Example
Operation representation
Op1
Offshift calendars
Time
Op1 ??
Resource A
T0
Let’s assume that, on Resource A, we selected 3 criteria (GROUPING RULE LIST) which are Attribute 1, Attribute 2 and Attribute 3:
Criteria (GROUPING RULE LIST) Identical? (GROUPING RULE MATCH) Weight (GROUPING RULE WEIGHT)
Product Attribute 1 Yes 50
Product Attribute 2 No 20
Product Attribute 3 Yes 30
The look ahead window is 5 days (GROUPING RULE WINDOW). The priority is 15 days (GROUPING RULE DELAY). The reference time
is the earliest due date (GROUPING RULE REFERENCE TIME).
Op1 characteristics:
Product Attribute 1 = “Yellow”
Product Attribute 2 = 2
Product Attribute 3 = “Aluminium”