You are on page 1of 3

ID Task Task Name Duration Start Finish Predecessors

Resource Names Cost


28 Dec '20 04 Jan '21
Mode S S M T W T F
0 TFSA 60 days Mon 04/01/21 Fri 26/03/21 $65,333.33
1 Review CRA 2.5 days Mon 04/01/21 Wed 06/01/21 Tester,Business $2,800.00 Tester,Business
Regulation Analyst
2 Define Requirements
3.33 days Wed 06/01/21 Mon 11/01/21 1 Business Analyst,Tester $3,733.33
3 Analyze Current 5 days Wed 06/01/21 Wed 13/01/21 1 Systems Analyst $3,600.00
System
4 Design a Solution 24 days Wed 13/01/21 Tue 16/02/21 2,3 Solution Designer $26,880.00 Solu
5 Build a Solution 15 days Tue 16/02/21 Tue 09/03/21 4 Developer,Tester $16,800.00
6 Perform Technical 2.5 days Tue 09/03/21 Thu 11/03/21 5 Tester,Developer $2,800.00
Testing
7 Demo the Solution 1 day Fri 12/03/21 Fri 12/03/21 6 Developer,Tester $1,120.00
8 Perform User 3 days Mon 15/03/21 Wed 17/03/21 7 Tester,Developer $3,360.00
Acceptance
9 Testing
Implement the 5 days Thu 18/03/21 Wed 24/03/21 8 Tester $2,000.00
Solution
10 Close the Release 2 days Thu 25/03/21 Fri 26/03/21 9 Scrum Master $2,240.00

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: TFSA
Summary Manual Summary Rollup Progress
Date: Tue 07/12/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
1 11 Jan '21 18 Jan '21 25 Jan '21 01 Feb '21 08 Feb '21 15 Feb '21
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Tester,Business Analyst

Business Analyst,Tester
Systems Analyst

Solution Desi

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: TFSA
Summary Manual Summary Rollup Progress
Date: Tue 07/12/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
Feb '21 22 Feb '21 01 Mar '21 08 Mar '21 15 Mar '21 22 Mar '21 29 Mar '21
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Solution Designer
Developer,Tester
Tester,Developer

Developer,Tester
Tester,Developer

Tester

Scrum Master

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: TFSA
Summary Manual Summary Rollup Progress
Date: Tue 07/12/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3

You might also like