.7 12.1113.9 16.9 22.6
C 25.0 19. 13, 3. 0.0 50,1 1053. 740. 181. O. 1.8 7.5 118.5 12.2 16.2
64 10 4.8 A 2 AA 287.5 220. 152. 35. 0.0 19.2 198. 136. 35. O. 1.0 10.7115.3 1.5 0.7
9 325.0 249. 172, 40. 0.0 12.3 125. 86, 22. 0. 0.4 12.5113.5 0.6 0.3
C 250.0 191. 132. 31. 0.0 16.7 175. 121. 30. O. 0.9 8.4 117.6 1.2 0.6
65 11 2,8 A 2 AA 112.5 86. 60, 14. 0.0 4,2 43. 30. 8. 0. 0.1 10.9115.1 0.0 0.0
C 102.5 78. 54. 13. 0.0 3.7 39. 27. 7. 0. 0.1 8.5 117.5 0.0 0.0
66 12 4.6 A 4/0AA 358.3 274. 190, 44. 0.0 27.5 565. 394. 99. 0. 1.1 10.8115.2 3.7 5.0
b 333.3 255, 176. 41. 0,0 35.9 721, 504. 129. O. 1.7 13.8112.2 6.1 8.1
C 370.8 284. 196. 46. 0.0 29.7 619. 431. 107. O. 1.2 8.7 117.3 4.5 6.0
67 13 2.1 A 2 AA 37.5 29. 20. 5. 0.0 8.9 91. 63. 16. 0. 0.2 11*0115.0 0.1 0.1
0 0.0 0. O. 0. 0.0 9.5 96. 66. 17, 0. 0.2 14.1111.9 0.2 0.1
C 0.0 0. O. 0. 0.0 7.3 77. 53. 13. 0. 0.1 8.8 117.2 0.1 0.0
68 14 1.9 A 2 AA 100.0 77. 53. 12. 0.0 3.7 38. 26. 7. 0. 0.1 11.1114.9 0.0 0,0
B 100.0 77. 53. 12. 0.0 3.8 38. 26. 7. O. 0.1 14.1111.9 0.0 0.0
C 100.0 77. 53. 12. 0.0 3.7 38. 26. 7. O. 0.1 8.9 117.1 '0.0 0.0
69 15 1.2 B 2 AA 25.0 19. 13. 3. 0.0 1.0 )10. 7. 2. 0. 0. 14. 111.9 0.0 0,0
70 16 2.0 A 4/0AA 250.0 191. 132. 31. 0.0 10.9 223. 155. 39. 0. 0.: 11.:115.0 0.3 0.3
B 250.0 191. 132. 31. 0.0 19,8 396. 275. 71. 0. 0.5 14.3111.7 0.8 1.1
C 250.0 191. 132. 31. 0.0 14.4 300. 208. 52. 0. 0.2 8.9 117.1 0.5 0.6
71 17 5.1 B 2 AA 150.0 115. 79. 18. 0.0 5.8 58. 40. 10. 0. 0.5 14.7111.3 0.2 0,1
C 37.5 29. 20. 5. 0.0 1.4 14. 10. 2. 0. 0.0 8.9 117.1 0.0 0.0
72 18 5.0 A 4/0AA 166.7 128. 88. 21, 0.0 3.1 64. 44. 11. O. 0.1 11.1 114.9 0.1 0.1
B 241.7 185. 128. 30, 0.0 4.6 93. 64, 17. 0. 0.3 14.6111.4 0.1 0.1
C 229.2 175. 121. 28. 0.0 4.2 88, 61. 15. 0. 0.2 9.1 116,9 0.1 0.1
63 9 5,7 9 2 AA 150.0 115. 79. 18. 0.0 5.7 58. 40. 10. 0. 0.5 12.6113.4 0.2 0.1
w
00
I-N
I.-b
PRINTOUTB. 2 (2 of 3)
PROGRAMPHSVOL
JORLDBANKLOSS STUDY
FEEDER 1 NORTHWEST 1
VOLTAGE= 12.47 KULINE TO LINE
SECT END LUlH PHASE COND LOADIN SECTION-LOAD THRUSECTION- VOLTAGE120 BASE -- LOSSES --
NODE K FT CONF SIZE CONH KU KVAR AMPS CUST COND KU KVAR AMPS CUST SECT ACCULEVEL KU KVAR
KVA X DROP DROP
56 2 7,0 b 2 AA 275.0 210, 146. 34. 0.0 9.8 106. 73. 18. 0. 0.9 4.0 122.0 0.7 0.3
C 200.0 153. 106. 25. 0.0 21.5 233. 160. 39. 0. 1,9 3.9 122.1 3.4 1.5
57 3 5.9 C 2 AA 200.0 153. 106. 25. 0.0 7.1 77, 53. 13. 0. 0.6 4.5 121.5 0.3 0.1 c
