DEEP
FOUNDATION
1
DEEP FOUNDATION
Deep Foundations are those
in which the depth of the foundation
is very large in comparison to its
width.
2
DEEP FOUNDATION
Most common forms of construction pertaining to deep
foundations are:
Pile Foundation (more commonly used in building
construction)
Cofferdams
Caisson or Well Foundation
3
Pile Foundation
4
5
Necessity of Pile
Foundation
• If the soil near the surface do not have sufficient
bearing capacity to support the structural loads
• If the estimated settlement of the soil exceeds
tolerable limits
• To increase factor of safety of heavy load
structures
6
Load Carrying Construction Materials
Mechanism Method
• Pre-Cast • Concrete
• End
Bearing • Cast-in-situ • Steel
• Friction • Timber
• Composite
7
Load carrying mechanism of
piles
Friction End Bearing
Pile Pile 8
Pre Cast Piles
o Displacement Pile
o Piles of any size
are made in
advance and then
used at the site
9
Non-displacement pile in
which a hole of the specified
diameter is bored to the required
depth.
Cast with concrete of specified
strength after the reinforcement
is placed in the hole.
10
11
Is the first material used in piling work
12
Can be driven in very
long lengths
Liable to corrosion
above the soil line
More expensive than
timber or concrete
13
Composite
Piles
Combinations of
materials are used.
Most common
materials are steel
and concrete.
14
Pi le Cap
o It is a thick concrete mat that rests on
driven concrete or timber piles.
o Provides stability to the
foundation in soft and unstable
ground
o It distributes the load of the building into
the piles.
15
Pile Cap
Pile cap for Pile cap Pile cap
two piles for three for four
piles piles
16
Pile Caps
17
Bangladesh University of Engineering and
Technology 18
A destructive natural
problem is:
Excavation
Problems: 1.Rain water make
the soft soil clay
and it is easy to
collapse.
2.Rain water can
stay in the
excavated area.
polythen
e
19
Draining the extra water
manually
Leveler Excess water
20
Vibrator touching
reinforcement
21
Pile Cap Rebar
22
Excess water in
concrete
Excess water
23
For part by part work , there
arise
Joining
effect:
Construction
Joint
Water stopper
24
Construction
Problems:
Piles were not on the same line A displaced pile is creating problems
for reinforcement work
25
Assignment
Compare Between Pre-
Cast and Cast in Situ Piles
26
Bangladesh University of Engineering and Technology
27