Date 29/10/2019 Page 1

LIMHSS Software Upgrade to R19P e r u O & M


Last
Ver. 1.0 Method29/10/2019
Update of Procedure (MOP)

LIMHSS01 Software Upgrade to R19

[Huawei CS] [Reviewer’s Name] [Approver’s Name]


Designed by Reviewed by Approved by
O&M Manager/VP

Confidential
Date 29/10/2019 Page 2

LIMHSS Software Upgrade to R19P e r u O & M


Last
Ver. 1.0 Method29/10/2019
Update of Procedure (MOP)

General Information

Confidential
Date 29/10/2019 Page 3

LIMHSS Software Upgrade to R19P e r u O & M


Last
Ver. 1.0 Method29/10/2019
Update of Procedure (MOP)

Proposed Date: [09/10/2019]

Proposed Time: [Peru GMT-5 (22:00hrs ~ 07:00hrs)]

Backup Date/Time: [16/10/2019] [Peru GMT-5 (22:00hrs ~ 07:00hrs)]

Activity Description: LIMHSS01 Software Upgrade to R19

Activity Purpose: Upgrade to V900R019C10SPC200

Network Type: 2G 3G LTE WiMax Other

Network Domains RAN (Radio Access Network) Transport/Transmission PS Core


Involved:
CS Core DATACOM ISP VAS Sites Other:______________

Involved NEs: Source Version: V900R010C10SPC120


Target Version: V900R019C10SPC200

LIMHSS01, AQPHSS01

Involved Services: Voice Service

Involved Markets and -


Providers:

Nextel NOC Sites & TX Voice Dispatch / ISP / HPPTT / CWAN


Monitoring
VAS Datacomm

RPN Activity Type: - RPN (Risk Priority


Number):

Location for execution: []

Bridge (if needed): -

Onsite Support Required: Yes No: Places (if yes): [NA]

Facilities: Remote Support Required: Yes: No:

Partners Support Required: Yes: No: Contact Info: [Huawei/POC Name]

Confidential
Date 29/10/2019 Page 4

LIMHSS Software Upgrade to R19P e r u O & M


Last
Ver. 1.0 Method29/10/2019
Update of Procedure (MOP)

Network Impact: Yes: No:

Impact Duration: 10 Seconds

Notification to Yes: No: Date: [DD-MM-YYYY]


OSIPTEL:

Notification to Yes: No: Date: [DD-MM-YYYY]


Providers:

Impacted NEs: LIMHSS01 (parcial)

Impacted Services: Voice (parcial)

Impacted Markets and -


Providers:

Ticket or Case -
reference (if any):

Comments and -
remarks:

MOP Scope
and Detailed Software Upgrade to LIMHSS01 R19
Description

Pre-conditions
None
in the Network

General
Expected Successful Software Upgrade to R19
Results

Pre – Works Attach test matrix and necessary checklist:

Admin user of PGW WEB and LMT Client

Confidential
Date 29/10/2019 Page 5

LIMHSS Software Upgrade to R19P e r u O & M


Last
Ver. 1.0 Method29/10/2019
Update of Procedure (MOP)

MOP Activities Attach Hour by Hour Activity:


Description
Reference Reference
Step Description Owner
Start Time End Time
Backing UP Data (BKP DB, BKP SYS) and
1 Huawei 19:00 22:00
export template
2 Configure software parameters Huawei 22:00 22:15
3 Run Pre Upgrade Check and VTS Huawei 22:15 23:00
4 Backing UP Data Huawei 23:00 00:30
5 Backup logs from PGW WEB LMT Huawei 00:30 01:00
6 Stop the Provisioning System Huawei-entel 01:00 01:30
Maintenance Tool for Backup in Redundancy
7 Huawei 01:00 01:30
USCDB
8 Upgrading Single SDB Huawei 01:30 04:00
9 Upgrade Verification Huawei 04:00 05:20
10 Install license in HSS Huawei 05:20 05:30
Command Huawei /
11 Restore Provisioning System 05:30 06:00
Configuration Entel

Attach the scripts and commands sequence:

Item Item description Remarks


1 Backing UP Data (BKP  Backups in LIMHSS
DB, BKP SYS) and export
template
1. Backup DB and
SYS.docx
 Backup the export template by File Transfer.

Confidential
Date 29/10/2019 Page 6

LIMHSS Software Upgrade to R19P e r u O & M


Last
Ver. 1.0 Method29/10/2019
Update of Procedure (MOP)

2 Configure software  Configure UPGRADESTATUS and


parameters REDUNDANCYSWITCH software
parameters.