58 4 5.7 A 2 AA 125,0 96. 66. 15. 0.0 4.4 48. 33. 8. 0. 0.3 2.5 123.5 0.1 0 I
B 100.0 77. 53. 12. 0.0 3.5 38. 27. 6. 0. 0.2 3.3 122.7 0.1 0.0
ENDOF FEEDER
TOTALLOSSESON PHASEA 71.5 128.9
PHASEB 99,8 180.5
PHASEC 69.6 119.9
OQ'~
1to
Fa1
PRINTOUTB.2 (3 of 3)
PROGRA
FIHSVOL
UORI-DBANKLOSSSTUDY
NORTHUESTI
FEEDER NUMBER 1
ANDCURRENT
KILOWAITPKILDVAR FLOW
DY
PHASESANDNEUTRAL
SECT KILOWATTS KILOVARS AtiPERES
NO. A 9 C A B C A B C N
55 1814.8 2271.1 1872.5 1335.2 1683.0 1367.5 303.2 383.1 311.5 76.2
59 1540.8 1765.8 1383.4 1120.0 1294.8 1003.7 267.2 311.1 236.3 61.4
60 134.2 201.9 105.4 93.0 140.1 73.0 23.0 35.1 17.7 15.1
61 38.3 63.9 38.3 26.5 44.2 26.5 66 1. . ,
62 1089.7 1244.4 1053.3 764.5 876.1 739.6 18969 2607 186.54 34.1
64 197.6 124.9 175.3 136.4 86.3 121.0 34.5 22.1 30.1 11.0
65 43.1 0.0 39.2 29.8 0.0 27.1 7.5 0.0 6.7 7.2
66 565.3 721.4 618.8 393.7 503.6 431.4 99.2 129.3 106.8 26.9
67 91.0 95.8 76.6 62.9 66.3 53.0 16.0 17.2 13.2 3.1
68 38,3 38,3 38.3 26.5 26.5 26.5 6.7 6.9 6.6 0.1
69 0.0 9.6 0.0 0.0 6.6 0.0 0.0 1.7 0.0 1.7
70 223.5 396.4 300,2 154.8 274.8 208.1 39.2 71.2 51.8 28.0
71 0.0 57.5 14.4 0.0 39,8 9.9 0.0 10.4 2.5 9.4
72 63.8 92.6 87.8 44.2 64 1 60.8 11.2 16.6 15.2 5.0
63 0.0 57.6 0.0 0,0 39.8 0.0 0.0 10.2 0.0 10,12
56 0.0 105.9 233.2 0.0 73.1 160,5 0.0 17.6 38.6 33.4
57 0.0 0.0 76.8 0.0 0.0 53.1 0.0 0.0 12.8 12.8
58 47.9 38.3 0.0 33.1 26.5 0.0 7.9 6.3 0.0 7.2
I%
to
0
W
PRINTOUT B.3
PROGRAMFAULT
WORLDBANKLOSS STUDY
NORTHWEST1
FEEDER I
SUBSTATIONVOLTAGE 12.47KY LINETO LINE
SOURCEIMPEDANCES(OHMS)
RI = 0,400 XI = 0.600
RO = 0.000 XO = 0.000
…--CUMULATIVE-------------
NODE PREV MILES POSITIVESEQ. ZEROSEQ. PH-TO-OR PH-TO-PH 3-PH
SECT FROM R X R X MIN* MAX** (AMPS) (AMPS)
WIRE SUB (OH1S) (OHMS) (AMPS)
SOURCE 238. 14976. 8646. 9984.
1 336 AA 0.665 0.62 1.04 0.41 1.98 235. 4935. 5156. 5954.
5 336 AA 2.372 1.18 2.17 1.46 7.06 229. 1798. 2527. 2918.
6 4/0 AA 3.508 1.77 2.95 2.38 10.47 222. 1240. 1810. 2090.
7 2 AA 3.840 2.33 3.21 3,02 11.49 217. 1108. 1573. 1817.
8 4/0 AA 3.201 1.61 2.74 2.13 9.55 224. i354. 1960. 2264. 0
10 2 AA 4.105 3.12 3.43 3.89 12.33 212. 995. 1345. 1552. x
I1 2 AA 4.643 4.01 3.84 4.94 14.00 205. 855. 1123.
12 4/0AA 4.076 2.07 3.35 2,84 12i18 219* 1073. 1584, 1829.
13 2 AA 4.475 2.73 3,65 3.61 13.41 213. 955. 1366. 1577.
14 2 AA 4.830 3.32 3.93 4.31 14.50 209, 868, 1212, 1400.
15 2 AA 4.711 3.13 3.83 4,07 14.15 210, 895.
