SCHEDULE FABRICATION MOBILE CHOCOLATE TANK CAP.

1000 LTR ( 8 UNITS )


ID TaskTask Name Duration Start Finish
Mode Qtr 1, 2022 Qtr 2, 2022 Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1 Mobile Chocolate Tank Cap. 268 days Tue 01/02/22 Thu 09/02/23
1000 Ltr (8 Units)

2 Start 1 day Tue 01/02/22 Tue 01/02/22

3 PO Receive 1 day Wed 02/02/22 Wed 02/02/22

4 Engineering Desing 30 days Thu 03/02/22 Wed 16/03/22

5 Drawing Approval 7 days Tue 08/03/22 Wed 16/03/22

6 Fabrication Work 140 days Thu 17/03/22 Wed 28/09/22

7 FAT 30 days Thu 22/09/22 Wed 02/11/22

8 Delivery & Installation 30 days Thu 03/11/22 Wed 14/12/22

9 Test Run 5 days Thu 02/02/23 Wed 08/02/23

10 Finish 1 day Thu 09/02/23 Thu 09/02/23

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 06/12/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1