11-Des-15

Coal Getting (Tonase - Trucking) Coal Getting (Tonase - Timbangan) Coal (Tonase) Waste (bcm) Total
Pit/ROM
B C1 C2 B C1 C2 Hauling Soil Mud Clay (Bcm)
PHL Timur - - - - - - - - - - -
PHL Barat - - - - - - - 864,00 - 1.198,13 2.062,13
General/Mining Service - - - - - - - - - - -
StockROM - - - - - - - - - - -
Disposal/Waste Dump - - - - 0- - - - - - -
Sub Total 0,00 0,00 0,00 0,00 0,00 0,00 0,00 864,00 0,00 1.198,13 2.062,13
Ket :
Rain and Slippery 5,40 Jam

Produksi Aktual Desember 2015 Variance Target Target Produksi Desember 2015

MTD Coal Getting (Trucking) - Tonase (7.700) 0,0% Coal Getting (Trucking) 7.700 Tonase

MTD Coal Getting (Timbangan) - Tonase (7.700) 0,0% Coal Getting (Timbangan) 7.700 Tonase

MTD Waste 16.914 bcm (29.586) 36,4% Waste 46.500 bcm

MTD Coal Hauling 331,92 Tonase (7.368) 4,3% Coal Hauling 7.700 Tonase
MTD Coal in StockROM 2.593,02 Tonase