16 4/0AA 4.457 2.27 3.61 3.14 13.33 216. 984. 1461, 1688.
17 2 AA 5.431 3.89 4.35 5,04 16.35 204. 768. 1069.
18 4/0AA 5,404 2.76 4.27 3.91 16.17 211. 817. 1226, 1416.
9 2 AA 4,278 3.40 3.54 4.23 12.91 210. 946.
2 2 AA 1,987 2.82 2.03 2.99 6.08 218, 1622. 1794.
3 2 AA 3.105 4,68 2,86 5.17 9.58 204. 1024.
4 2 AA 1,739 2.41 1.85 2.50 5.31 221. 1862. 2056.
* INCLUDES30.0OHMSFAULTRESISTANCE
SSUMES0 OHMS FAULTRESISTANCE
A*
OQ 1-
m 3
0
I-H
APPENDIX B
- 89 - Page 14 of 21
The basic transformer model was originated during the 1960's and 1970's
in the development of transformer load management systems for electrical
utilities. 1/
Figure B.5 is a simplified diagram of the basic model and Printout B.5
provides a summary of the Model. The electrical characteristics of the trans-
former (high and low side) are represented by a single impedance (resistance
R and reactance X). The load on the transformer and the no load losses (iron
losses) are imposed on the impedance to determine the load losses (copper
losses).
The model has the capability to simulate single phase transformers, three
phase transformers, and banked transformers. No load and load losses as
well as "probable loss of life" can be determined for single phase, three
phase or mixed single/three phase loads.
A power transformer may have "Tap Changing Under Load" (TCUL) capabilities
which enables the transformer to provide power to the primary system at voltage
levels commensurate with load levels. In general, TCUL transformers provide
power within the range of +10% of nominal voltage (say 12,500 volts + 1,250
volts). Representing a TCUL power transformer requires the special variation
of the basic model shown in Figure B.6.
Regulator Models
1/ *Skim the Cream Off Distribution Costs*, electric Light & Power March,
1975, by W.G. Scott, Scott & Scott Consultants, Inc., St. Louis,
Missouri.
APPENDIXB
-90 - Page 15 of 21
Figure B.5
C ID
XTOTAL
Resistance I
Model Ii I
Model j Reactance
o Single Phase
o Three Phase ,
o Bank of I
Transformers
IQ.t
00
fh
Ho
F%V
APPENDIXB
- 92 - Pagel7 of 21
For example,let us assume this is a 12,500 volt primary system and we set
the regulatorat 12,500 volts on the load side.
If the source voltage is 11,900 volts, the tap changer would go to the
boost level of 5% and the load side voltage would be 11,900 +-(.05 x 11,900
595) - 12,495 volts.
If the sourcevoltage is greater than 12,500 volts, the regulator taps would
go to a buck positionat the level necessary to provide 12,500 on the load
side.
SecondarySystem Models
The most simple system consistsof a single servicedrop from the trans-
former to the consumer (Figure B.8 - (1)). Losses for such a system are
usually negligiblealthoughthey can be computedby the method described
herein.
I .
TOTAL
Variable I
Resistance I
acde l ~I Ii I
Model
o Single Phase I
o Three Phase Variable
o Bank of Reactance
Transformers
I~~~~~~ I
Figure B.7
REGULATOR DIAGRMI
Load
Side
,_9,
Tap Changer
+10%
The complex system in a dynamic growth situation can become a major source
of losses. This is caused by existing consumers increasing their usage and
the indiscriminate addition of new consumers to already loaded systems.
Secondary systems are modeled for the computer using a variation of the
primary system models shown in Figure B.2. The distribution transformer
becomes the substation and the secondaries become the line sections.
96 - APPENDIXB
Page 1 of 21
FigureB.8
Service drop
D.T. , , D.T.
OPEN\
I a' '
APPENDIX C
This section of the Appendix provides the details of the following four
scenarios which were investigated in this project:
Distribution Transformers
Secondary Systems
For esLchof the above, this section contains investment costs, configura-
tion of facilities, losses (kW and kWH), annual costs and present worth of
annual,costs where applicable.
The most pertinent results of the case studies have been presented in Chapter
V and summarized in the Summary and Conclusions. The details of the studies
presented in this section of the Appendix may be used to develop further
results and/or used as a guide to expand the studies into parallel areas.
The area served by the Padri feeder out of the Mano Chahal Substation in
the Bhikhiwind Subdividion of Punjab State, India was used in the primary
conductor loading studies. The loads served by this feeder as of mid-1978
were increased annually for 20 years in accordance with growth rates deter-
mined in a previous study (Rural Electrification Engineering Research Project).
APPENDIX C
-98- Page 2 of 27
TABLE C.1
1978 - - 1.92 -
A digital model (see Appendix B) of the feeder was used to compute voltages,
loading, losses and fault currents. Printouts C.1 and C.2 are examples of the
type of analysis used in the study.
