ID Task Task Name Duration Start Finish

August 2021 September 2021 October 2021 November 2021 December 2021 January 2022
Mode 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21
1 GEDUNG KELAS
2 PEKERJAAN BETON DAN PONDASI
3 PEKERJAAN PONDASI
4 Pengukuran/Uitzet Bouwplank 2 days Wed 01/09/21Thu 02/09/21
5 Pek. Galian Tanah 3 days Fri 03/09/21 Mon 06/09/21
6 Urugan Kembali 1 day Wed 22/09/21Thu 23/09/21
7 Urugan Pasir bawah Pondasi 1 day Tue 07/09/21Wed 08/09/21
8 Lantai Kerja 2 days Wed 08/09/21Fri 10/09/21
9 STRUKTUR LT. 1
10 Pondasi Foot Plate (100 x 100 x 30 ) cm 4 days Fri 10/09/21 Tue 14/09/21
11 Sloof 20 x 30 3 days Wed 15/09/21Fri 17/09/21
12 Kolom 25 x 25 - 4 m (K1) 21 7 days Sat 18/09/21 Sat 25/09/21
13 Kolom 20 x 20 - 3 m (K2) 2 7 days Sat 18/09/21 Sat 25/09/21
14 Kolom 15 x 15 - 3 m (KP1) 4 7 days Sat 18/09/21 Sat 25/09/21
15 Balok 20 x 30 (B1) 10 days Sat 25/09/21 Wed 06/10/21
16 Balok 15 X 25 (B2) 10 days Sat 25/09/21 Wed 06/10/21
17 Balok 15 X 10 (BL) 10 days Sat 25/09/21 Wed 06/10/21
18 STRUKTUR LT. 2
19 Plat Beton t. 12 cm 3 days Sun 03/10/21Wed 06/10/21
20 Kolom 20 x 20 (K2) 18 7 days Wed 06/10/21Wed 13/10/21
21 Kolom 15 x 20 (KP2) 5 7 days Wed 06/10/21Wed 13/10/21
22 Kolom 15 x 15 (KP1) 8 7 days Wed 06/10/21Wed 13/10/21
23 Balok 15 X 25 (B2) 10 days Thu 14/10/21Mon 25/10/21
24 Balok 15 x 10 (BL) 10 days Thu 14/10/21Mon 25/10/21
25 Ring Balok 15 x 20 10 days Mon 01/11/21Thu 11/11/21
26 STRUKTUR LT. 3
27 Plat Beton t. 12 cm 3 days Tue 26/10/21Thu 28/10/21
28 Kolom 15 x 15 (KP1) 9 3 days Fri 29/10/21 Mon 01/11/21
29 Ring Balok 15 X 15 3 days Tue 09/11/21Thu 11/11/21
30 Plat Beton t. 10 cm 1 day Fri 12/11/21 Fri 12/11/21
31 Tangga Minimalis (T.1) 3 days Wed 06/10/21Sat 09/10/21
32 Tangga Minimalis (T.2) 3 days Tue 26/10/21Thu 28/10/21
33 PEKERJAAN KUDA-KUDA DAN ATAP
34 Pek. Rangka Atap Baja Ringan 2 days Mon 06/12/21Tue 07/12/21
35 Pasangan Atap Genteng Metal Pasir 1 day Wed 08/12/21Wed 08/12/21
36 Pasangan Nok Genteng Metal Pasir 1 day Wed 08/12/21Wed 08/12/21
37 Listplank Woodplank 1 day Thu 09/12/21Thu 09/12/21
38 PEKERJAAN LANTAI DAN DINDING 61 days Fri 29/10/21 Sun 02/01/22
39 Pemasangan 1 m² Dinding Hebel 10 pakai Drymix PM 380 7 days Mon 08/11/21Mon 15/11/21
40 Pemasangan 1 m² Dinding Partisi 10 days Fri 26/11/21 Mon 06/12/21
41 Pek. Plesteran + Acian 1 m2 dengan DRYMIX/ MU dan setara 10 days Mon 15/11/21Thu 25/11/21

