Professional Documents
Culture Documents
1. Types of foundations-
1. Shallow foundation
o Individual footing or isolated footing
o Combined footing
o Strip foundation
o Raft or mat foundation
2. Deep Foundation
o Pile foundation
o Drilled Shafts or caissons
The shape of individual footing is square or rectangle and is used when loads from the
structure is carried by the columns. Size is calculated based on the load on the column
and the safe bearing capacity of soil.
Rectangular isolated footing is selected when the foundation experiences moments due to
the eccentricity of loads or due to horizontal forces.
For example, consider a column with a vertical load of 200 kN and a safe bearing
capacity of 100 kN/m then the area of the footing required will be 200/100 = 2m . So, for
2 2
a square footing, the length and width of the footing will be 1.414 m x 1.414 m.
2. Combined Footing
Combined footing is constructed when two or more columns are close enough and their
isolated footings overlap each other. It is a combination of isolated footings, but their
structural design differs.
The shape of this footing is a rectangle and is used when loads from the structure is
carried by the columns.
Spread footings
Spread footings and wall footings are used for individual columns, walls and bridge piers
where the bearing soil layer is within 3m (10 feet) from the ground surface. Soil bearing
capacity must be sufficient to support the weight of the structure over the base area of the
structure.
These should not be used on soils where there is any possibility of a ground flow of water
above bearing layer of soil which may result in scour or liquefaction.
The use of mat foundation is for columns and walls foundations where the loads from the
structure on columns and walls are very high. This is used to prevent differential
settlement of individual footings, thus designed as a single mat (or combined footing) of
all the load-bearing elements of the structure.
It is suitable for expansive soils whose bearing capacity is less for the suitability of
spread footings and wall footings. Raft foundation is economical when one-half area of
the structure is covered with individual footings and wall footings are provided.
These foundations should not be used where the groundwater table is above the bearing
surface of the soil. The use of foundation in such conditions may lead to scour and
liquefaction.
Pile Foundation
Pile foundations are used to transfer heavy loads of structures through columns to hard
soil strata which is much below ground level where shallow foundations such as spread
footings and mat footings cannot be used. This is also used to prevent uplift of the
structure due to lateral loads such as earthquake and wind forces.
Pile foundation resists the loads from the structure by skin friction and by end bearing.
The use of pile foundations also prevents differential settlement of foundations.
Drilled shafts can transfer column loads larger than pile foundations. It is used where the
depth of hard strata below ground level is located within 10m to 100m (25 feet to 300
feet).
Drilled shafts or caisson foundation is not suitable when deep deposits of soft clays and
loose, water-bearing granular soils exist. It is also not suitable for soils where caving
formations are difficult to stabilize, soils made up of boulders, artesian aquifer exists.
3. Properties of soil
4. Bearing capacities and its test
bearing capacity is the capacity of soil to support the loads applied to the ground.
The bearing capacity of soil is the maximum average contact pressure between the
foundation and the soil which should not produce shear failure in the soil.
250,450 KN/mm2
5. What is RMC: Ready-mix concrete, or RMC as it is also known, refers to concrete that is
specifically manufactured for customers' construction projects, and supplied to the
customer on site as a single product. It is a mixture of Portland or other cements, water
and aggregates: sand, gravel, or crushed stone.
Factor Being
Ready-Mix Concrete Site-Mixed Concrete
Considered
Recommended
High-rise structures Low-rise structures
Application
Requires a suitable access for the concrete Requires space for material
Space
mixer truck. storage and batch mixers.
10. CPM: The critical path method (CPM), also known as critical path analysis
(CPA), is a scheduling procedure that uses a network diagram to depict a
project and the sequences of tasks required to complete it, which are known as
paths. Once the paths are defined, the duration of each path is calculated by an
algorithm to identify the critical path, which determines the total duration of the
project.
11. PERT: Technique to assist in project planning when historical cost and time data are not
available or reliable. Usually associated with R&D and new product development projects where
the uncertainty is great
12. Moment in a beam: bending of the beam along the length of beam
a bending moment is the reaction induced in a structural element when an external force or
moment is applied to the element, causing the element to bend. The most common or
simplest structural element subjected to bending moments is the beam
13. Cantilever: beam connected from one side and hanging from other.
14. Slack/float: time a project can be delayed without delaying the total projects or delaying
subsequent activities
15. Test of concrete: Slump test for workability
16. Characteristic strength: The characteristic strength is defined as the strength of
the concrete below which not more than 5% of the test results are expected to fall.
17. Cantilever beam and its cross section:
Retarding admixtures, which slow the setting rate of concrete, are used to counteract the
accelerating effect of hot weather on concrete setting. High temperatures often cause an
increased rate of hardening which makes placing and finishing difficult. Retarders keep
concrete workable during placement and delay the initial set of concrete. Most retarders
also function as water reducers and may entrain some air in concrete.
Corrosion-inhibiting admixtures fall into the specialty admixture category and are used to
slow corrosion of reinforcing steel in concrete. Corrosion inhibitors can be used as a
defensive strategy for concrete structures, such as marine facilities, highway bridges,
and parking garages, that will be exposed to high concentrations of chloride. Other
specialty admixtures include shrinkage-reducing admixtures and alkali-silica reactivity
inhibitors. The shrinkage reducers are used to control drying shrinkage and minimize
cracking, while ASR inhibitors control durability problems associated with alkali-silica
reactivity.
38. Development length: A development length can be defined as the amount of
reinforcement(bar) length needed to be embedded or projected into the column to
establish the desired bond strength between the concrete and steel (or any other two
types of material).
39. Flanges and rectangle beam
The web resists shear forces, while the flanges resist most of the bending moment
experienced by the beam. The Euler–Bernoulli beam equation shows that the I-shaped
section is a very efficient form for carrying both bending and shear loads in the plane of
the web.