The system was modified and/or increased to meet four levels of maximum con-
ductor loading -- 100%, 75% 50% and 25%.
Table C.2 is a tabulation of the basic primary line costs used to calculate
the cost of improvements.
TABLE C.2
3 Phase, 3 Conductor
13 MM2 $4,500
20 MM2 $5,400
2
25 M $6,450
30 MM2 $6,900
48 MM2 $9,300
Reconductor
To 30 MM2 $4,500
To 48 MM2 $6,600
The system changes shown in Table C.1 were priced out using the costs of
Table C.2 and the present worth of these costs for the 20 years were
derived using the economic models discussed in Appendix A. Table C.3
Provides a summary of the results.
PRINTOUT C.1
PROGRA11
DALVOL
WORLDBANKLOSSSTUDY
FEEDER 6 PADRI-FEE1DER-6
VOLTAGE
=' 11.00KV-LINE TO LINE
SECT END LGTH PHIASECOND --- LOADIN SECTION …------LOAD THRIUSECTION--- VOLTAGE(PERCENT) LOSSES
- -
NODE 1(11R CONF SIZE COHN KU KVAR AMPS CUST COND KU I(VAR AIPS CUST SECI ACCULEVEL KU K(VAR
KVA Z DRO DROP
SUBSTATION
TOTALS 630. 472. 100.0
-486 450 0.40- ABC 481*1 00-- -0. 0- 0 .0 0.0- 21.0- -630, 472. 41. -0.-'' 0;-
OI 0.1 -99.9 0.9- 0.7
487 451 0.01 ABC 481111 100.0 63, 47, 4. 0.0 21.0 629. 471. 41. 0. 0.0 0.2 99.8 0.0 0.0
488 452 1.30 ABC 4011 0.0 0. 0. 0 00 1.9 566. 424. 37. 0. 0.4 0.6 99.4 2.4 1.9
489 453 0.01 ABC 48111 100.0 63. 47. 4. 0.0 18.9- 564. 422.- 37. 0. 0.0 0.6 99.4 0.0 0.0
-
490' 454 0 40 "ABC--48K1 -0.0 0;O0 0. 0.0 16a.81- SOt;-&-375. 33c 0; 0 i1t0.7 *.99#3--' O0.6'-0.5
491 455 0.60 ABC 13111 50.0 31. 23. 2. 0.40 3.0 31. 23, 2, 0. 0.0 0.7 99.3 0.0 0.0
492 456 0.20 ABC 48101 0,0 0. 0. 0. 0.0 15,7 469. 351, 31. 0. 0.1 0.8 99.2 0.3 0.2 -
-493 457 0.80 ABC 13101 50.0 31. 23. 2. 0.0 3.0 31, 23, 2. 0. 0.0 0.8 99.2 0.0 o0.
494 458 0. 40 - ABC-- 3011 '0;0- 0.- 0.-0.-. 19.5-- 438..28 29.- 0i, Oil-~~9,~. -0.4
495 459 0.80 ABC 13111 50.0 31, 23. 2. 0.0 3.0 31. 23, 2. 0. 0.0 0.9 99.1 0.0 0.0
496 460 0,10 ABC 30111 0.0 0. 0. 0. 0.0 18,1 406. 304. 27. 0. 0.0 0,9 99.1 0.1 0.1
497 461 0.01 ABC 30111 63.0 39. 30. 3. 0.0 18.1 406. 304. 27. 0. 0.0 0.9 99.1 0.0 0.0
498 462 0.10 'ABC --301111 0-0 -0--0-- -0O. -'. -16,4 366.4 274. -24, 0. -a; . 9.- . ,
499 463 0.01 ABC 30H1 100,0 63. 47. 4. 0.0 16.4 366. 274, 24. 0. 0,0 1.00 0.0 0.0
500 464 0,50 ABC 30HN9 0.0 0. 6. 0s 0.0 13.6 304. 227. 20. 0. 0,1 1.1 ;89.9 0.4 0.2
-501 465 0.70 ABC 13111 50.0 31. 23.- 2. 0.0 3.0 31. 23. 2. 0, 0.0 1.1 98.9 0,0._ol 0.0
02-466- 0.20-'ABC 30111 0.0 0. -0.Oo -00 1. 272. 18.