Task Project Summary Manual Task Start-only Deadline

Project: TIME SCHEDULE GD.KE Split Inactive Task Duration-only Finish-only Progress
Date: Tue 03/08/21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish
August 2021 September 2021 October 2021 November 2021 December 2021 January 2022
Mode 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21
42 Pasang Kolom Praktis 11 x 11 cm 2 days Fri 29/10/21 Sun 31/10/21
43 Pek. Lantai keramik 40 x 40 cm 10 days Thu 09/12/21Sun 19/12/21
44 Pek. Rabatan Keliling t.7cm 1 day Sun 26/12/21Mon 27/12/21
45 Pek. Lantai keramik 20 x 20 cm WC 1 day Sat 18/12/21 Sun 19/12/21
46 Pek. Realing tangga (besi galvanis 2") 4 days Wed 29/12/21Sun 02/01/22
47 PEKERJAAN PINTU DAN JENDELA
48 Kusen Alumunium 4" + Pintu Teakwood 9 mm Lapis HPL + Aksesoriesnya (P1) 2 days Sat 18/12/21 Mon 20/12/21
49 Kusen Alumunium 4" + Pintu Teakwood 9 mm Lapis HPL + Aksesoriesnya (P2) 2 days Thu 16/12/21Sat 18/12/21
50 Kusen Alumunium 4" + Pintu Teakwood 9 mm Lapis HPL + Aksesoriesnya (P3) 4 days Sun 12/12/21Thu 16/12/21
51 Kusen Alumunium 4" + Pintu Teakwood 9 mm Lapis HPL + Aksesoriesnya (P4) 1 day Wed 01/09/21Wed 01/09/21
52 Kusen Alumunium 4" + Pintu Teakwood 9 mm Lapis HPL + Aksesoriesnya (P5) 1 day Thu 23/12/21Fri 24/12/21
53 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J1) 4 days Fri 03/12/21 Wed 08/12/21
54 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J2) 4 days Wed 08/12/21Sun 12/12/21
55 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J3) 3 days Sun 12/12/21Wed 15/12/21
56 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J4) 2 days Thu 16/12/21Sat 18/12/21
57 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J5) 1 day Tue 14/12/21Wed 15/12/21
58 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J6) 3 days Wed 15/12/21Sat 18/12/21
59 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J7) 2 days Sat 18/12/21 Tue 21/12/21
60 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J8) 1 day Mon 20/12/21Tue 21/12/21
61 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J9) 2 days Tue 21/12/21Thu 23/12/21
62 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J10) 1 day Thu 23/12/21Fri 24/12/21
63 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J11) 2 days Fri 24/12/21 Sun 26/12/21
64 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J12) 2 days Sun 26/12/21Tue 28/12/21
65 Jendela Alumunium 4" + Kaca 5 mm Clear + Aksesories (J13) 1 day Wed 08/12/21Wed 08/12/21
66 Bovenlist Alumunium 4" + Kaca 5 mm Clear + Aksesories (BV) 1 day Wed 08/12/21Wed 08/12/21
67 Bovenlist Alumunium 4" + Kaca 5 mm Clear + Aksesories (BV2) 1 day Wed 08/12/21Wed 08/12/21
68 PEKERJAAN PLAFOND
69 Pek. Plafond Gypsum Board 9mm Rangka Hollow Galvanis 8 days Sun 12/12/21Mon 20/12/21
70 Pek. List Plafond Gypsum 10 cm 2 days Tue 21/12/21Wed 22/12/21
71 PEKERJAAN PENGECATAN
72 Cat dinding dalam ( ICI ) 6 days Tue 21/12/21Mon 27/12/21
73 Cat plafond setara ICI 4 days Thu 23/12/21Mon 27/12/21
74 Cat dinding luar dengan ( ICI Weathershield ) 5 days Tue 04/01/22Sun 09/01/22
75 Waterproofing Dak Beton 2 days Sat 13/11/21 Mon 15/11/21
76 PEKERJAAN LISTRIK
77 Pas. Instalasi Kabel 3x2,5 NYM + Pipa conduit 20mm 3 days Thu 09/12/21Sun 12/12/21
78 Pas. Instalasi Titik Stop Kontak 3x2,5 NYM 3 days Thu 09/12/21Sun 12/12/21
79 Pasang Saklar ganda 3 days Mon 15/11/21Thu 18/11/21
80 Pasang Saklar tunggal 3 days Mon 15/11/21Thu 18/11/21
81 Lampu Downligh 18 watt termasuk armatuer 3 days Mon 20/12/21Thu 23/12/21
82 Pemasangan MCB 1 phase 6 A 1 day Wed 08/12/21Wed 08/12/21

Task Project Summary Manual Task Start-only Deadline

Project: TIME SCHEDULE GD.KE Split Inactive Task Duration-only Finish-only Progress
Date: Tue 03/08/21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name Duration Start Finish
August 2021 September 2021 October 2021 November 2021 December 2021 January 2022
Mode 24 29 03 08 13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21
83 Pemasangan MCB 1 phase 10 A 1 day Wed 08/12/21Wed 08/12/21
84 Pemasangan Box MCB 2 Group 1 day Sat 08/01/22 Sun 09/01/22
85 Lampu Downligh 18 watt termasuk Kap Gantung 1 day Wed 22/12/21Thu 23/12/21
86 PEKERJAAN SANITARY
87 Closet jongkok standar setara TOTO 2 days Tue 07/12/21Thu 09/12/21
88 Floor drain 1 day Fri 10/12/21 Fri 10/12/21
89 Kran air 1/2" 1 day Tue 30/11/21Wed 01/12/21
90 Kitchen Sink 7 days Thu 06/01/22Thu 13/01/22
91 Pembuatan 1 m' Gravel U 20 CM 3 days Sun 26/12/21Wed 29/12/21
92 Pek. Plesteran Gravel 2 days Wed 29/12/21Fri 31/12/21
93 Pek. Acian Gravel 3 days Fri 31/12/21 Mon 03/01/22
94 Tangki air kapasitas 1m3 1 day Sat 06/11/21 Mon 08/11/21
95 Instalasi Pipa PVC 3/4" 14 days Thu 14/10/21Fri 29/10/21
96 Instalasi Pipa PVC 3" 14 days Thu 14/10/21Fri 29/10/21
97 Instalasi Pipa PVC 4" 14 days Thu 14/10/21Fri 29/10/21
98 Stop Kran 1" 1 day Sat 06/11/21 Mon 08/11/21
99 Water Moor 1 day Sat 06/11/21 Mon 08/11/21
100 Pintu PVC KM/WC 2 days Tue 11/01/22Thu 13/01/22
101 Meja Keramik 7 days Thu 06/01/22Thu 13/01/22

Task Project Summary Manual Task Start-only Deadline

Project: TIME SCHEDULE GD.KE Split Inactive Task Duration-only Finish-only Progress
Date: Tue 03/08/21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone