Professional Documents
Culture Documents
3. Consideration is the legal term given to the benefits in exchange between the
contracting parties. No contract can be formed if one party is not bound to provide
consideration to the other party.
The rules of consideration are:
1) Past consideration is treated as no consideration, that means contractor cannot
enforce(執行) the original promise if the act was performed before the promise was
made.
2) Consideration must be sufficient but not need to be fair
3) To carry out either public duty or an existing contractual obligation does not
provide consideration.
4) Only the parties to the contract who can be given consideration and will be able
to enforce a contract.
4. Quantum Meruit is the duty imposed by law to pay a reasonable sum for goods
or services received.
a. Where no price is fixed.
-If the contractor does work, he is entitled to be paid a reasonable sim for his
labour and materials supplied.
-If contract term for payment is for the whole work, completion may be made a
condition before payment.
-In absent of clear workings, contractor is entitled periodically to demand payment
on account of the value of work he has done.
b. Failed negotiations
-If work is carried out while negotiations on the terms of the contract are proceeding,
but never reached upon essential terms, contractor is entitled to be paid a
reasonable sum for the work carried out.
c. Prevention of completion by employer
-If wrongful acts by the employer prevent completion, the contractor can claim a
quantum merit payment.
d. Acceptance of part performance
-If the contractor can prove, by inferred or implied agreement, a new contract to pay
for the work done, he may recover the money for the work be has completed on the
basis of the new contract.
e. Wavier of a condition
-It is always open to a party to waive a condition, which is inserted for his benefit.
f. Work outside the contract
-Contractor, who does work outside the contract at the client’s request, is entitled to
be paid a reasonable sum for the additional work.
Employer’s Obligations
(i) Payment
(ii) Give possession of the site
(iii) State extent and time of possession
(iv) Appoint an architect and quantity surveyor
(v) Supply instructions
(vi) Must not interfere with progress
Duty of:
Architect
Design, advise, supervise construction, and certify payments due to main contractor.
Act as an agent for the client under terms of engagement which constitutes an
independent sub-contractor contractual relationship.
Quantity Surveyor (QS)
(i) Pre-Contract Stage :
Advise on project costs, prepare tender documents and tender report.
(ii) Post Contract Stage
Prepare certificates of payment and variation accounts and calculate adjustments to
the contract sum due to fluctuations.
Foreman-in-Charge
Receive architect’s instructions on behalf of the main contractor on site.
8. Variations
1. Most building contracts are entire contracts which mean no obligation to carry
out variations or to pay for variations.
2. Can introduce a variation clause to modify doctrine of entirely.
3. Give client right to require variations and provide rules governing adjustment of
contract sum.
4. Where the valuation relates to the carrying out of:
4.1 Additional or substituted work which can be properly valued by measurement;
4.2 Work which is the subject of Provisional Quantities or Provisional items; or
4.3 Work involved in the expenditure of Provisional Sums.
5. The work shall be measured and shall be valued in accordance with following
rules;
5.1 Where the work is the same as or similar in character to and is carried out under
the same or similar conditions to work priced in the Contract Bills, and the variation
does not substantially change the quantity of the work, the rates in the Contract Bills
for that work shall determine the Valuation;
5.2 Where the work is the same as or similar in character to work priced in the
Contract Bills but is not carried out under the same or similar conditions, or the
Variation substantially changes the quantity of the work, the rate in the Contract Bills
for that work shall determine the Valuation but with a fair adjustment for the
difference in conditions or quantity; and
5.4 Where the work is not the same as or similar in character to any work priced in
the Contract Bills the work shall be valued at fair rates.
9. Retention
1. Objective: Secure main contractor ‘s obligation to complete the work and make
good defects.
2. Client holds retention money as trustee for the main contractor but without
obligation to invest.
3. Normally is 10% of the certified value of contractor work done, limit 5% of the
contract sum.
Client is permitted to draw from the fund to reimburse himself for:
1. Work executed by third party where main contractor did not compile with a valid
instruction.
2. Issuing of Certificate of Practical Completion, one moiety of the retention fund is
released.
3. The rest being released after the issue of the Certificate of Making Good Defects.
Example: Driver have a duty to follow the rules of the road and ride the passenger to
his destination. Passenger have duty to pay the fee.