-04. 0.' 0-0 1- 98.9.0Ot 0.1
503 1003 1.20 ABC 13111 0.0 0, 0. 0. 0.0 0.0 0. 0. 0. 0. 0.0 1.1 90,9 0.0 0.0
510 474 0.40 ABC 30111 0.0 0. 0. 0. 0.0 12.2 272. 204. 18. 0, 0.1 1.2 98.8 0.3 0.1
511 475 0.50 ABC 13111 100.0 271. 203, 18. 0.0 25.8 272. 203. 18, 0. 0.2 1.4 98.6 0.8 0.2
END OFFEEDER.- . ......-.-.... .
oQ'
N4
PRINTOUT C.2
FAULTCURRENTLEVELS
FEEDER 6
SUBSTATIONVOLTAGE 11.00KY LINE TO LINE
FAULT DUTY BUS IHPEDANCES(IOHS)
RI 0.476--X1t--- .734 - - ---- - ---- --
, - --.
RO t 0,358 XO - 0.476
------- --
CUMULATIVE -----
NODE VEY -P? Ok
IITIVE-BED. - EOSEG. I;T0 S - S V ------- . - -
OQ
CA
- 102 - APPENDIX C
Page 6 of 27
TABLE C.3
CONDUCTORLOADING STUDY
Present Worth
Description of Costs ($)
The loss at peak for the various maximum conductor loading levels are shown
in Table C.4 for selected years. These losses at peak (kW) for each year were
converted to peak, should and off-peak demands plus peak, shoulder and off-
peak energy losses. This was accomplished with a computer program which pro-
vided the data in the form of Printout C.3. The demand and energy losses were
then priced out and present worthed by one of the economic analysis models
described in Appendix A (see Printout C.4).
The results of the conductor loading study are summarized in Table C.5.
TABLEC.4
0 V
-4
PKC SH O.P. PK 51H OeP.
LOSSFACTORSFOR YEAR 1 OF STUDY WINTER 0.62 0.40 0.33 SUMMER 0.50 0.32 0.26
HOURS 905. 1810. 1629. 920. 1840. 1656.
OIFFIRSTANNUALPEA"
PROPORTION 0.83 0.79 0.74 1.00 0.95 0.89
LOSSFACTORSFOR YEAR 2 OF STUDY WINTER 0,62 0.40 0,33 SUMhER 0.50 0632 0.26
HOURS 905. 1810. 1629. 920. 1840. 1656.
OF FIRSTANNUALPEK..0.
PROPORTION 0.84 0,7 ._1.06-1.01 0.94-
Nt ~~~~~~~~~103849.2
120W.1 7149.t 0? 10. .
DEMANDLOSSES(KW) 185 16.6 14.6 27:0 24.3 21,2
LOSSFACTORSFOR YEAR 3 OF STUDY MINTER 0.62 0.40 0.33 SUNMER 0.50 0,32 0.26
HOURS 905, 1810. 1629. 920. 1840. 1656.
Of FIRSTANAPAK..
PROPORTION 094 .8 0.3 - A2-107 1.00-
FACTORS
LOAD' 77.98 65.65 63.09 69.15 58.21 55.94
ENERGYLOSSES 12307.21.4291.29184.0 14624.016960.010912.0
DEMANDLOSSES(KW) 21.9 19.7 17.3 32.0 28.8 25.2
LOSSFACTORSFOR YEAR 4 OF STUDY MINTER 0.62 0.40 0.33 SUMMHER 0.50 0.32 0.26
HOUiRS 905. 1810. 162?, 920. 1840. 1656.
OF FIRST-ANNUAL-PEAK
PROPORTION .9 094 08V11 1.13 _ 1.06-
LOADFACTORS 77.98 65.65 63.09 69.15 58.21 55.94
ENERGYLOSSES 15304.010864.011480.0 18280.021200.013640.0
DEMANDLOSSES(KU) 27.4 24.6 21.6 40.0 36.0 31.4
LOSSFACTORSFOR YEAR 5 OF STUDY MINTER 0.62 0.40 0.33 SUMMER 0.50 0.32 0.26
HiOURS 905. 1010, 1629. 920. 1840. 1656.
eROPORTIONOF FIR5TANNUALPEAK_- 1,03 1.00 0.94 -- 1,26 1.20 .. 1.12
LOADFACTORS 77.98 65.65 63.09 69.15 58.21 55.94
ENERGYLOSSES 18268.521213.513632.5 21707.525175.016197,5
DEHANDLOSSES(KU) 32.6 29,3 25.7 47.5 42.8 37.3
LOSSFACTORSFOR YEAR 6 OF STUDY MINTER 0.62 0,40 0.33 SUMMER 0650 0.32 0.26
HOtURS 905. 1gl0. 162?. 920, 1840. 1656.
PROPORTION PEAK._-
OF FIRST_ANNUAL 1.12._ __099 __---
-i, _ .- _ Ia34_- 1.27 _-1.19.
LOADFACTORS 77 98 65.65 163.09 69.15 50.21 55.94
ENERGYLOS ES 2192M. 25456.21659.0 26049.030210.019437.0
DEMANDLOSSES(KU) 39.1 35.1 30.8 57.0 51.3 44.8
LOSSFACTORSFOR YEAR 7 OF STUDY MINTER 0.62 0.40 0.33 SUMMER 0.50 0.32 0.26
hiOURS 905. 1010. 1629. 920. 1840. 1656.