Please do it in two sites, don’t change them


back until standby site finish upgrade

2. Configuring the
USCDB upgrade function and Redundancy Function.docx

UIM:
 Backing Up the Value of FORBIDCRCERR

3. Backing Up the
Value of FORBIDCRCERR.docx
 Changing the Length of the Intra-UIM DRU
Data Replication Queue

4. Changing the
Length of the Intra-UIM DRU.docx
3 Run Pre Upgrade Check  Follow the guide for pre-upgrade checks in
and VTS LIMHSS01 and AQPHSS01

5. Conducting Health
Checks.docx
 Perform VTS health check
4 Backing UP Data  Follow the guide for backups before upgrade:

6. Backing Up
Data.docx
 Backup alarms and one week performance
result of HSS/ENS/EIR/UIM/CGP/USCDB
from OMU WEBUI
 Backup LST MAPSERV/LST MAPCONF
 Backup LST EMAPCONF/LST EMAPSERV
5 Backup logs from PGW  Backup PGW WEB LMT
WEB LMT 1. Log in to the PGW Web LMT.
2. Run the LST MAPSERV command.
3. Run the LST MAPCONF command.
4. Save the output of step 2 and step 3 on the local
PC.
6 Stop the Provisioning Confirm with customer that provisioning system is
System stopped.
Run LST LOG in PGW Web interface and check that
there are no commands received from provisioning
system.
IF NOT THEN MUST UNPLUG PGW
INTERFACE CABLES:
Disconnect Card3 Lan0 of SLOT 1 and SLOT 3
SUBRACK 0 for PGW interface boards.

Confidential
Date 29/10/2019 Page 7

LIMHSS Software Upgrade to R19P e r u O & M


Last
Ver. 1.0 Method29/10/2019
Update of Procedure (MOP)

7 Maintenance Tool for Before upgrade execution need to perform data


Backup in Redundancy maintenance tool:
USCDB

12. Backing Up the


FDB of the Redundancy USCDB.docx
8 Upgrading Single SDB Follow the guide for Single SDB upgrade:
Remember to do upgrade for
CGP/USCDB/HSS/EIR/ENS/UIM together

7. Upgrade
Implementation.docx
9 Install license in HSS Install new license for new version in HSS

Install new license file for


USCDB/HSS/ENS/EIR/UIM, run the commands in
their window of OMU LMT
DSP ESN
ACT LICENSE

Install license.docx

10 Restore Provisioning Contact Provisioning System to restore


System Provisioning to LIMHSS01
IF STOPS PROVISIONING WAS
UNPLUGGING CABLES, RECONNECT CABLES IN
PGW INTERFACE
Connect again Card3 Lan0 of SLOT 1 and SLOT 3
SUBRACK 0 for PGW interface boards.

Validation Attach test matrix and necessary validations:

Refer to the following attachment for verification procedure:


No. Operation Operation Method Owner
Item
1 Monitor main Boards CPU KPI: Huawei
KPIs • Mean CPU Load
• Send Routing for SM
• MAP Operation Success Rate
• Check IMEI Success Rate
• Number of Successful ULA Messages
• Successful Response Rate of ULR Messages
• Successful Response Porcentage of SNR Messages
• Number of Successful SNA Messages
• Successful Response Percentage of PUR Messages
• Number of Successful PUA Messages
• Successul Response Percentage of UDR Messages
• Number of Successful UDA Messages
• Number of IP packets Successfully Received

Confidential
Date 29/10/2019 Page 8

LIMHSS Software Upgrade to R19P e r u O & M


Last
Ver. 1.0 Method29/10/2019
Update of Procedure (MOP)

• Number of IP packets Successfully Sent

Traces Validate Service by capturing Subscriber 2G/3G/4G


2 Huawei
Message Trace (basic service)

Attach the GO / NO GO Criteria and escalation levels:

Attach the scripts and commands sequence:

A rollback is required when errors occur during the upgrade, the upgrade is canceled

Go / No Go while the upgrade is in progress, or services become abnormal after the upgrade is
Criteria complete.
DO NOT PERFORM A SWITCHOVER

Roll Back
Procedure Refer to following steps for rollback process:
Task Remarks
Rollback Operation and  Refer to the following guide:
Validation

9. Upgrade
Rollback.docx

If new license was installed, //LIMHSS01


Rollback license DSP ESN:;
ACT LICENSE: FN="
LIC20190726EPWT60_LIMHSS01.dat ", LT=BOTH;

LIC20190726EPWT6
0_LIMHSS01.dat

Roles & The roles and responsibilities should be detailed below and some
Responsibilitie additional information can be gathered including providers:
s
Contact
Area /
Contact name Number / E-mail
Responsability
UFMI
Jenry Luis +51 970569968 CS Core Engineer Jenry.luis.wx@huawei.com
Cristian iriarte +51 946190777 CS Core Leader Cristian.iriarte.wx@huawei.com
Alfonzo
+51 942984457 AMS Technical Director Alfonzo.carhuayo@huawei.com
Carhauyo
Additional
Information:

Confidential
Date 29/10/2019 Page 9

LIMHSS Software Upgrade to R19P e r u O & M


Last
Ver. 1.0 Method29/10/2019
Update of Procedure (MOP)

Next-day KPI Report:


11am, 2pm, 5pm