Calculation of Weighted N-values for OHR at Shyamnagar

Borehole-1
Layer
DEPTH N-value
Thickness

1.5 1.5 2
3 1.5 4
4.5 1.5 4
6 1.5 4
7.5 1.5 5
9 1.5 6
10.5 1.5 4
12 1.5 2
13.5 1.5 3
15 1.5 3
16.5 1.5 4
18 1.5 13
19.5 1.5 22
21 1.5 24
22.5 1.5 24
24 1.5 27
25.5 1.5 30
27 1.5 49
28.5 1.5 54
30 1.5 62

Weighted
N 17

This calculation of N-value is done assuming the pile termination level is


at 30m depth from Ground Level
Calculation of Weighted N-values for OHR at Shyamnagar

Borehole-2
Layer
DEPTH N-value
Thickness

1.5 1.5 4
3 1.5 3
4.5 1.5 2
6 1.5 4
7.5 1.5 5
9 1.5 6
10.5 1.5 5
12 1.5 5
13.5 1.5 5
15 1.5 4
16.5 1.5 11.5
18 1.5 17
19.5 1.5 25
21 1.5 26
22.5 1.5 34
24 1.5 34
25.5 1.5 36
27 1.5 53
28.5 1.5 58
30 1.5 64

Weighted
N 20

This calculation of N-value is done assuming the pile termination level is


at 30m depth from Ground Level