A2
PROPORTIONOF FIRST ANNUAL-PEAK..
LOADFACTORS
ENERGYLOSSES
.1 '" 03
7):9'861:619 '61.09
--
26422.030681.419716.9
- - - - A: fs :
'319 1AI
2 5 .24
31395.936411.023426.7 0
DEMANDLOSSES(KU) 47.1 42.3 37,1 68.7 61.8B 54.0 0V
N'
PRINTOUT C.3
PRINTOUT C.4
o3
APPENDIXC
Page 10 of 27
- 106 -
TABLE C.5
Capacitors were used to control power factor to 95% by adding them to the
conducitorstudy cases.
The locations for the capacitors on the feeders were determined with the aid
of the capacitor placement program described in Appendix B (see Printout B.7).
The cost for installing the capacitors are detailed in Table C.6.
TABLE C.6
(INSTALLED)
Correction of the power factor to approximately 95% will require the instal-
lation of capacitors as shown in Table C.7.
APPENDIX C
Page 12 of 27
- 108 -
TABLE C.7
CAPACITOR INSTALLATIONS
The results of the study are summarized in Table C.8 and shown graphically
in Figure C.2 of Chapter V.
APPENDIX C
- 109 - Page 13 of 27
TABLE C.8
VARIOUS MAXIMUMCONDUCTORLOADING
P.W. of
Maximum Capacitor P.W. Cost of Losses ($xlOOO) *
Conductor Annual Benefit
Loading Costs No With to
(%) ($xlOOO) Capacitor Capacitor Savings Cost Ratio
Distribution Transformers
No protection
TABLE C.9
TRANSFORMER CHARACTERISTICS
(12.47/7.2 kV PRIMARY)
No Load Total
kVA Loss Loss Price Annual
Rated % R %Z (kW) (kW) $ Cost*
* Annual costs based on 20 years life, capital recovery at 12% plus 1% O&M.
The transformer loading and analysis model described in Appendix B was used to
impose loadings from 50% to 250% on the transformers. Table C.10 is a summary
of the losses for the transformers being studied at various load levels.
APPENDIX C
- 111 - Page 15 of 27
TABLE C.10
DISTRIBUTION TRANSFORMER
VERSUS
The load losses are also shown graphically in Figure C.1 (Two Pages).
These graphs do show the major differences in load losses between various
sizes. Table C.11 is a comparison of losses for a 10 kW demand.
Figure C.1 (1 of 2)
3. a
2.0
U) .F
cn
(0
i-
0
kVA /2
1.0 F1~~~~~~~~~~~~~~~
O kVA
0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
0 10 20 30 40
l)emand (kW)
12.0
Figure C,1 (2 of 2)
8.0
En 6020 kVA I-
01 /100 kVA
4.0
2.0
0~5
2-0 kV/,,t1
0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Demand (kW)
APPENDIX C
- 114 - Page 18 of 27
TABLE C.11
The energy losses are derived from the following equations on the assumption
that the Annual Loss Factor is 30%.
Energy Loss = kW No Load x 8760 hours + kW Load Loss x 8760 hours x .30
The energy loss for the 5 kVA transformer of Table C.9 would be
Energy Loss = (0.045 x 8760) + (0.572 x 8760 x .3) - 394 + 1503 - 1897 kWH
The losses for the 10 and 25 kVA transformers were derived in a similar
manner and shown in Table C.12.
- 115 - APPENDIX C
Page 19 of 27
TABLE C.12
SERVING
ENERGY LOSSES
SIZE DEMAND NO LOAD LOAD TOTAL
(kVA) (kW) (kWH) (kWH) (kWH)
- $219
The above procedure was used to derive the costs of Table C.13.
- 116 - APPENDIX C
Page 20 of 27
TABLE C.13
SERVING
25 53 46 99 98 197 71.4
The 5 kVA has the thermal capability to serve a 10 kW load under average
loading conditions and many utilities are electing to do so. However, at
the assumed level of costs for losses, a 10 kVA transformer can serve the
10 kW load at 70% of the annual costs of the 5 kVA transformer and a 25 kVA
is certainly a feasible selection if growth is expected.
The above process was used to derive the data in Table C.5 and the graphs of
Figures C.4 and C.5.
The results have been based on a small segment of the many variables
associated with distribution transformers. They are not conclusive but
they certainly point out the need to explore further.
APPENDIX C
- 117 - Page 21 of 27
Secondary Systems
The maLjordifferences between the two concepts are: the centralized systems
transport power to the consumer over low voltage (240/416 volts) secondary
lines whereas, the Decentralized system transports the power directly to the
consumer or central load centers at high voltage (11,000 volts).
