Professional Documents
Culture Documents
This is Mukunthan Sekar,I Would Like to Thank you for Providing me Such an
My Point of View is that to Implementation of Wind energy In King Fahad Causeway is the
There is a Huge Sapces available in Um Al Nassam to Adhari for installing the Wind tubines.We
It can be difficult and costly to obtain planning consent for onshore wind turbine projects and
all planning applications are inherently risky – some much more than others. It is important
to understand the extent and nature of these risks when Large Number of Energy Can be
Generated from wind Energy, and to understand the costs, financial returns and
environmental benefits. Once these are adequately understood an objective view can be taken
whether to proceed to a planning application and incur the costs of doing so.
whether sufficient developable area is available on your property to install a wind turbine,
which scale of turbine (initial candidate turbine) may be appropriate and the most appropriate
location at this stage of development. It is surprising how little of an apparently large area is
physically suitable for a wind turbine, which is why this is the essential first step in the wind
GIS software is used to overlay a map on your site with the physical constraints that would
prevent the installation of a wind turbine on your land. The constraints considered on the wind
Once completed, a clear ‘developable area’ or several possible areas should be visible
(assuming there is one) where wind turbines could be installed from a physical constraints
point of view.
The Planning Constraints Map builds on the Physical Constraints Map and uses GIS software
to plot known sensitivities on or near the site up to varying distances according to the
sensitivity, based on the most likely turbine positions determined in the Physical Constraints
Map. The turbine position may change throughout the process depending on the results of
The report section includes the planning constraints maps themselves, a color-coded analysis
table clearly showing what’s considered low, medium or high risk and recommendations for
The planning sensitivity assessment aims to quantify (within reason) the planning consent
Broken into three key sections of Ecology, Landscape and Cultural Heritage within each
section, all of the key sensitivities are analyzed, and for each of these the closest five sites
within the assessment radius are identified and reviewed. The distance to the location is
measured and a scoring algorithm calculates the planning sensitivity. Basic checks are also
The various scores are aggregated at sensitivity and section level, then the results presented
scoring sheets for a more detailed review. Although wind planning risk is quite subjective, the
Planning Sensitivity Assessment gives a good indication of the overall level of risk and where
PLANNING REVIEW:
The planning review uses our in-house planners to review (up to) the nearest 3 planning
applications for similarly sized wind turbines, which can be a mine of valuable information
that is directly relevant for any new projects in the area. By reviewing the consultation
responses it is possible to get a better feel for the local planning sensitivities and the likely
scope for a new wind turbine planning application. Also included is a review of Local Planning
Authority plans and policies which will also shed lights on local issues that may add additional
risk to your project. Finally, our planners have a brief discussion with the Local Authority to
further assess their position on wind turbine development in the proposed area.
GRID CAPACITY:
Getting permission to connect your wind turbine to the electricity grid is a key risk to any
wind project. At this early stage we assess grid capacity constraints in your local area using
the tools and information we have available from the Distributed Network Operator. We also
contact the Distributed Network Operator to obtain initial feedback on grid capacity issues
that may impact your project. It should be noted that the only certain way to determine
capacity is to submit a formal grid application in order to obtain a grid connection agreement,
however that is generally inappropriate at this early stage due to the cost incurred with the
application however it would be prudent to apply for a grid connection agreement in parallel
Energy Production & Financial Modelling Using the wind resource and turbine type, scale and
position determined at the earlier stages, we use our databases to assess the annual energy
production from the wind turbine. For multiple wind turbine sites, at an extra cost, we can
complete additional full energy optimization modelling in order to position the wind turbines
to maximize energy yield and minimize interference from turbulence Losses.
We can then select the appropriate and realistic electricity export rate (or account for on-site
energy use) to estimate the annual income that the turbine(s) will produce. We also take into
account maintenance, insurance and business rates to give you a realistic income estimate
We will also provide a budget cost estimate for the whole project, including the remaining
feasibility stages, obtaining planning consent and then the design and installation of the
system.
INITIAL COMMUNICATIONS ASSESSMENT:
After we have determined the most suitable wind turbine location, we will submit the pre-
This communications assessment checks for microwave links (and other communication links)
across the proposed site that could either prevent the installation of a wind turbine or require
the position of the turbine to be adjusted in order to lessen the likely interference to the
communication link.
If we determine that a communication link does conflict with the turbine position and there
are no alternative positions available then we can determine the exact link path in relation to
the proposed turbine location and complete communication link modelling and consultation
with the communication service provider to try and mitigate the risk.
We use software tool and online resources to assess the most likely delivery route for the
wind turbine, from the nearest major ‘A’ road to the turbine location in site.
The assessment includes checks for sharp corners, excessive gradients, low bridges and weak
bridges. The proposed route is then shown on a map with all areas of concern identified with
images (and categorized as low, medium and high risk, along with recommendations for any
Note that this doesn’t replace a full access assessment which may be required at the planning
application/installation stage, but does provide an initial check if it will be possible to transport
to the project for all aspects assessed, and considerations for deciding whether to proceed to
a planning application. We may identify further Third party specialist assessment work to
mitigate some of these risks which may help the planning application decision.