Professional Documents
Culture Documents
Additional Requirements:
(a) Minimum Stone Size > 1.25x Maximum Spacing between wires.
Maximum
Gabion
Velocity
Thickness (Ft)
(ft/sec.)
1/2 6
3/4 11
1 14
Special Sizing Notes:
(a) When sizing gabions, both lower and upper bounds on stone size should be established using Table 11.1 and Tab
blished using Table 11.1 and Table 11.2.
INPUT
Flow Depth (Yo)= 6.12 ft
V100 at Abutment= 5.54 ft/sec
Width of abutment footing = 10 ft
Width of abutment(W) = 8 ft
Thickness of abut footing (X)= 1 ft
Design Scour depth at abutment (y)= 5.5 ft
Angle of Repose (ф)= 46.5 deg
Clear opening (Abut-to-Abut) = 30 ft
DESIGN
Critical Velocity= 5.54 ft/sec (Avg velocity for 100 yr, V100)
Extent of Gabions:
16 ft Governs.
DESIGN
Critical Velocity= 1.38 ft/sec (Avg velocity for 100 yr, V100)
Extent of Gabions:
26.8 ft Governs.
002 40 3.5
003 40 4
0016 39 2.25
0028 27 3
0033 37 3
0053 45 2
00665 28 3
02465 20 4
05165 36 3.5
05465 50 2.25
Notes on Excavation depth (Taken from "Flood Scour for Bridges and Highways" b
Excacation: The top layer of gabion/riprap should be at least 6 in below a riverbed
Exception:
(a) If computed scour depth is high, it may not be feasible to provide riprap depth eq
permissible. In such situations, the thickness of riprap may be reduced to 0.5y, wher
if effective, monitoring is done.
(b) If the excavation depth is not excessive and doesnot cause instability of footing,
not be reduced and will be based on calculated velocity. If the design depth d is grea
footing or bedrock is not available within the depth d, then an alternative counterme
Abutment Details V100 at Abut Scour Depth (ft) Angle of Repose
Soil type
(ft/sec) (deg)
Thickness (ft) Contraction Total
2.5 1.38 2.94 13.17 SP 30
2.5
2.75
2.25
not be feasible to provide riprap depth equal to full scour depth. Deep excavations adjacent to spread footings are not
ss of riprap may be reduced to 0.5y, where y=maximum scour depth, provided d is not less than 3 ft, a filter layer is used, and
and doesnot cause instability of footing, a higher value of d between 0.5y and y may be used. However, the size of stone will
ated velocity. If the design depth d is greater than the available depth beween the river bed elevation and the bottom of the
he depth d, then an alternative countermeasure should be considered.