A computer model was developed for each of the centralized systems and
the systems were analyzed as to voltage, loading and losses.
n DISTIRBUTIONTRANSFORMER
( LOADS(KVA)
CONSUMER
SECONDARYSYSTEM (240/416 VOLTS)
'A0
'a~~~~~~~~~~~~~~~~~~~~~~~~~~~0
~- C-)
FtigureC.3
SMALL DISTIRBUTIONTRANSFORMERS(KVA)
G) CONSUMERLOADS(KVA) 3
SECONDARYSYSTEM(240/416 VOLTS)
. ' ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
.~~~~~~~~~
0~~~~~~~~~~~~~~~~~~~~
.
. \\~~~~~~~~~~~~~~~~~~~~~~~~~~
\~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~1
__
APPENDIX C
- 120 - Page 24 of 27
TABLE C.14
SECONDARY SYSTEMS
The basic costs used in study consist of the primary costs detailed
in Table C.2, the installed transformer costs of Table C.15 and the
secondary costs of Table C.16.
APPENDIX C
- 121 - Page 25 of 27
TABLE C.15
TABLE C.16
US$/kM
Items Labor Materials Other Total
Three One
Phase Wires Neutral Wire
TABLE C.17
60 CENTRALIZEDSECONDARY
SYSTEMS
VERSUS
SECONDARY
60 DECENTRALIZED SYSTEMS
Difference
DeCentralized
Minus
Item Centralized Decentralized Centralized
Transformer Statistics
Annual Costs
Investment plus O&M $110,130 $116,827 $ 6,697
Cost of Losses at:
$130/kW, $0.01/kWH $48,256 $10,167 ($38,089)
$250/kW, $0.034/kWH $104,904 $22,236 ($82,668)
APPENDIX D
Peak Demand
Loading EquivalentHours
Average Demand
Load Factor
Load Duration
* Loss Factor
Table D.1 and Figure D.1 show the hourly loads for a selectedpeak day where
the PeaLkDemand occurredduring the hour from 7 p.m. to 8 p.m.
TABLE D.1
PEAK DAY
MORNING AFTERNOON/EVENING
HOUR HOUR
DEMAND DEMAND
FROM TO KILOWATTS FROM TO KILOWATTS
12 AM 1 AM 10 12 PM 1 PM 13
1 AM 2 AM 8 1 PM 2 PM 15
2 AM 3 AM 6 2 PM 3 PM 16
3 AM 4 AM 7 3 PM 4 PM 19
4 AM 5 AM 8 4 PM 5 PM 21
5 AM 6 AM 9 5 PM 6 PM 24
6 AM 7 M 10 6 PM 7 PM 27
7 AM 8 AM 12 7 PM 8 PM 30
8 AM 9 AM 15 8 PM 9 PM 28
9 AM 10 AM 14 9 PM 10 PM 23
10 AM 11 AM 13 10 PM 11 PM 19
11 AM 12 PM 11 11 PM 12 AM 13
PEAK DAYS
25 - ~~~~~~~~~~~~~~~LOSSES
20
10
Load Duration is the relationship of demands and the duration of the demands
over a specified time period. In Table D.2, the hourly demands have been
sorted in descending order and the following computed:
The Load Duration parameters for the example have been plotted in Figure D.2
(Percent of Peak Versus Percent Duration).
Losses are a function of the squares of the load current (amps) which is
direcitlyrelated to the squares of the demands. The squares of the demands
for the example day are shown in Table D.2 and graphed in Figure D.3.
Loss E3quivalentHours are the number of hours of peak load which will produce
the same total losses as is produced by the actual loads over a specified
time period.
TABLE D.2
PEAK DAY
6849
100 2
90 -
80 -
LOADDURATIONGRAPH
PEAKDAY
70 -
60 -
50
40
30
0
20 -
10 -
0 10 20 30 40 50 60 70 80 90 100
PERCENT OF TIME
Figure D. 3
900
800 -
600-
A500-
400-
200r
100
2 4 6 8 10 NOON 2 4 6 8 10
APPENDIXD
- 132 - Page 9 of 19
Loss Factor is the percentageof time requiredby the peak load to produce
the same losses as producedby the actual loads over a specifiedtime
period. Loss Factor may be computedfrom the followingrelationships:
and
2
Loss Factor (%) - (HourlyDemand) x 100
(Peak Demand) x Hours
2
(1) Loss Factor = (15.46 kW) x 100 = 31.7%
(30 kW)2
An examinationof the loading for the ExampleDay will provide some basics
about the relationshipbetween energy and demand losses. In the developing
countries,technicalenergy losses of 15% are common so we will assume that
15% of the energy is lost enroute to delivery:
This energy loss may be divided among the 24 hourly loads in proportionto
the squaresof the demands (6th column of Table D.2). The peak hour would
become responsiblefor:
The Loss Factor is always less than or 'equalto the Load Factor because
losses are proportionalto the square of the loads. In the Example,the
Load Factor is 51.5% and the Loss Factor is 31.7%.
