DETAILED ESTIMATE

S. Quantity
no Description of work Nos L(ft) B(ft) D(ft) (Cft ) Unit Rate Amount
I GROUND FLOOR:
1 Earthwork excavation
in loose soil within the
initial lead and lift.
(1) For lift 1 4.00 4.00 10.00 160.00
160 Cft 46.00 7360
2 Flooring concrete in
P.C.C. 1:5:10 using
40mm HBS.
(1) For floor 1 25.00 27.00 0.50 337.50
337.50 Cft 135.00 45563

3
Disposal of excavated
earth outside site 160.00 Cft 9.00 1440
4 Concrete ring for lift
Floor 1 10.00 6000

5 Floor finishing with


a)Vitrified tiles
1 25.00 27.00 675.00
675.00 Sft 90.00 60750

6
Glass partion wall with
aluminium frame
1 22.00 10.00 220.00
220.00 Sft 280.00 61600

GROUND FLOOR TOTAL 182713