If hourly loads are known, the loss factor may be calculated as follows:
However, hourly loads are rarely available so one must depend upon the
probable relationship between Load Factors and Loss Factors as determined
from studies.
For Load Type A, the demand at any time is either at 100% or 0% full load.
The Load Factor for Load Type A can vary from 0.0% to 100.0%. The Loss
Factor for Load type A is always equal to the Load Factor.
For Load Type B, the load is constant for 23 hours (from 0% to 100% of Full
Load) and 100% of full load for the 24th hour. The Load Factor will vary
from a low of 4.17% (when the constant portion is 0.0%) to a high of 100%.
The Loss Factor equals the Load Factor at the low end (4.17%) and at the
high end (100.0%). Between these values, the Loss Factors and Load
Factors have the relationships shwon in Figure D.5 and Table D.3.
- 135 - APPENDIX D
Page 12 of 19
Fi&ure D.4
LOADINGEXTREES
100 -
75V
LOAD TYPE A DEMAND
IS 100%
so0 1OR 5 0.%
25
5 10 15 20 24
HOURS
75 __
LOAD TYPE B
50
25-
CONSTANT DEMANDFOR 23 HOURS
(MAY VARY FROM 0% TO 100.0%
5 10 15 20 24
HOURS
- 136 - APPENDIX D
Page 13 of 19
Figure D.5
100
to~~8 0.
cJn
0U
q
E. I-/
* TYPE
/ B
<: g t ~~~~~TYPE
A //L
5n = ~
LOADING
X40 ~ LADIN B
TYPE
20 i / / ~~~~~~LOADINIG
20
0 20 40 60 80 100
% LOAD FACTOR
APPENDIX_D
Page 14 of 19
- 137 -
TABLE D.3
For all practical purposes, Type A Loading and Type B Loading represent the
two extremes in the relationship between Load Factors and Loss Factors.
For all practical purposes, the Maximum demand loss at peak is associated with
Type B Loading (constant demand for all hours but one which is the peak
demand). A computer model was developed for Loading Type B based on the
following:
Peak - 100.0
100
80
60 F
DISTRIBUTION-
$60 q ~~~~FEEDER/
LOAD TYPE A/
40-
DISTRIBUTION
TRANSFORMER
20 LOAD TYPE B
0~
0 20 40 60 80 100
% LOAD FACR
- 140 - APPENDIX D
Page 17 of 19
The Type B Loading model was used to derive the data detailed in Table D.4
and the graphs of Figure D.7 for a 25 hour loading cycle and an 8760 hour
loading cycle.
Table D.4 or the graphs of Figure D.7 may be used to approximate the per-
cent demand loss at peak when the load factor and energy loss are known.
For the,Example Load (Exhibit D.1), the Load Factor is 51.5% and the
energy loss is 15%. The 15% loss curve of Figure D.7 indicates that the
the maximum peak loss would be 28% and we know that the minimum is 15%.
An average value of (15 + 28)/2 21.5% could be used for studies (The
calculated value was 24.3%).
APPENDIX D
Page 18 of 19
- 141 -
TABLE D.4
TYPE B LOADING
100 -
24 HOUR
8760 HOURS
80
60
04
5 40
20
0 20 40 60 80 100
% LOAD FACTOR
APPENDIX E
Page 1 of 3
- 143-
BIBLIOGRAPHY
1. C.J. Baldwin, C.J. Hoffman, P.J. Jeynes; "A Further Look at Cost of
Losses", AIEE Transactions, Part III, Vol. 80, 1961.
Technical Analysis
11. J.H. Cronin, C.R. Murray, B.G. Seiling; "Transformer Losses and
their Effect on Design", Proceedings of the American Power
Conference, 1978.
14. C.J. Baldwin, C.H. Hoffman, P.H. Jeynes; "A Further Look at Cost
of Losses", Presented AIEE Fall General Meeting, October 15-20, 1961.
15. D.I.H. Sun, S. Abe, R.R. Shoults, M.S. Chen, P. Eichenberger, D. Farris;
"Calculation of Energy Losses in a Distribution System", Presented at
the IEEE PES Summer Meeting, July 15-20, 1979.
APPENDIX E
Page 3 of 3
- 14+5-
16. N.E. Chang; "System Data Plus Computer Cuts Power Losses", Electric
Light and Power, August, 1970.
25. J.F. Calvert, T.W. Sze; "A New Approach to Loss Minimization in
Electric Power Systems", Presented at AIEE Fall General Meeting,
October 7-11, 1957.